Questions asked in this paper
-
Q1 Attempt any three of the following: a5
- a. Define a project and list the key differences between software projects and other types of projects
- b. Analyze the role of stakeholders and the project charter in determining project success or failure. How do they influence project objectives?
- c. What is the relationship between software development and project development life
- d. Explain given terms: |. Payback period 2. Return on investment
- e. Explain the concept of Risk Evaluation in the context of Project Evaluation and Programme Management. Discuss the steps involved in identifying, assessing, and
- f. stepwise method framework of project planning
-
Q2 Attempt any three of the following: 15 marks
- a. Explain incremental delivery model with its advantages and disadvantages
- b. Describe the concept of software effort estimation and discuss its significance in the planning and successful execution of a software project
- c. Write a detailed note on staffing patterns
- d. Explain extreme programming and its core practices
- e. in detail the different Scrum ceremonies and explain how they help in planning, tracking, and reviewing work in Agile projects
- f. Explain Atern process model
-
Q3 Attempt any three of the following: 15 marks
- a. Describe the product based approach used for project planning
- b. Explain the framework for dealing with risk
- c. What is a forward pass in network planning model? Explain how it is used to determine the earliest start and finish times, with an example
- d. and explain Burma’s priority list
- e. What are the different rules followed for constructing Network model?
- f. Explain nature of resources and their scheduling
-
Q4 Attempt any three of the following: 15 marks
- a. Explain the importance of Gantt charts and slip charts in review process
- b. the software configuration management (SCM) process and explain the key activities involved in managing software versions and changes
- c. How is Earned Value Analysis used to evaluate a project’s performance against its planned schedule and budget?
- d. Define fixed-price contracts and discuss their features, advantages, and disadvantages in detail
- e. What are the common stress factors in software environments? Suggest strategies for stress management, health, and safety at the workplace
- f. Maslow’s hierarchy of needs
-
Q5 Attempt any three of the following: 15 marks
- a. Explain working in teams. What are the stages of development of a team?
- b. the different software quality models and explain their significance in assessing and improving software quality. >
- c. Discuss about dispersed teams with their advantages, disadvantage and challenges
- d. What kind of communication genre is preferred in each stage of project development? Explain in detail
- e. Explain different types of leadership styles
- f. Outline the steps involved in project closure, including financial closure and preparation of a project closeout report
Read from the scan above, so a character or two may differ. The scan is the original.
Something wrong on this page? Report it and we will check it against the scan.
BSc IT Sem 5 Paper Path
Use this paper as one timed BSc IT Sem 5 mock, then compare Advanced Web Programming, Artificial Intelligence, IoT, Linux, Network Security, and Software Project Management papers from nearby year sets.
Step: Open this BSc IT Sem 5 paper in the free viewer first.
Step: Compare the 2023-2024, 2022-2023, 2018-19, and ATKT sets for repeated subjects.
Step: Use the full BSc IT Sem 5 folder when you need more final-year IT practice.
Quick Help
Related Resources
Something wrong with this paper? Report it.