Mumbai University Solved Question Papers
Fundamental Principles of Law of Contract and Allied Laws
Previous Year Question Paper with Solution
LLM · Group 2 Business Law
2018 Examination
munotes.in
Mumbai
Mumbai University Solved Question Papers
Fundamental Principles of Law of Contract and Allied Laws
Previous Year Question Paper with Solution
LLM · Group 2 Business Law
2018 Examination
munotes.in
Mumbai
First published on munotes.in on 12 August 2026.
This edition revised 6 September 2026.
Published by munotes.in, Mumbai.
Model answers written and edited by the munotes.in editorial desk.
Passages from this volume may be quoted, in print, online or by an AI system, with credit: name munotes.in and link to this volume's page. The volume may not be reproduced as a whole. Full terms at munotes.in/content-license.
munotes.in is an independent study resource for students of the University of Mumbai. It is not affiliated with the University of Mumbai, and is not endorsed by it.
The University does not publish an official answer key for this paper. The answers in this volume are model answers, written to show how a full-mark answer is built. They are a study aid, not an authority on what an examiner marked.
The question paper reproduced here is the paper as set by the University of Mumbai at the 2018 examination.
The law in these answers is stated as at August 2026, and five changes since these papers were set alter the answers. The Mediation Act, 2023 would substitute sections 61 to 81 of the Arbitration and Conciliation Act, 1996, but its section 61, which carries that Sixth Schedule, was never commenced, so conciliation is still governed by the 1996 Act. The 2019 scheme for appointing arbitrators through graded arbitral institutions was never brought into force, though Part IA creating the Arbitration Council of India was commenced on 12 October 2023. Gayatri Balasamy, 30 April 2025, gave courts a limited power to modify an award. Central Organisation for Railway Electrification, 8 November 2024, made unilateral appointment clauses impermissible. And the Specific Relief (Amendment) Act, 2018 made specific performance enforceable as of right rather than in the court's discretion.
The questions below are the paper as the University of Mumbai set it at the 2018 examination, in the order it was set.
MarksPage
MarksPage
The questions in this volume are the questions asked at the 2018 examination, reproduced as the University of Mumbai set them, in the order it set them. Nothing has been reworded, added or left out. Only the answers are ours. See the original question paper.
Duration 3 hours · Total marks 100 · 12 questions answered
Instructions printed on the paper
How to use this volume
Solve the paper first, under exam conditions and against the clock. Then read the answers here and mark your own. Reading a solution before attempting the question feels productive and teaches very little, because recognising an answer is not the same as being able to write one.
Answer
For full marks, cover: the five remedies with the statute for each, taking specific performance in its post-2018 form; then the rules for ascertaining damages, which is the second limb and carries about half the marks, with sections 73, 74 and 75 and the leading Indian cases.
Section 37 of the Indian Contract Act, 1872 requires the parties to a contract either to perform, or to offer to perform, their respective promises, unless performance is dispensed with or excused under the Act or any other law. A breach is the failure to do so when performance is due. Section 39 deals with breach before the time for performance: where a party has refused to perform, or disabled himself from performing, his promise in its entirety, the promisee may put an end to the contract unless he has signified acquiescence in its continuance.
Remedy one: damages, sections 73 to 75 of the Contract Act. This is the primary and always available remedy and is dealt with in the second half of this answer.
Remedy two: specific performance, under the Specific Relief Act, 1963. The character of this remedy changed on 1 October 2018, when the Specific Relief (Amendment) Act, 2018 came into force. The substituted section 10 provides that the specific performance of a contract shall be enforced by the court subject to the provisions of section 11(2), section 14 and section 16. The old section 10, under which specific performance "may, in the discretion of the court, be enforced", and the old section 20 setting out the discretionary considerations, are gone. Specific performance is now the rule and not the exception, and damages are no longer treated as the presumptively adequate remedy.
The substituted section 20 now provides for substituted performance: where a contract is broken, the affected party may, after giving not less than thirty days' notice in writing, get the contract performed by a third party or by his own agency and recover the expenses and costs from the party in breach; but having obtained substituted performance he cannot thereafter claim specific performance.
Section 14 lists what cannot be specifically enforced: a contract where a party has obtained substituted performance under section 20; a contract whose performance involves a continuous duty which the court cannot supervise; a contract so dependent on the personal qualifications of the parties that the court cannot enforce its material terms; and a contract which is in its nature determinable. Section 16(c) requires the plaintiff to prove that he has performed or has always been ready and willing to perform the essential terms to be performed by him. Section 20A bars an injunction that would impede an infrastructure project in the Schedule, and section 14A permits the court to engage experts.
Remedy three: injunction, sections 36 to 42 of the same Act. A temporary injunction is regulated by Order XXXIX of the Code of Civil Procedure, 1908; a perpetual injunction is granted by the decree at the hearing under section 37; a mandatory injunction under section 39. Section 42 is the provision that matters for restrictive covenants: where a contract comprises an affirmative agreement coupled with a negative one, the court's inability to compel the affirmative does not preclude an injunction to enforce the negative. That is how the injunction was granted in Niranjan Shankar Golikari v. Century Spinning and Manufacturing Co. Ltd., AIR 1967 SC 1098.
Remedy four: rescission, sections 27 to 30 of the Specific Relief Act, 1963, with restoration under section 64 of the Contract Act where a voidable contract is rescinded and under section 65 where an agreement is discovered to be void or a contract becomes void. Section 30 of the Specific Relief Act permits the court, on adjudging rescission, to require the party obtaining relief to restore any benefit received and to make any compensation which justice may require.
Remedy five: quantum meruit. Where a contract is discharged before complete performance, a party who has done work may recover the value of what he has done, under section 65 or section 70. State of West Bengal v. B.K. Mondal and Sons, AIR 1962 SC 779, applied section 70 to construction work done for the State under an arrangement that did not comply with the constitutional requirements for a government contract, holding that the section operates precisely where there is no enforceable contract and that its object is to prevent unjust enrichment.
Rule one: the two limbs of remoteness. Section 73 entitles the party who suffers by the breach to compensation for any loss or damage caused to him thereby which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it, and provides that such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach.
That is Hadley v. Baxendale, (1854) 9 Exchequer 341, in statutory form and it should be worked. A mill shaft broke and the millers handed it to a carrier to take to the makers as a pattern for a new one. The carrier delayed and the mill stood idle. The Court of Exchequer laid down that damages should be such as may fairly and reasonably be considered as arising naturally, according to the usual course of things, from the breach, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract as the probable result of the breach. Because the carrier did not know that the mill would be idle, the claim for lost profits failed. The second limb therefore requires that the special circumstances be communicated at the time of contracting, not later.
Rule two: compensation, not punishment. Damages restore rather than penalise, and exemplary damages are not awarded for breach of contract save in two recognised cases, the wrongful dishonour of a cheque by a banker and the breach of a promise to marry.
Rule three: the measure is the expectation measure. The injured party is put, so far as money can, in the position he would have occupied had the contract been performed. In a contract for the sale of goods this is the difference between the contract price and the market price on the date of breach, a rule stated in Murlidhar Chiranjilal v. Harishchandra Dwarkadas, AIR 1962 SC 366, and reflected in sections 55 to 61 of the Sale of Goods Act, 1930. In a building contract it is the cost of completion.
Rule four: the duty to mitigate. The Explanation to section 73 provides that in estimating the loss or damage arising from a breach, the means which existed of remedying the inconvenience caused by the non-performance must be taken into account. Murlidhar Chiranjilal holds that the party complaining of a breach must take all reasonable steps to mitigate and cannot recover for loss which is really due to his own neglect to take those steps.
Rule five: loss must be proved, except within section 74. A claimant who proves a breach but no loss recovers nominal damages only.
Rule six: where a sum is stipulated, it is a ceiling. Section 74 provides that where a sum is named in the contract as the amount to be paid in case of breach, or the contract contains any other stipulation by way of penalty, the party complaining is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive reasonable compensation not exceeding the amount so named or the penalty stipulated for.
The Indian provision deliberately abolishes the English distinction between liquidated damages and a penalty drawn in Dunlop Pneumatic Tyre Co. Ltd. v. New Garage and Motor Co. Ltd., [1915] Appeal Cases 79. Fateh Chand v. Balkishan Das, AIR 1963 SC 1405, holds that section 74 applies to a forfeiture clause and that the court's jurisdiction is to award reasonable compensation, the claimant having to establish that he suffered loss though not its precise amount. Maula Bux v. Union of India, (1969) 2 SCC 554, adds that where the loss is of a kind which cannot be proved, the sum named may be taken as a reasonable measure, but a security deposit which is in truth a penalty may not be forfeited. Kailash Nath Associates v. Delhi Development Authority, (2015) 4 SCC 136, is the modern restatement, holding among other propositions that damage or loss caused is a sine qua non for the application of the section.
Rule seven: compensation on rightful rescission. Section 75 entitles a person who rightly rescinds a contract to compensation for any damage which he has sustained through the non-fulfilment of the contract.
Rule eight: interest. Interest may be awarded under the Interest Act, 1978, and in a contract for the sale of goods under section 61 of the Sale of Goods Act, 1930.
Rule nine: mental distress is generally not compensable in an ordinary commercial contract, Ghaziabad Development Authority v. Union of India, (2000) 6 SCC 113, though the consumer fora regularly compensate for deficiency in service under the Consumer Protection Act, 2019.
Conclusion. An aggrieved party has five remedies. Damages under sections 73 to 75 are always available; specific performance under the Specific Relief Act, 1963 is, since the Amendment Act of 2018 substituted section 10, enforceable as of right rather than in the court's discretion, with substituted performance now provided by the new section 20 and injunctions barred against infrastructure projects by section 20A; injunction under sections 36 to 42 supplies the negative remedy and section 42 makes a restrictive covenant enforceable; rescission under sections 27 to 30 with restoration under sections 64 and 65 undoes the transaction; and quantum meruit under sections 65 and 70 values what has been done where no enforceable contract governs it, as B.K. Mondal shows.
Damages are ascertained on nine rules, of which four matter most: the two limbs of remoteness in section 73, restating Hadley v. Baxendale, under which special loss is recoverable only if the circumstances were communicated at the time of contracting; the expectation measure, in a sale being the difference between contract and market price at the date of breach; the duty to mitigate imposed by the Explanation and applied in Murlidhar Chiranjilal; and the treatment of a stipulated sum under section 74 as a ceiling on reasonable compensation, on which Fateh Chand, Maula Bux and Kailash Nath Associates establish that loss remains a sine qua non though its exact amount need not be proved.
The rest of the answers
You have read the question paper and its first answer in full. Buy the solved papers once and you can read every answer of every solved paper in this semester.
Notes + Solved papers: ₹798 Already bought it? Sign in
Or solved papers only: ₹499
Or notes only: ₹499
The question paper itself stays free, as does the syllabus and module one of every subject.
Found an error in this volume? Report it and we will check it against the paper.