Tracking Defects to Closure
Chapter Seventy-Seven
Syllabus topic Module 2, "Defect Management: ... defect reporting and tracking"
Pages 441 to 445 of 622
In one line
Tracking follows every defect from report to closure and the whole population of defects week by week: how many arrive, how many close, how many stay open and for how long, and which requirements they belong to; the trends say when a product is nearly ready, and the ages say which defects are being neglected.
In the wording a student can write in an examination: defect tracking is the continuing record and review of each defect's status, from its report to its closure, and of the defects together. Florac's framework records the date of each status change, and "These attributes are used to determine status, problem age, and problem arrival rate. This information is also of primary importance in product readiness models to determine when the product is ready for acceptance testing or delivery." The main tracking measures are the arrival rate (new defects per period), the closure rate (defects closed per period), the open count and its trend, and the age of open defects. A defect review board meets regularly to triage new reports and act on old ones. And through traceability, which the ISTQB syllabus asks to be maintained "between the test basis elements, testware associated with these elements (e.g., test conditions, risks, test cases), test results, and defects", each defect is tied to the requirement and test it concerns.
Tracking one defect, and tracking them all
Chapter Seventy-Four, on the defect life cycle, followed one defect, DR-205, through its states. Tracking asks a second kind of question, about all of them at once. Florac puts it in terms of the process: "The rate of problem arrival and the time it takes to process a problem report through closure addresses the efficacy of the problem management process." A single defect can be handled perfectly while the population grows out of control; only the counts over time show it.
The defect review board
Somebody has to look at the numbers and at the reports behind them. On ExamReg's project that is the defect review board: the test lead, the development lead and the exam cell's product owner, meeting twice a week during testing. It does two jobs. It triages every new report, taking the decisions of Chapter Seventy-Five, on the defect management process: accept, reject, duplicate, defer, or send to the change control board, which is "responsible for reviewing, evaluating, approving, delaying, or rejecting changes to a project" (the PMBOK Guide). And it reviews the open list, oldest and most severe first, asking of each why it is still open and what would close it.
Arrival, closure and the open count
Plot the defects reported each week and the defects closed each week, and a test cycle usually shows a shape. Early on, testers find defects faster than developers fix them, and the open count rises. As the product stabilises, fewer new defects arrive, the fixes catch up, and the open count falls. The week in which closures first overtake arrivals is the turning point; the open count's approach to zero, or to a small set of known defects, is what Florac's "product readiness models" look for.
Tracking Defects to Closure
Worked example: release 2.0's ten test weeks
The program tracks release 2.0's 114 test-phase defects over its ten test weeks, then takes the list of defects open at the end of week 6, the midpoint of testing, and analyses it as the review board did that week.
from collections import Counter
from itertools import accumulate
# release 2.0's ten test weeks (FINDINGS 5.2.5): defects reported and closed each week
new = [10, 16, 18, 17, 14, 12, 10, 8, 5, 4]
closed = [4, 10, 14, 16, 16, 15, 13, 11, 8, 5]
open_at_end = [a - c for a, c in zip(accumulate(new), accumulate(closed))]
print("week new closed open")
for week, (n, c, o) in enumerate(zip(new, closed, open_at_end), 1):
print(f"{week:>4} {n:>4} {c:>7} {o:>5} {'#' * o}")
turn = next(w for w, (n, c) in enumerate(zip(new, closed), 1) if c > n)
print(f"closures first exceed new reports in week {turn}; open at the end: {open_at_end[-1]}")
# the defects open at the end of week 6: (id, severity, requirement area, days open)
week6 = [("DR-221", "major", "FEE", 3), ("DR-224", "minor", "FORM", 5),
("DR-226", "cosmetic", "HALLTICKET", 5), ("DR-218", "minor", "FEE", 8),
("DR-213", "major", "FORM", 9), ("DR-209", "minor", "LOGIN", 12),
("DR-207", "cosmetic", "FORM", 13), ("DR-204", "minor", "FEE", 15),
("DR-199", "major", "FEE", 20), ("DR-195", "minor", "FORM", 26),
("DR-190", "cosmetic", "HALLTICKET", 31), ("DR-183", "minor", "FEE", 40)]
bands = [("0 to 7 days", 0, 7), ("8 to 14 days", 8, 14), ("15 to 30 days", 15, 30), ("over 30 days", 31, 999)]
print(f"week 6: {len(week6)} open, by age:")
for name, low, high in bands:
ids = [d for d, s, r, age in week6 if low <= age <= high]
print(f" {name:<14} {len(ids):>2} {' '.join(ids)}")
print(" by requirement area:", ", ".join(f"{r} {n}" for r, n in Counter(r for _, _, r, _ in week6).most_common()))
old_major = [d for d, s, r, age in week6 if age > 14 and s in ("critical", "major")]
print(" for the review board, major and open over 14 days:", " ".join(old_major))week new closed open
1 10 4 6 ######
2 16 10 12 ############
3 18 14 16 ################
4 17 16 17 #################
5 14 16 15 ###############
6 12 15 12 ############
7 10 13 9 #########
8 8 11 6 ######
9 5 8 3 ###
10 4 5 2 ##
closures first exceed new reports in week 5; open at the end: 2
week 6: 12 open, by age:
0 to 7 days 3 DR-221 DR-224 DR-226
8 to 14 days 4 DR-218 DR-213 DR-209 DR-207
15 to 30 days 3 DR-204 DR-199 DR-195
over 30 days 2 DR-190 DR-183
by requirement area: FEE 5, FORM 4, HALLTICKET 2, LOGIN 1
for the review board, major and open over 14 days: DR-199Tracking Defects to Closure
The trend. The open count climbs for four weeks, to 17, while testers find defects faster than they are fixed, and the bars show the shape at a glance. In week 5 closures (16) overtake new reports (14) for the first time, and from then on the open count falls every week. By week 10 new reports are down to 4 a week and only 2 defects remain open: DR-311 and DR-318, the two the college accepted as known defects at acceptance testing. A falling arrival rate is only good news if testing has not slowed down; the review board checks it against the test progress figures (Chapter Ten, on test reporting) before reading it as stability.
The snapshot. At the end of week 6, twelve defects were open. Seven were under two weeks old, which is the normal flow. Five had been open more than 14 days, and two more than a month; the review board's rule is to ask about every defect over 14 days old, and to act at once on any that is major or critical. That picks out DR-199, a major defect in the fee area, 20 days old. The others old enough to ask about are minor or cosmetic, which may be why they waited, and the board decides for each whether to fix it now or defer it deliberately rather than by neglect.
The requirement view. Five of the twelve belonged to the fee requirements and four to the exam form. Traced to requirements, open defects say which parts of the product are not yet ready, which the ISTQB syllabus names as one use of traceability: it "can be used to evaluate the level of residual risk in a test object". The fee area was the one to watch.
What a tracking report contains
A weekly tracking report for a defect review board answers five questions, each with a number:
- How many new defects, and how many closed, this period, and the trend over recent periods?
- How many are open, by severity and by status (new, assigned, fixed and awaiting verification, reopened, deferred)?
- How old are the open ones, and which exceed the agreed age for their severity?
- Which requirements, modules or areas have open defects?
- What was decided about each defect that needed a decision?
Tracking Defects to Closure
What it does not mean
Tracking is not reporting once. It is a continuing record, read as a trend; one week's numbers say little.
A falling arrival rate does not prove quality. It may mean the product is stabilising, or that testing has slowed; it is read beside the test progress figures.
An old defect is not always a neglected one. It may be deferred by decision; the point of ageing is to make every such decision explicit.
Zero open defects is not the goal. Known, accepted defects with agreed workarounds, like DR-311 and DR-318, may be released; unknown ones are the danger.
Quick revision
- Florac: status dates give "status, problem age, and problem arrival rate", and are "of primary importance in product readiness models".
- Measures: arrival rate, closure rate, open count and its trend, age of open defects.
- Defect review board: triages new reports and reviews the open list, oldest and most severe first.
- Traceability (ISTQB): between test basis, testware, results and defects; open defects by requirement show residual risk.
- Worked example: open count peaked at 17 in week 4; closures overtook arrivals in week 5; 2 open at the end (DR-311, DR-318); week 6: 12 open, 5 over 14 days, one major (DR-199) escalated; fee area 5, form 4.
Test yourself
1. What does defect tracking involve? Keeping a continuing record of every defect's status from report to closure, with the date of each change, and reviewing the defects together over time: how many arrive and close each period, how many are open, how old they are, and which requirements they affect, so that neglected defects and trends are seen and acted on.
2. What are the arrival rate and the closure rate, and what does their crossing mean? The arrival rate is the number of new defects reported per period; the closure rate the number closed per period. When closures first exceed arrivals, the open count starts to fall, a sign that the product is stabilising, provided testing effort has not dropped.
3. Why track the age of open defects? Because a defect can sit open without anyone deciding anything about it. Age shows which defects have waited longest; with a rule such as reviewing every defect open more than two weeks, each old defect is either fixed or deferred by an explicit decision.
4. What is a defect review board, and what does it do? A group, typically the test lead, development lead and product owner, that meets regularly during testing to triage every new defect report and to review the open defects, deciding for each whether to fix, defer, reject or escalate it.
Tracking Defects to Closure
5. How does traceability help in tracking defects? By linking each defect to the requirement and test case it concerns, it shows which requirements still have open defects, and so which parts of the product are not ready and where residual risk remains; and it tells the tester which test confirms a fix.
6. In the worked example, which defect did the board escalate at week 6, and why? DR-199, because it was the only major defect that had been open more than 14 days; the other old defects were minor or cosmetic and were considered for fixing or deliberate deferral.