Mumbai University Solved Question Papers munotes.in
March 2026
BSc IT · Sem V
March 2026 - Software Project Development Examination
Previous Year Question Paper with Solution
munotes.in Mumbai
Mumbai University Solved Question Papers munotes.in
March 2026
BSc IT · Sem V
March 2026 - Software Project Development Examination
Previous Year Question Paper with Solution
munotes.in Mumbai
First published on munotes.in on 12 November 2026.
Published by munotes.in, Mumbai.
Model answers written and edited by the munotes.in editorial desk.
Passages from this volume may be quoted, in print, online or by an AI system, with credit: name munotes.in and link to this volume's page. The volume may not be reproduced as a whole. Full terms at munotes.in/content-license.
munotes.in is an independent study resource for students of the University of Mumbai. It is not affiliated with the University of Mumbai, and is not endorsed by it.
The University does not publish an official answer key for this paper. The answers in this volume are model answers, written to show how a full-mark answer is built. They are a study aid, not an authority on what an examiner marked.
The question paper reproduced here is the paper as set by the University of Mumbai at the March 2026 - Software Project Development examination.
The questions below are the paper as the University of Mumbai set it at the March 2026 - Software Project Development examination, in the order it was set.
MarksPage
MarksPage
MarksPage
The questions in this volume are the questions asked at the March 2026 - Software Project Development examination, reproduced as the University of Mumbai set them, in the order it set them. Nothing has been reworded, added or left out. Only the answers are ours. See the original question paper.
Duration 2½ hours · Total marks 75 · 30 questions answered
How to use this volume
Solve the paper first, under exam conditions and against the clock. Then read the answers here and mark your own. Reading a solution before attempting the question feels productive and teaches very little, because recognising an answer is not the same as being able to write one.
1.
Attempt any three of the following · 15 Marks
Answer
For full marks, cover: what ISO 12207 is, its four process groups, the development activities it names with what each produces, the management activities alongside them, how the activities fit the three stages of a project, and a conclusion.
ISO/IEC/IEEE 12207 is the international standard for software life cycle processes. It was first published in 1995. It defines the processes needed to develop and maintain software. It defines processes, not stages, so it does not force one life cycle model on a project.
The standard arranges its processes in four groups:
The technical processes are the software development activities. For a project manager they become the activities a plan must contain.
| Activity | What happens | What it produces |
|---|---|---|
| Requirements definition | find out what the stakeholders need and what the software must do | a requirements specification |
| Architecture and design definition | decide the structure, then the detail of each part | architecture and design documents |
| Implementation | write the code for each component | tested components |
| Integration | combine the components into a whole | an integrated system |
| Verification | check that the product meets its specification | test results |
| Transition | install the system in its operational environment and hand it over | an installed system, trained users |
| Activity | What happens | What it produces |
|---|---|---|
| Validation | confirm that the system meets the users' real needs in use | acceptance |
| Operation and maintenance | run the system, then correct and improve it | a supported system |
The 1995 edition grouped these under its development process. It listed requirements analysis, design, coding, integration, testing, installation and support for acceptance of the software.
The standard also names seven technical management processes. They are project planning, project assessment and control, decision management, risk management, configuration management, information management and quality assurance. These run beside the development activities from start to finish.
A project passes through three stages: the feasibility study, planning and project execution. The development activities happen in execution. Planning decides their order, effort and dates. Operation and maintenance usually continue after the project closes, so the plan must allow for the handover.
Conclusion. ISO 12207 recommends a full set of development activities, from requirements definition through design, implementation, integration, verification, transition and validation to operation and maintenance. Each activity produces a product that can be checked, and management processes control the work around them.
The rest of the answers
You have read the question paper and its first answer in full. Buy the solved papers once and you can read every answer of every solved paper in this semester.
Notes + practical solutions + solved papers: ₹798 Already bought it? Sign in
Or solved papers only: ₹499
Or notes + practical solutions: ₹499
The question paper itself stays free, and so does the syllabus.
What do you need?
Tap one.
The answers are on this page
You can read the first answer here. The box further down shows how to read all of them.
Read it here, any time
We keep checking and updating our papers and notes, and adding more. A saved copy would be an old version. Reading on munotes.in always gives you the latest one.
I paid, but I can't open it
Please type an email, or a 10-digit phone number.
Done
If we find your payment, we send a link to the email you paid with. Open it to read.
Check your email in 2 minutes. Also check Spam.
No email after 10 minutes?
Something else
Please write a little more, so we can help.
Your email app opens with this. You can add more there. We reply by email.
Found an error in this volume? Report it and we will check it against the paper.