Q1 a. Write a short note on post optimality sensitivity analysis with respect to addition and deletion of a constraint in a L.P.P 10 marks
- b. Use two-phase simplex method to solve following LP problem. Subject to the constraints 10
- p. optimum simplex table for a maximization type LPP, describe the procedure of checking the effect on feasibility of the current solution if an element of requirement vector is changed from bx to by; where by = Ab, . How is the solution modified if the change affects the feasibility of the
- q. Use dual simplex method to solve the problem: Subject to the constraints: 10
-
Q2 a. Find the optimum level to which the stock should be raised at the beginning of each period t (t is fixed and known). If the demand ‘r’ is a discrete random variable with 12 marks
- p.m.f P(r). The per unit costs of overstock & under stock are & C2 per unit time Also demand occurs at a uniform rate
- b. Describe different costs associated with inventory system. manufacturing situation is holding per item per unit time, C3 is the setup (12) cost per production cycle, ‘R’ is the demand rate. Shortages are not allowed and the production rate is finite. is the interval between the start of successive production cycles. ‘q’ is the number of items produced per production run. Find an expression for the optimum order quantity and the minimum cost per unit time 8
- q. Explain the problem of inventory models with price breaks. How would you obtain the EOQ in case of a problem with two price breaks? 8
-
Q3 a. Explain the concept of Individual and Group replacement Policy. Derive the condition for the replacement of item where maintenance cost increases with time and money value does not change with time where ‘t’ is continuous random variable 10 marks
- b. What is meant by Present worth factor? A firm is considering replacement of an equipment whose cost is Rs. 4000 and the scrap value is negligible at the end of any year. Based on the experience, it has been found that the maintenance cost is Rs. 1000 for the second year and it increases by Rs. 300 every year thereafter. When should the equipment be replaced? 10
- p. Derive the condition for the replacement of item where maintenance cost increases with time and money value is involved 10
- q. Arefrigeratoris priced at Rs.60000 and running costs are estimated at Rs.6000 foreach of the first four years, increasing by Rs.2,000 per year in the fifth and the subsequent years. If money is worth 10% per year, when should the truck be replaced? (No scrap 10
-
Q4 Explain in brief the concept of reliability. Also explain series and parallel system and find expression for their reliabilities 10 marks
- b. Write a short note on the Monte Carlo method used in Simulation Theory. Explain the Mid Square Method for generating random numbers. Also state its limitations with 10
- p. Anelectronic device has 15 valves, 20 resistors and 10 capacitors, all connected in series. The components in each category are identical and their failure times are found to follow exponential distribution with the following mean failure time: time in hours What is the reliability of the system for 100 hours? Also find MTTF of the system 10
- q. is meant by Simulation? Explain the (i) multiplicative Congruential method for generating random numbers Also explain how generated random numbers can be used to further generate random sample from normal distribution 10
-
Q5 Attempt ANY TWO sub-questions
- a. Use simplex method to solve the following LP problem and obtain the optimal solution: 10
- b. Find the optimum order level that minimizes the total expected cost for single period model with instantaneous discrete demand without set-up cost. (State clearly the 10
- c. zero, all items in a system are new. Each item has a probability of failing immediately before the end of the first month of life and a probability q=(1-p) of failing immediately before the end of the second month. If all items are replaced as they fail Show that the expected number of failures f(x) at the end of the month x is given by Where N is the number of items in the system. If the cost per item of individual replacement is C; and the cost per item of group replacement is Co, find the condition under which (i)a group replacement policy at the end of each month is most profitable (i1) no group replacement policy is better than that of pure individual replacement 10
- d. (i) Write note on Bath-tub curve? 10
- (ii) State advantages and disadvantages of Simulation Technique
Read from the scan above, so a character or two may differ. The scan is the original.
Something wrong on this page? Report it and we will check it against the scan.
Quick Help
No. The full paper opens straight away, with no login and nothing to pay.
Related Resources
Something wrong with this paper? Report it.
Connected Papers
BSc / Sem VI · 43 papers
Apr 2023 - BIOTECHNOLOGY PAPER I CELL BIOLOGY,MEDICAL BIOTECH & BIOSTAT
Apr 2023 - BIOCHEMISTRY I METABOLISM AND ANALYTICAL TECHNIQUESN II
Apr 2023 - BIOCHEMISTRY II NUTRITION AND PHARMCOLOGY
Apr 2023 - BIOCHEMISTRY IV IMMUNOLOGY AND PATHOPHY SIOLOGY II
Apr 2023 - BOTANY CURRENT TRENDS IN PLANT SCIENCES II
Apr 2023 - BOTANY FORM AND FUNCTION III
Apr 2023 - BOTANY PLANT DIVERSITY III
Apr 2023 - BOTANY PLANT DIVERSITY IV
Apr 2023 - CHEMISTRY ANALYTICAL CHEMISTRY
Apr 2023 - CHEMISTRY III ORGANIC CHEMISTRY
Apr 2023 - CHEMISTRY INORGANIC CHEMISTRY
Apr 2023 - CHEMISTRY PHYSICAL CHEMISTRY
Apr 2023 - MATHEMATICS BASIC COMPLEX ANALYSIS
Apr 2023 - MATHEMATICS GRAPH THEORY AND COMBINATORICS
Apr 2023 - MATHEMATICS INTEGRAL TRANSFORMS
Apr 2023 - MATHEMATICS TOPOLOGY OF METRIC SPACES AND REAL ANALYSIS
Apr 2023 - PHYSICS CLASSICAL MECHANICS
Apr 2023 - PHYSICS ELECTRONICS
Apr 2023 - PHYSICS NUCLEAR PHYSICS
Apr 2023 - STATISTICS ACTURIAL SCIENCE
Apr 2023 - STATISTICS DISTRIBUTION THEORY STOCHASTIC PROCESS
Apr 2023 - STATISTICS OPERATIONS RESEARCH TECHNIQUES Open
Apr 2023 - STATISTICS TESTING OF HYPOTHESIS
Apr 2023 - ZOOLOGY ENVIRONMENTAOL BIOLIGY AND ZOOPHARMA
Apr 2023 - ZOOLOGY GENTICS AND INFORMATICS
Apr 2023 - ZOOLOGY PHYSIOLOGY AND TISSUE CULTURE
Apr 2023 - ZOOLOGY TAXONOMY CHORDATES AND TYPE STUDY
Apr 2023 - BIOCHEMISTRY III BIOSTATISTICS AND BIOINFORMATICS
2023 - TIME TABLE
2023 - TIME TABLE
Questions? Email contact@munotes.in
Done!