BSc IT Sem V March 2026 Software Project Development Question Paper with Solutions

MU B.Sc. (Information Technology) student group Free to join

Mumbai University Solved Question Papers munotes.in

March 2026

BSc IT · Sem V

March 2026 - Software Project Development Examination

Previous Year Question Paper with Solution

munotes.in Mumbai

munotes.in

First published on munotes.in on 12 November 2026.

Published by munotes.in, Mumbai.

Model answers written and edited by the munotes.in editorial desk.

Passages from this volume may be quoted, in print, online or by an AI system, with credit: name munotes.in and link to this volume's page. The volume may not be reproduced as a whole. Full terms at munotes.in/content-license.

munotes.in is an independent study resource for students of the University of Mumbai. It is not affiliated with the University of Mumbai, and is not endorsed by it.

The University does not publish an official answer key for this paper. The answers in this volume are model answers, written to show how a full-mark answer is built. They are a study aid, not an authority on what an examiner marked.

The question paper reproduced here is the paper as set by the University of Mumbai at the March 2026 - Software Project Development examination.

munotes.in ii
munotes.in iii
munotes.in iv
munotes.in v

The Paper as Set

The questions in this volume are the questions asked at the March 2026 - Software Project Development examination, reproduced as the University of Mumbai set them, in the order it set them. Nothing has been reworded, added or left out. Only the answers are ours. See the original question paper.

Duration 2½ hours  ·  Total marks 75  ·  30 questions answered

How to use this volume

Solve the paper first, under exam conditions and against the clock. Then read the answers here and mark your own. Reading a solution before attempting the question feels productive and teaches very little, because recognising an answer is not the same as being able to write one.

munotes.in vi

SECTION I

1.

Attempt any three of the following · 15 Marks

munotes.in 1

a.What are the different software development activities recommended in ISO 12207.[5]

Answer

For full marks, cover: what ISO 12207 is, its four process groups, the development activities it names with what each produces, the management activities alongside them, how the activities fit the three stages of a project, and a conclusion.

What ISO 12207 is

ISO/IEC/IEEE 12207 is the international standard for software life cycle processes. It was first published in 1995. It defines the processes needed to develop and maintain software. It defines processes, not stages, so it does not force one life cycle model on a project.

The standard arranges its processes in four groups:

  1. Agreement processes: acquisition and supply, between a buyer and a supplier.
  2. Organizational project-enabling processes: life cycle models, infrastructure, portfolio, human resources, quality and knowledge.
  3. Technical management processes: the management work of a project.
  4. Technical processes: the development work itself.
munotes.in 2

The development activities

The technical processes are the software development activities. For a project manager they become the activities a plan must contain.

ActivityWhat happensWhat it produces
Requirements definitionfind out what the stakeholders need and what the software must doa requirements specification
Architecture and design definitiondecide the structure, then the detail of each partarchitecture and design documents
Implementationwrite the code for each componenttested components
Integrationcombine the components into a wholean integrated system
Verificationcheck that the product meets its specificationtest results
Transitioninstall the system in its operational environment and hand it overan installed system, trained users
munotes.in 3
ActivityWhat happensWhat it produces
Validationconfirm that the system meets the users' real needs in useacceptance
Operation and maintenancerun the system, then correct and improve ita supported system

The 1995 edition grouped these under its development process. It listed requirements analysis, design, coding, integration, testing, installation and support for acceptance of the software.

The management activities alongside

The standard also names seven technical management processes. They are project planning, project assessment and control, decision management, risk management, configuration management, information management and quality assurance. These run beside the development activities from start to finish.

munotes.in 4

Where the activities fall in a project

A project passes through three stages: the feasibility study, planning and project execution. The development activities happen in execution. Planning decides their order, effort and dates. Operation and maintenance usually continue after the project closes, so the plan must allow for the handover.

Conclusion. ISO 12207 recommends a full set of development activities, from requirements definition through design, implementation, integration, verification, transition and validation to operation and maintenance. Each activity produces a product that can be checked, and management processes control the work around them.

munotes.in 5

The rest of the answers

The first answer is free. The rest come with the B.Sc. (Information Technology) Semester 5 solved papers.

You have read the question paper and its first answer in full. Buy the solved papers once and you can read every answer of every solved paper in this semester.

Notes + practical solutions + solved papers: ₹798 Already bought it? Sign in

Or solved papers only: ₹499
Or notes + practical solutions: ₹499

The question paper itself stays free, and so does the syllabus.

Issue

Found an error in this volume? Report it and we will check it against the paper.

Done!