KSLU Solved Question Papers
Land Law
Previous Year Question Paper with Solution
B.A. LL.B. (Five Years) · Sem 10
2025 Jun Examination
munotes.in
Mumbai
KSLU Solved Question Papers
Land Law
Previous Year Question Paper with Solution
B.A. LL.B. (Five Years) · Sem 10
2025 Jun Examination
munotes.in
Mumbai
First published on munotes.in on 21 October 2026.
Published by munotes.in, Mumbai.
Model answers written and edited by the munotes.in editorial desk.
Passages from this volume may be quoted, in print, online or by an AI system, with credit: name munotes.in and link to this volume's page. The volume may not be reproduced as a whole. Full terms at munotes.in/content-license.
munotes.in is an independent study resource for students of Karnataka State Law University. It is not affiliated with Karnataka State Law University, and is not endorsed by it.
The University does not publish an official answer key for this paper. The answers in this volume are model answers, written to show how a full-mark answer is built. They are a study aid, not an authority on what an examiner marked.
The question paper reproduced here is the paper as set by Karnataka State Law University at the 2025 Jun examination.
The questions below are the paper as Karnataka State Law University set it at the 2025 Jun examination, in the order it was set.
MarksPage
MarksPage
The questions in this volume are the questions asked at the 2025 Jun examination, reproduced as Karnataka State Law University set them, in the order it set them. Long reading passages are shortened to their first and last lines and our summary; the original paper prints them in full. Only the answers are ours. See the original question paper.
Duration 3 hours · Total marks 80 · 20 questions answered
Instructions printed on the paper
How to use this volume
Solve the paper first, under exam conditions and against the clock. Then read the answers here and mark your own. Reading a solution before attempting the question feels productive and teaches very little, because recognising an answer is not the same as being able to write one.
Unit I
Answer
For full marks, cover: the stages of compulsory acquisition under the 2013 Act in order: social impact assessment (sections 4 to 9); preliminary notification and its effect (section 11); survey and objections (sections 12 to 15); the rehabilitation scheme (sections 16 to 18); the declaration and its time limit (section 19); marking out and notice (sections 20 to 22); enquiry and award within twelve months (sections 23 and 25); possession after payment (section 38); urgency (section 40); Karnataka's 2019 changes; a case; conclusion.
Under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, land is acquired in stages. Two notifications are central. The preliminary notification under section 11 announces that land is needed. The declaration under section 19 confirms that particular land is needed for a public purpose. The award and possession follow.
Before any notification, the appropriate Government studies the social impact with the Panchayat or Municipality. The study takes up to six months and includes a public hearing. An independent Expert Group appraises it. The Government then satisfies itself that there is a real public purpose and that only the minimum land is being taken. For private company and partnership projects, consent of 80 or 70 per cent of the affected families is taken during the study.
When land appears to be needed for a public purpose, the preliminary notification is issued. It is published in the Gazette and in two newspapers. It also goes up in the local language in Panchayat and revenue offices, on the website and in the affected area. It must state the public purpose, the reasons for displacement, a summary of the study and the Administrator's name. The Gram Sabha is told of it at a special meeting.
From publication, no one may deal with the land or encumber it until the proceedings end. The Collector must update the land records within two months.
Officers may enter the land to survey it, take levels and mark boundaries. The owner must be present or given sixty days' notice. Damage caused is paid for. Under section 15, any person interested may object within sixty days. He may object to the area, to the public purpose or to the findings of the study. The Collector hears him and reports to the Government, whose decision is final.
The Administrator surveys the affected families and prepares a draft rehabilitation and resettlement scheme. It is discussed in the Gram Sabhas and at public hearings. The Collector reviews it and the Commissioner approves it.
When the Government is satisfied that the land is needed for a public purpose, it issues a declaration. It also declares a resettlement area. The summary of the rehabilitation scheme must be published with it. No declaration can issue until the Requiring Body deposits the cost of acquisition as prescribed. The declaration is conclusive evidence that the land is needed for a public purpose.
If no declaration is made within twelve months of the preliminary notification, that notification is deemed rescinded. Periods of court stay are excluded. The Government may extend the period by a recorded and published decision.
The Collector has the land marked, measured and planned. He gives public notice and notice to each person interested, inviting claims to compensation and rehabilitation. Under section 23, he holds an enquiry into objections, measurements, value and the interests claimed.
The Collector makes an award of the true area, the compensation with the rehabilitation award, and its apportionment. Under section 25, he must make it within twelve months of the declaration, or the whole acquisition lapses. The Government may extend the period by a published decision. Compensation includes market value, a multiplying factor, the value of assets and solatium of 100 per cent.
The Collector takes possession only after compensation is paid or tendered within three months of the award. The money part of the rehabilitation entitlements must be paid within six months. Rehabilitation must be complete before families are displaced. The land then vests in the Government free from encumbrances.
Under section 40, in cases of urgency such as defence or natural calamities, the Government may take possession thirty days after notice, before the award. The social impact study may then be dispensed with under section 9. In Karnataka, Act 16 of 2019 lets the State exempt notified projects from the study. Its section 23-A lets the Deputy Commissioner make an award without enquiry where all interested persons agree in writing.
Radhy Shyam v. State of Uttar Pradesh, (2011) 5 SCC 553. Land at Greater Noida was notified for industrial development. The State invoked urgency to dispense with the hearing of objections under section 5-A of the 1894 Act. The Supreme Court quashed the acquisition. It held that hearing objections is not delay that defeats the purpose. That hearing is the statutory form of the right to be heard. Sections 15 and 40 of the 2013 Act keep that rule and narrow the urgency power.
Conclusion. Acquisition under the 2013 Act moves from a social impact study to a preliminary notification, objections, a rehabilitation scheme and a declaration within twelve months. The award must follow within twelve months of the declaration, and possession only after payment. Each stage is published and open to challenge. The preliminary notification lapses without a timely declaration, and the acquisition lapses without a timely award.
The rest of the answers
You have read the question paper and its first answer in full. Buy the solved papers once and you can read every answer of every solved paper in this semester.
Solved papers: ₹499 Already bought it? Sign in
The question paper itself stays free.
Found an error in this volume? Report it and we will check it against the paper.