1Module I
1
OVERVIEW OF ITSPROJECT
MANAGEMENT
Unit Structure
1.0Objectives
1.1What is a project?
1.1.1Project Definition
1.2Project Attributes
1.3Project Constraints
1.3.1Time
1.3.2Cost
1.3.3Scope
1.4What is Project Management
1.4.1Features of projects
1.4.2Project Classification
1.4.3Project Managem ent Tools and techniques
1.4.4Project Success Factors
1.5Introduction to An Overview of IT Project Management
1.5.1What is IT Project Management?
1.5.2Project Management Framework
1.5.3Responsibilities of an IT Project Manager
1.5.4System view of a project
1.5.5Stakeholder Management
1.5.6Project Phases and the project life cycle
1.6Summary
1.0 OBJECTIVE
In this unit you are going to learn:
IT Project Management
Project Management Framework
Role of IT Project Manager
Project System View
How to manage stakeholder?
Project phases and lifecyclemunotes.in
Page 2
2Project management has been practiced since early civilization.
Until the beginning of twentieth century civil engineering projects were
actually treated as projects and were generally managed by creative
architects and engineers. Project management as a discipline was not
accepted. It was in the 1950s that organizations started to systematically
apply project management tools and techniques to complex projects. As a
discipline, Project Management developed from several fields of
application including con struction, engineering, and defense activity.
Two forefathers of project management are commonly known: Henry
Gantt, called the father of planning and control techniques who is famous
for his use of the Gantt chart as a project management tool; and Henri
Fayol for his creation of the five management functions which form the
foundation of the body ofknowledge associated with project and program
management. The 1950s marked the beginning of the modern Project
Management era. Project management became recog nized as a distinct
discipline arising from the management discipline.
1.1WHAT IS A PROJECT?
All of us have been involved in projects, whether they be our
personal projects or in business and industry. Examples of typical projects
are for example:
Persona lprojects:
➢obtaining an MCA degree
➢writing a report
➢planning a party
➢planting a garden
Industrial projects:
➢Construction of a building
➢provide electricity to an industrial estate
➢building a bridge
➢designing a new airplane
Projects can be of any size and duration. They can be simple, like
planning a party, or complex like launching a space shuttle.
1.1.1 Project Definition:
A project can be defined in many ways :
Aproject is “a temporary endeavor undertaken to create a unique
product, service, or resu lt.” Operations, on the other hand, is work done in
organizations to sustain the business. Projects are different from
operations in that they end when their objectives have been reached or
the project has been terminated.
A project is temporary . A proj ect’s duration might be just one
week or it might go on for years, but every project has an end date. You
might not know that end date when the project begins, but it’s theremunotes.in
Page 3
3somewhere in the future. Projects are not the same as ongoing operations,
althou gh the two have a great deal in common.
A project is an endeavor . Resources, such as people and
equipment, need to do work. The endeavor is undertaken by a team or
anorganization, and therefore projects have asense ofbeing
intentional, planned events . Successful projects do not happen
spontaneously; some amount of preparation and planning happens first.
Finally, every project creates a unique product orservice . This is
thedeliverable for the project and the reason, why that project was
undertaken.
1.2PROJECT ATTRIBUTES
Projects come in all shapes and sizes. The following attributes help
us to define a project further:
A project has a unique purpose. Every project should have a well -
defined objective. For example, many people hire firms to design a nd
build a new house, but each house, like each person, is unique.
A project is temporary. A project has a definite beginning and a
definite end. For a home construction project, owners usually have a date
in mind when they’d like to move into their new homes.
A project is developed using progressive elaboration or in an iterative
fashion.
Projects are often defined broadly when they begin, and as time
passes, the specific details ofthe project become clearer. For example,
there are many decisions that m ust be made in planning and building a
new house. It works best to draft preliminary plans for owners to approve
before more detailed plans are developed.
A project requires resources, often from various areas. Resources
include people, hardware, software, or other assets. Many different types
of people, skill sets, and resources are needed to build a home.
A project should have a primary customer or sponsor. Most projects
have many interested parties or stakeholders, but someone must take the
primary role of sponsorship. The project sponsor usually provides the
direction and funding for the project.
A project involves uncertainty. Because every project is unique, it is
sometimes difficult to define the project’s objectives clearly, estimate
exactly how long it will take to complete, or determine how much it will
cost. External factors also cause uncertainty, such as a supplier going out
of business or a project team member needing unplanned time off. This
uncertainty is one of the main reasons project man agement is so
challenging.munotes.in
Page 4
41.3PROJECT CONSTRAINTS
Like any human undertaking, projects need to be performed and
delivered under certain constraints. Traditionally, these constraints have been
listed as scope, time, and cost. These are also referred to as th e Project
Management Triangle, where each side represents a constraint. One side of
the triangle cannot be changed without impacting the others. A further
refinement of the constraints separates product 'quality' or 'performance' from
scope, and turns qual ity into a fourth constraint.
The time constraint refers to the amount of time available to complete
a project. The cost constraint refers to the budgeted amount available for the
project. The scope constraint refers to what must be done to produce the
project's end result. These three constraints are often competing constraints:
increased scope typically means increased time and increased cost, a tight
time constraint could mean increased costs and reduced scope, and a tight
budget could mean increased time and reduced scope.
The discipline of project management is about providing the tools and
techniques that enable the project team (not just the project manager) to
organize their work to meet these constraints.
Another approach to project management is to consider the three
constraints as finance, time and human resources. If you need to finish a job
in a shorter time, you can allocate more people at the problem, which in turn
will raise the cost of the project, unless by doing this task quicker we will
reduce costs elsewhere in the project by an equal amount.
1.3.1Time:
For analytical purposes, the time required to produce a product or
service is estimated using several techniques. One method is to identify tasks
needed to produce the deliverables docu mented in a work breakdown structure
orWBS. The work effort for each task is estimated and those estimates are
rolled up into the final deliverable estimate.
The tasks are also prioritized, dependencies between tasks are identified,
and this informatio n is documented in a project schedule. The dependencies
between the tasks can affect the length of the overall project (dependency
constraint), as can the availability of resources (resource constraint). Time is not
considered acost noraresource since theproject manager cannot control the
rate at which it is expended. This makes it different from all other resources
and cost categories.
1.3.2Cost:
Cost to develop a project depends on several variables including :
labor rates, material rates, risk manageme nt, plant (buildings, machines, etc.),
equipment, and profit. When hiring an independent consultant for a project,
cost will typically be determined by the consultant's or firm's per diem rate
multiplied by an estimated quantity for completion.munotes.in
Page 5
5Figure 1 .1 : The Project management Triangle
1.3.3Scope:
Scope is requirement specified for the end result. The overall
definition of what the project is supposed to accomplish, and a specific
description of what the end result should be or accomplish can be said to be
the scope of the project. A major component of scope is the quality of the final
product. The amount of time put into individual tasks determines the overall
quality of the project. Some tasks may require a given amount of time to
complete adequately, b ut given more time could be completed exceptionally.
Over the course of a large project, quality can have a significant impact on
time and cost or vice versa.
Together, these three constraints viz. Scope, Schedule & Resources
have given rise to the phrase "On Time, On Spec, On Budget". In this case,
the term "scope" is substituted with "spec(ification)"
1.4WHAT IS PROJECT MANAGEMENT
Project management is “the application of knowledge, skills, tools
and techniques to project activities to meet the project requirements.” The
effectiveness of project management is critical in assuring the success of any
substantial activity. Areas of responsibility for the person handling the project
include planning, control and implementation. A project should be initiated
with a feasibility study, where a clear definition of the goals and ultimate
benefits need to be determined. Senior managers' support for projects is
important so as to ensure authority and direction throughout the project's
progress and, also to ensure t hat the goals of the organization are effectively
achieved in this process.
Knowledge, skills, goals and personalities are the factors that need to
be considered within project management. The project manager and his/her
team should collectively possess the necessary and requisite interpersonal and
technical skills to facilitate control over the various activities within the
project.
The stages of implementation must be articulated at the project
planning phase. Disaggregating the stages at its early point assists in the
munotes.in
Page 6
6successful development of the project by providing a number of milestones
that need to be accomplished for completion. In addition to planning, the
control of the evolving project is also a prerequisite for its success. Control
require s adequate monitoring and feedback mechanisms by which senior
management and project managers can compare progress against initial
projections at each stage of the project. Monitoring and feedback also enables
the project manager to anticipate problems a nd therefore take pre -emptive
and corrective measures for the benefit of the project.
Projects normally involve the introduction of a new system of some
kind and, in almost all cases, new methods and ways of doing things. This
impacts the work of other s: the "users". User interaction is an important factor
in the success of projects and, indeed, the degree of user involvement can
influence the extent of support for the project or its implementation plan. A
project manager is the one who is responsible for establishing a
communication in between the project team and the user. Thus one of the
most essential quality of the project manager is that of being a good
communicator, not just within the project team itself, but with the rest of the
organizatio n and outside world as well.
1.4.1Features of projects:
Projects are often carried out by a team of people who have been
assembled for that specific purpose. The activities of this team may be co -
ordinated by a project manager.
Project teams may consist of pe ople from different backgrounds and
different parts of the organisation. In some cases project teams may
consist of people from different organisations.
Project teams may be inter -disciplinary groups and are likely to lie outside
the normal organisation hierarchies.
The project team will be responsible for delivery of the project end
product to some sponsor within or outside the organisation. The full
benefit of any project will not become available until the project as been
completed.
1.4.2Project Classificati on:
In recent years more and more activities have been tackled on a project
basis. Project teams and a project management approach have become
common in most organisations. The basic approaches to project management
remain the same regardless of the type of project being considered. You may
find it useful to consider projects in relation to a number of major
classifications:
a)Engineering and construction
The projects are concerned with producing a clear physical output,
such as roads, bridges or buildings. The requirements of a project team are
well defined in terms ofskills and background, as are the main procedures thatmunotes.in
Page 7
7have to be undergone. Most of the problems which may confront the project
team are likely to have occurred before and therefore their solution may be
based upon past experiences.
b)Introduction of new systems
These projects would include computerisation projects and the
introduction of new systems and procedures including financial systems. The
nature and constitution of a project team m ay vary with the subject of the
project, as different skills may be required and different end -users may be
involved. Major projects involving a systems analysis approach may
incorporate clearly defined procedures within an organisation.
c)Responding to deadlines and change
An example of responding to a deadline is the preparation of an annual
report by a specified date. An increasing number of projects are concerned
with designing organisational or environmental changes, involving developing
new product s and services.
1.4.3Project Management Tools and techniques:
Project planning is at the heart of project management. One can't
manage and control project activities if there is no plan. Without a plan, it is
impossible to know if the correct activities are underway, if the available
resources are adequate or of the project can be completed within the desired
time. The plan becomes the roadmap that the project team members use to
guide them through the project activities. Project management tools and
techniqu es assist project managers and their teams in carrying out work in all
nine knowledge areas. For example, some popular time -management tools
and techniques include Gantt charts, project network diagrams, and critical
path analysis. Table 1.1 lists some co mmonly used tools and techniques by
knowledge area.
Knowledge Area Tools & Techniques
Integration management Project selection methods, project managementmethodologies, stakeholder analyses, projectcharters, project management plans, projectmanagementsoftware, change requests, changecontrol boards, project review meetings,lessons -learned reports
Scope management Scope statements, work breakdown structures,
mind maps, statements of work, requirementsanalyses, scope management plans, scopeverificat ion techniques, and scopechangecontrolsmunotes.in
Page 8
8Cost ManagementNet present value, return on investment,paybackanalyses, earned value management,project portfolio management, costestimates,cost management plans, cost baselines
Time management Gantt charts, project network diagrams,critical -path analyses, crashing, fast tracking,schedule performance measurementsHuman resourcemanagementMotivation techniques, empathic listening,responsibility assignment matrices, project
organizational charts, resource histograms,team building exercises
Quality managementQuality metrics, checklists, quality controlcharts, Pareto diagrams, fishbone diagrams,
maturity models, statistical methods
Risk managementRisk management plans, risk registers,probability/impa ct matrices, risk rankings
Communication
managementCommunications management plans, kickoffmeetings, conflict management,communicationsmedia selection, status andprogress reports, virtual communications,
templates, project Web sites
Procurement
mana gementMake -or-buy analyses, contracts, requests for
proposals or quotes, source selections, supplier
evaluation matrices
Table 1.1 : Project Management Tools and Techniques
1.4.4Project Success Factors:
The successful design, development, and implementatio n of information
technology (IT) projects is a very difficult and complex process. However,
although developing IT projects can be difficult, the reality is that a relatively
small number of factors control the success or failure of every IT project,
regar dless of its size or complexity. The problem is not that the factors are
unknown; it is that they seldom form an integral part of the IT development
process.
Some of the factors that influence projects and may help them succeed are
Executive Support
User involvement
Experienced project managers
Limited scope
Clear basic requirementsmunotes.in
Page 9
9Formal methodology
Reliable estimates
1.5 INTRODUCTION TO AN OVERVIEW OF IT PROJECT
MANAGEMENT
In IT, projects have become more complex as technologies rapidly
change and en d-users demand greater ease -of-use and flexibility. For an IT
project manager to achieve their objectives, it is imperative that these
initiatives are completed on time and on budget.
Discover what it means to manage IT projects, common challenges
faced b y IT project managers, and tips to make your next IT project a success.
You’ll also find helpful resources, like guides and free templates.
1.5.1 What Is IT Project Management?
IT project management (ITPM) is the process of managing the
plan, organiza tion, and accountability to achieve information technology
goals. Since the reach of IT spans across most of a business or enterprise, the
scope of these projects can be large and complex.
The magnitude of IT project management often means that it’s
more than just applying knowledge, aligning skills, and using regular tools
and techniques to drive a project to completion. IT project managers deal with
the challenges of interdependent integrations, rapid technology upgrades, and
version changes that can oc cur throughout the project timeline.
1.5.2 Project Management Framework
Initiation:
Project Managers work with other concerned stakeholders to evaluate
and determine the values and feasibility of the projectmunotes.in
Page 10
10Planning:
Create a project plan: team, time line, activities, and resources
budgeting. Designing required solutions to solve the customer’s problem.
Communicate project plan to all stakeholders.
Execution :
Team delivery of project plan. Test project implementation to ensure
successful project inte gration. Monitor all aspect of project plan to ensure
quality and delivery time. Establish training and modes of continues support
for customers
Performance Control:
Project execution process gets evaluated in this phase by means of
KPIs like project obje ctives, quality deliverables, cost monitoring, overall
project performance, etc.
Closure :
The promised project deliverables are handed over to the client for
validation. A final closure meeting is also held to discuss the overall
experience and to close a ll project accounts.
1.5.3 Responsibilities of an IT Project Manager
Main Responsibilities of an IT Project Manager:
Today’s IT project managers (IT PM) must be able to juggle a wide
range of tasks and responsibilities. They must be able to handle firmwa re and
software integrations, website construction, database storage and
management, and also build complex and geographically diverse
infrastructures and networks, all while planning for potential security and data
risks.
Throughout their projects, IT PM is responsible for setting goals,
communicating and motivating team members and stakeholders, identifying
the right resources for each task, researching, managing change, performing
needs assessment, and properly sequencing tasks.
Additional responsibili ties of the IT project manager include the
following:
Project planning and overall management
Promoting and achieving project support
Ensuring overall capability with existing technology
Minimizing duplicate work
Utilizing team member skills
Controlling co sts and maintaining budgets
Challenges Faced by IT Project Managers:
The complexities and interdependencies of large -scale, long -term,
diverse IT projects are among the most challenging issues of IT projects. Here
are a few more top challenges faced by IT project managers:munotes.in
Page 11
11Making multiple assumptions when integrating different hardware,
networks, and software to the existing system.
Unclear expectations from the business, end -users, and stakeholders.
Rapidly changing technology, leading to necessary mid -project upgrades
that can affect timelines.
Geographically diverse offices and remote work associated.
1.5.4 System view of a project
A system view of Project is to take a look into the scope of the project
and to know how does that fit into the organizatio n by analyzing the project
using the following interrelated elements,
Programmed Objectives
Rules, Regulations, Constraints and Policy Restrictions
Management Control
Inputs
Implementation Process
Output
Outcome
Impact
Feedback
So by analyzing the above elements of the project, a project can be planned
and managed.
1.5.5 Stakeholder Management
Who are Stakeholders?
Stakeholders are individuals who get impacted by the project. A
Stakeholder can be a supporter and a resistor.
Project Stakeholder Manageme nt involves identification of
stakeholders, analysis of their expectations and influences, development of
appropriate strategies to work with the stakeholders and executing the process.
Frequent communication is required with the stakeholders. Needs and
expectations of the stakeholders to be understood. Managing conflicting
interest and involving stakeholders in key project decisions and activities are
also crucial. All of this forms a part of the stakeholder management process.
The project manager is expec ted to possess the ability to identify the needs
and influences of the stakeholders to manage them effectively.
Identify Stakeholders:
The process of identifying individuals who are impacted by the project
is known as Identify Stakeholders Process. The pr oject manager will be able
to identify the appropriate focus of each stakeholder as an outcome of Identify
Stakeholders process. Stakeholders can include the customers, sponsors,
employees, management, government, and society as well. These stakeholders
have a potential to exert positive or negative influence on the project
deliverables.munotes.in
Page 12
12Stakeholder needs are to be identified at an early stage of the project to
ensure that all their requirements and voices are considered. The stakeholders
can be classified on the basis of their interest in the project, the level of
influence on the project outcome and their involvement. For the success of the
project, the project manager needs to have a relationship that is cordial and
extremely success oriented.
Stakeholde rs Process can receive inputs from:
Project Charter: Internal and external parties related to the project are
identified using the project charter
Procurement Documents: The parties involved in a procurement contract are
key project stakeholders
Enterprise Environmental Factors: Organizational culture, its structure,
governmental regulations, trends, practices or habits of individuals represent
enterprise environmental factors.
Organizational Process Assets: Stakeholder registers from previous projects,
lessons learned are important inputs for identifying stakeholders
Stakeholder Analysis
A qualitative and quantitative analysis is required to systematically
determine the interest of stakeholders throughout the project. The benefits of
this analysis are:
Stakeholder interests can be identified
Stakeholder expectations can be identified
Another benefit includes identification of stakeholder relationships
that can be leveraged to build partnerships with stakeholders to increase the
probability of project succes s
Steps involved in stakeholder analysis process are:
Identification of potential stakeholders including their roles,
departments, interests, knowledge, expectations, and influence levels.
Identify and analyze the potential impact each stakeholder could
generate Classify the stakeholder's basis logical categories of potential impact
Determine the likely reaction of these stakeholders to respond in various
situations Plan the approach strategy to enhance their positive support and
reduce negative influences
Multiple classification models are used for stakeholder analysis, but not
limited to:
Power/Interest grid: Bifurcation of stakeholders based on their level of
authority and their level of concern regarding project outcomes.
Power/Influence grid: Bifurcati on of stakeholders based on their level of
authority and their level of involvement in the project
Power/Impact grid: Bifurcation of stakeholders based on their level of
authority and their level of impacting changes on project activitiesmunotes.in
Page 13
13Salience model: This model describes categories of stakeholders based on
their power, urgency, and legitimacy.
Outputs of Identifying Stakeholders:
Stakeholder register is updated with details such as:
Stakeholder information
Includes their name, organizational position, location, role in the project,
business phone number, email address, etc
Stakeholder requirements
Key expectations, major requirements, involvement in the project etc
Stakeholder Classification
1.5.6 Project Phases and the project life cycle
The Project Life Cycle (Phases):
The project manager and project team have one shared goal: to carry
out the work of the project for the purpose of meeting the project’s objectives.
Every project has a beginning, a middle period during which activities move
the projec t toward completion, and an ending (either successful or
unsuccessful). A standard project typically has the following four major
phases (each with its own agenda of tasks and issues): initiation, planning,
implementation, and closure. Taken together, thes e phases represent the path a
project takes from the beginning to its end and are generally referred to as the
project “life cycle.”
Initiation Phase:
During the first of these phases, the initiation phase, the project
objective or need is identified; thi s can be a business problem or opportunity.
An appropriate response to the need is documented in a business case with
recommended solution options. A feasibility study is conducted to investigate
whether each option addresses the project objective and a fi nal recommended
solution is determined. Issues of feasibility (“can we do the project?”) and
justification (“should we do the project?”) are addressed.
Once the recommended solution is approved, a project is initiated to
deliver the approved solution and a project manager is appointed. The major
deliverables and the participating work groups are identified, and the project
team begins to take shape. Approval is then sought by the project manager to
move onto the detailed planning phase.
Planning Phase:
The next phase, the planning phase, is where the project solution is
further developed in as much detail as possible and the steps necessary to
meet the project’s objective are planned. In this step, the team identifies all of
the work to be done. The projec t’s tasks and resource requirements are
identified, along with the strategy for producing them. This is also referred to
as “scope management.” A project plan is created outlining the activities,
tasks, dependencies, and timeframes. The project manager coo rdinates the
preparation of a project budget by providing cost estimates for the labour,munotes.in
Page 14
14equipment, and materials costs. The budget is used to monitor and control cost
expenditures during project implementation.
Once the project team has identified the wo rk, prepared the schedule,
and estimated the costs, the three fundamental components of the planning
process are complete. This is an excellent time to identify and try to deal with
anything that might pose a threat to the successful completion of the proj ect.
This is called risk management. In risk management, “high -threat” potential
problems are identified along with the action that is to be taken on each high -
threat potential problem, either to reduce the probability that the problem will
occur or to red uce the impact on the project if it does occur. This is also a
good time to identify all project stakeholders and establish a communication
plan describing the information needed and the delivery method to be used to
keep the stakeholders informed.
Finall y, you will want to document a quality plan, providing quality
targets, assurance, and control measures, along with an acceptance plan,
listing the criteria to be met to gain customer acceptance. At this point, the
project would have been planned in detail and is ready to be executed.
Implementation (Execution) Phase:
During the third phase, the implementation phase, the project plan is
put into motion and the work of the project is performed. It is important to
maintain control and communicate as needed d uring implementation. Progress
is continuously monitored and appropriate adjustments are made and recorded
as variances from the original plan. In any project, a project manager spends
most of the time in this step. During project implementation, people ar e
carrying out the tasks, and progress information is being reported through
regular team meetings. The project manager uses this information to maintain
control over the direction of the project by comparing the progress reports
with the project plan to m easure the performance of the project activities and
take corrective action as needed. The first course of action should always be to
bring the project back on course (i.e., to return it to the original plan). If that
cannot happen, the team should record variations from the original plan and
record and publish modifications to the plan. Throughout this step, project
sponsors and other key stakeholders should be kept informed of the project’s
status according to the agreed -on frequency and format of communi cation.
The plan should be updated and published on a regular basis.
Status reports should always emphasize the anticipated end point in
terms of cost, schedule, and quality of deliverables. Each project deliverable
produced should be reviewed for quality and measured against the acceptance
criteria. Once all of the deliverables have been produced and the customer has
accepted the final solution, the project is ready for closure.
Closing Phase:
During the final closure, or completion phase, the emphasis i s on
releasing the final deliverables to the customer, handing over project
documentation to the business, terminating supplier contracts, releasing
project resources, and communicating the closure of the project to allmunotes.in
Page 15
15stakeholders. The last remaining ste p is to conduct lessons -learned studies to
examine what went well and what didn’t. Through this type of analysis, the
wisdom of experience is transferred back to the project organization, which
will help future project teams.
Example: Project Phases on a Large Multinational Project:
A U.S. construction company won a contract to design and build the
first copper mine in northern Argentina. There was no existing infrastructure
for either the mining industry or large construction projects in this part of
South America. During the initiation phase of the project, the project manager
focused on defining and finding a project leadership team with the knowledge,
skills, and experience to manage a large complex project in a remote area of
the globe. The project tea m set up three offices. One was in Chile, where large
mining construction project infrastructure existed. The other two were in
Argentina. One was in Buenos Aries to establish relationships and
Argentinean expertise, and the second was in Catamarca —the lar gest town
close to the mine site. With offices in place, the project start -up team began
developing procedures for getting work done, acquiring the appropriate
permits, and developing relationships with Chilean and Argentine partners.
During the planning phase, the project team developed an integrated
project schedule that coordinated the activities of the design, procurement, and
construction teams. The project controls team also developed a detailed
budget that enabled the project team to track project e xpenditures against the
expected expenses. The project design team built on the conceptual design and
developed detailed drawings for use by the procurement team. The
procurement team used the drawings to begin ordering equipment and
materials for the cons truction team; develop labour projections; refine the
construction schedule; and set up the construction site. Although planning is a
never -ending process on a project, the planning phase focused on developing
sufficient details to allow various parts of t he project team to coordinate their
work and allow the project management team to make priority decisions.
The implementation phase represents the work done to meet the
requirements of the scope of work and fulfil the charter. During the
implementation ph ase, the project team accomplished the work defined in the
plan and made adjustments when the project factors changed. Equipment and
materials were delivered to the work site, labour was hired and trained, a
construction site was built, and all the constru ction activities, from the arrival
of the first dozer to the installation of the final light switch, were
accomplished.
The closeout phase included turning over the newly constructed plant
to the operations team of the client. A punch list of a few remain ing
construction items was developed and those items completed. The office in
Catamarca was closed, the office in Buenos Aries archived all the project
documents, and the Chilean office was already working on the next project.
The accounting books were rec onciled and closed, final reports written and
distributed, and the project manager started on a new project.munotes.in
Page 16
161.6 SUMMARY
IT project managers deal with the challenges of interdependent
integrations, rapid technology upgrades, and version changes that can
occur throughout the project timeline.
IT project manager is responsible for setting goals, communicating and
motivating team members and stakeholders, identifying the right resources
for each task, researching, managing change, performing needs
assessment , and properly sequencing tasks.
Stakeholders have a potential to exert positive or negative influence on the
project deliverables.
Project Life Cycle contains initiation, planning, implementation, and
closure.
munotes.in
Page 17
17Module II
2
SOFTWARE PROCESS MODELS
Unit Structure
2.0 Objectives
2.1 Introduction
2.2 Software Process Models:
2.2.1 Waterfall Model
2.2.2 Evolutionary process model
2.2.2.1 Prototype Model
2.2.2.2 Spiral Model
2.2.3 Incremental Process Model
2.2.3.1 Iterative Approach
2.2.3.2 Rapid Application Development Model
2.2.3.3 Joint Application Development Model
2.2.3.4 Concurrent Development Model
2.2.4 Agile Development
2.2.4.1 Extreme Programming
2.2.4.2 Scrum
2.3 Summary
2.0 OBJECTIVES
After going through this unit, you will be able to learn:
Different kind of approaches to built Software
Software development approaches benefits and limitations.
Need for Software Development Models
2.1 INTRODUCTION
Software Process Models were originally proposed to bring order to
the chaos of software development. History has indicated that these
conventional models have brought a certain amount of useful structure to
software engineering work and have provided reas onably effective roadmap
for software teams.munotes.in
Page 18
182.2 SOFTWARE PROCESS MODELS
A software process model (sometimes called a Software Development
Life Cycle or SDLC model) is a simplified representation of a software
process. Each process model represents a process from a particular
perspective and thus only provides partial information about that process. For
example, a process activity model shows the activities and their sequence but
may not show the roles of the people involved in these activities. In thi s
section, I introduce a number of very general process models (sometimes
called process paradigms) and present these from an architectural perspective.
That is, we see the framework of the process but not the details of process
activities. These generic m odels are high -level, abstract descriptions of
software processes that can be used to explain different approaches to
software development. You can think of them as process frameworks that may
be extended and adapted to create more specific software engine ering
processes.
2.2.1 Waterfall Model
Waterfall Model:
The Waterfall Model was the first Process Model to be introduced. It
is also referred to as a linear -sequential life cycle model. It is very simple to
understand and use. In a waterfall model, each phase must be completed
before the next phase can begin and there is no overlapping in the phases.
The Waterfall model is the earliest SDLC approach that was used for
software development.
The waterfall Model illustrates the software development process in a
linear sequential flow. This means that any phase in the development process
begins only if the previous phase is complete. In this waterfall model, the
phases do not overlap.
Waterfall Model –Design:
Waterfall approach was first SDLC Model to be us ed widely in
Software Engineering to ensure success of the project. In "The Waterfall"
approach, the whole process of software development is divided into separate
phases. In this Waterfall model, typically, the outcome of one phase acts as
the input for t he next phase sequentially.
The following illustration is a representation of the different phases of
the Waterfall Model.munotes.in
Page 19
19
The sequential phases in Waterfall model are −
Requirement Gathering and analysis −All possible requirements of the
system to be developed are captured in this phase and documented in a
requirement specification document.
System Design −the requirement specifications from first phase are
studied in this phase and the system design is prepared. This system
design helps in specifying hardware and system requirements and helps in
defining the overall system architecture.
Implementation −with inputs from the system design, the system is fir st
developed in small programs called units, which are integrated in the next
phase. Each unit is developed and tested for its functionality, which is
referred to as Unit Testing.
Integration and Testing −All the units developed in the implementation
phase are integrated into a system after testing of each unit. Post
integration the entire system is tested for any faults and failures.
Deployment of system −Once the functional and non -functional testing is
done; the product is deployed in the customer en vironment or released into
the market.
Maintenance −There are some issues which come up in the client
environment. To fix those issues, patches are released. Also to enhance the
product some better versions are released. Maintenance is done to deliver
these changes in the customer environment.munotes.in
Page 20
20All these phases are cascaded to each other in which progress is seen
as flowing steadily downwards (like a waterfall) through the phases. The next
phase is started only after the defined set of goals are achieved for previous
phase and it is signed off, so the name "Waterfall Model". In this model,
phases do not overlap.
Waterfall Model –Application:
Every software developed is different and requires a suitable SDLC
approach to be followed based on the internal a nd external factors. Some
situations where the use of Waterfall model is most appropriate are −
Requirements are very well documented, clear and fixed.
Product definition is stable.
Technology is understood and is not dynamic.
There are no ambiguous requir ements.
Ample resources with required expertise are available to support the
product.
The project is short.
Waterfall Model -Advantages
The advantages of waterfall development are that it allows for
departmentalization and control. A schedule can be set with deadlines for each
stage of development and a product can proceed through the development
process model phases one by one.
Development moves from concept, through design, implementation,
testing, installation, troubleshooting, and ends up at operatio n and
maintenance. Each phase of development proceeds in strict order.
Some of the major advantages of the Waterfall Model are as follows −
Simple and easy to understand and use
Easy to manage due to the rigidity of the model. Each phase has specific
deliverables and a review process.
Phases are processed and completed one at a time.
Works well for smaller projects where requirements are very well
understood.
Clearly defined stages.
Well understood milestones.
Easy to arrange tasks.
Process and results are well documented.
Waterfall Model –Disadvantages:
The disadvantage of waterfall development is that it does not allow
much reflection or revision. Once an application is in the testing stage, it is
very difficult to go back and change something that was not well -documented
or thought upon in the concept stage.
The major disadvantages of the Waterfall Model are as follows −
No working software is produced until late during the life cycle.
High amounts of risk and uncertainty.munotes.in
Page 21
21Not a good model for complex and object -oriented projects.
Poor model for long and ongoing projects.
Not suitable for the projects where requirements are at a moderate to high
risk of changing. So, risk and uncertainty is high with this process model.
It is difficult to measure progre ss within stages.
Cannot accommodate changing requirements.
Adjusting scope during the life cycle can end a project.
Integration is done as a "big -bang. at the very end, which doesn't allow
identifying any technological or business bottleneck or challenges early.
2.2.2 Evolutionary process model:
Evolutionary model is a combination of Iterative and Incremental
model of software development life cycle. Delivering your system in a big
bang release, delivering it in incremental process over time is the actio n done
in this model. Some initial requirements and architecture envisioning need to
be done.
It is better for software products that have their feature sets redefined
during development because of user feedback and other factors. The
Evolutionary develo pment model divides the development cycle into smaller,
incremental waterfall models in which users are able to get access to the
product at the end of each cycle.
Feedback is provided by the users on the product for the planning
stage of the next cycle a nd the development team responds, often by changing
the product, plan or process. Therefore, the software product evolves with
time.
All the models have the disadvantage that the duration of time from
start of the project to the delivery time of a solutio n is very high. Evolutionary
model solves this problem in a different approach.
Evolutionary model suggests breaking down of work into smaller
chunks, prioritizing them and then delivering those chunks to the customer
one by one. The number of chunks is h uge and is the number of deliveries
made to the customer. The main advantage is that the customer’s confidence
increases as he constantly gets quantifiable goods or services from the
beginning of the project to verify and validate his requirements. The mod el
allows for changing requirements as well as all work in broken down into
maintainable work chunks.
2.2.2.1 Prototype Model
Prototype methodology is defined as a Software Development model
in which a prototype is built, tests, and then reworked when ne eded until an
acceptable prototype is achieved. It also creates a base to produce the final
system.munotes.in
Page 22
22Software prototyping model works best in scenarios where the
project's requirement are not known. It is an iterative, trial, and error method
which take pla ce between the developer and the client.
Prototyping Model Phases
Prototyping Model has following six SDLC phases as follow:
Step 1: Requirements gathering and analysis
A prototyping model starts with requirement analysis. In this phase,
the requiremen ts of the system are defined in detail. During the process, the
users of the system are interviewed to know what their expectation from the
system is.
Step 2: Quick design
The second phase is a preliminary design or a quick design. In this
stage, a simple design of the system is created. However, it is not a complete
design. It gives a brief idea of the system to the user. The quick design helps
in developing the prototype.
Step 3: Build a Prototype
In this phase, an actual prototype is designed based on the information
gathered from quick design. It is a small working model of the required
system.
Step 4: Initial user evaluation
In this stage, the proposed system is presented to the client for an
initial evaluation. It helps to find out the strength and weakness of the working
model. Comment and suggestion are collected from the customer and
provided to the developer.
Step 5: Refining prototype
If the user is not happy with the current prototype, you need to refine
the prototype according to the user's f eedback and suggestions.
This phase will not over until all the requirements specified by the user
are met. Once the user is satisfied with the developed prototype, a final system
is developed based on the approved final prototype.
Step 6: Implement Prod uct and Maintain
Once the final system is developed based on the final prototype, it is
thoroughly tested and deployed to production. The system undergoes routine
maintenance for minimizing downtime and prevents large -scale failures.munotes.in
Page 23
23Four types of Prototyp ing models are:
Rapid Throwaway prototypes
Evolutionary prototype
Incremental prototype
Extreme prototype
Rapid Throwaway Prototype:
Rapid throwaway is based on the preliminary requirement. It is
quickly developed to show how the requirement will look vis ually. The
customer's feedback helps drives changes to the requirement, and the
prototype is again created until the requirement is base lined. In this method, a
developed prototype will be discarded and will not be a part of the ultimately
accepted protot ype. This technique is useful for exploring ideas and getting
instant feedback for customer requirements.
Evolutionary Prototyping:
Here, the prototype developed is incrementally refined based on
customer's feedback until it is finally accepted. It helps you to save time as
well as effort. That's because developing a prototype from scratch for every
interaction of the process can sometimes be very frustrating.
This model is helpful for a project which uses a new technology that is
not well understood. It is also used for a complex project where every
functionality must be checked once. It is helpful when the requirement is not
stable or not understood clearly at the initial stage.
Incremental Prototyping:
In incremental Prototyping, the final product is d ecimated into
different small prototypes and developed individually. Eventually, the
different prototypes are merged into a single product. This method is helpful
to reduce the feedback time between the user and the application development
team.
Extreme P rototyping:
Extreme prototyping method is mostly used for web development. It is
consists of three sequential phases.
Basic prototype with the entire existing page is present in the HTML
format. You can simulate data process using a prototype services lay er. The
services are implemented and integrated into the final prototype. Best
practices of Prototyping. Here, are a few things which you should watch for
during the prototyping process:
You should use Prototyping when the requirements are unclear. It is
important to perform planned and controlled Prototyping. Regular meetings
are vital to keep the project on time and avoid costly delays. The users and the
designers should be aware of the prototyping issues and pitfalls. At a very
early stage, you need to approve a prototype and only then allow the team to
move to the next step.munotes.in
Page 24
24In software prototyping method, you should never be afraid to change
earlier decisions if new ideas need to be deployed. You should select the
appropriate step size for each version . Implement important features early on
so that if you run out of the time, you still have a worthwhile system
Advantages of the Prototyping Model
Here, are important pros/benefits of using Prototyping models:
Users are actively involved in development. T herefore, errors can be
detected in the initial stage of the software development process.
Missing functionality can be identified, which helps to reduce the risk of
failure as Prototyping is also considered as a risk reduction activity.
Helps team membe r to communicate effectively.
Customer satisfaction exists because the customer can feel the product at a
very early stage. There will be hardly any chance of software rejection.
Quicker user feedback helps you to achieve better software development
solutions. It allows the client to compare if the software code matches the
software specification.
It helps you to find out the missing functionality in the system. It also
identifies the complex or difficult functions that encourage innovation and
flexible d esigning.
It is a straightforward model, so it is easy to understand. No need for
specialized experts to build the model.
The prototype serves as a basis for deriving a system specification.
The prototype helps to gain a better understanding of the cust omer's needs.
Prototypes can be changed and even discarded.
Prototype also serves as the basis for operational specifications.
Prototypes may offer early training for future users of the software system.
Disadvantages of the Prototyping Model:
Prototypi ng is a slow and time taking process.
The cost of developing a prototype is a total waste as the prototype is
ultimately thrown away.
Prototyping may encourage excessive change requests.
Sometimes customers may not be willing to participate in the iteratio n
cycle for the longer time duration.
There may be far too many variations in software requirements when each
time the prototype is evaluated by the customer.
The poor documentation because the requirements of the customers are
changing.
It is very difficu lt for software developers to accommodate all the changes
demanded by the clients.munotes.in
Page 25
25After seeing an early prototype model, the customers may think that the
actual product will be delivered to him soon.
The client may lose interest in the final product when he or she is not
happy with the initial prototype.
Developers who want to build prototypes quickly may end up building
sub-standard development solutions.
2.2.2.2 Spiral Model
Spiral Model:
The spiral model combines the idea of iterative development with the
systematic, controlled aspects of the waterfall model. This Spiral model is a
combination of iterative development process model and sequential linear
development model i.e. the waterfall model with a very high emphasis on risk
analysis. It allows inc remental releases of the product or incremental
refinement through each iteration around the spiral.
Spiral Model –Design:
The spiral model has four phases. A software project repeatedly passes
through these phases in iterations called Spirals.
Identifi cation:
This phase starts with gathering the business requirements in the
baseline spiral. In the subsequent spirals as the product matures, identification
of system requirements, subsystem requirements and unit requirements are all
done in this phase. Thi s phase also includes understanding the system
requirements by continuous communication between the customer and the
system analyst. At the end of the spiral, the product is deployed in the
identified market.
Design:
The Design phase starts with the conce ptual design in the baseline
spiral and involves architectural design, logical design of modules, physical
product design and the final design in the subsequent spirals.
Construct or Build:
The Construct phase refers to production of the actual software
product at every spiral. In the baseline spiral, when the product is just thought
of and the design is being developed a POC (Proof of Concept) is developed
in this phase to get customer feedback. Then in the subsequent spirals with
higher clarity on requir ements and design details a working model of the
software called build is produced with a version number. These builds are sent
to the customer for feedback.
Evaluation and Risk Analysis:
Risk Analysis includes identifying, estimating and monitoring the
technical feasibility and management risks, such as schedule slippage and cost
overrun. After testing the build, at the end of first iteration, the customer
evaluates the software and provides feedback. The following illustration is amunotes.in
Page 26
26representation of the Spiral Model, listing the activities in each phase. Based
on the customer evaluation, the software development process enters the next
iteration and subsequently follows the linear approach to implement the
feedback suggested by the customer. The process o f iterations along the spiral
continues throughout the life of the software.
Spiral Model Application:
The Spiral Model is widely used in the software industry as it is in
sync with the natural development process of any product, i.e. learning with
maturi ty which involves minimum risk for the customer as well as the
development firms.
The following pointers explain the typical uses of a S piral Model −
When there is a budget constraint and risk evaluation is important.
For medium to high -risk projects.
Long -term project commitment because of potential changes to economic
priorities as the requirements change with time.
Customer is not sure of their requirements which are usually the case.
Requirements are complex and need evaluation to get clarity.
New product line which should be released in phases to get enough
customer feedback.
Significant changes are expected in the product during the d evelopment
cycle.
Spiral Model -Pros and Cons:
The advantage of spiral lifecycle model is that it allows elements of
the product to be added in, when they become available or known. This
assures that there is no conflict with previous requirements and de sign.
This method is consistent with approaches that have multiple software
builds and releases which allows making an orderly transition to a
maintenance activity. Another positive aspect of this method is that the spiral
model forces an early user invol vement in the system development effort.
On the other side, it takes a very strict management to complete such
products and there is a risk of running the spiral in an indefinite loop. So, the
discipline of change and the extent of taking change requests is very important
to develop and deploy the product successfully.
The advantages of the Spiral SDLC Model are as follows −
Changing requirements can be accommodated.
Allows extensive use of prototypes.
Requirements can be captured more accurately.
Users s ee the system early.
Development can be divided into smaller parts and the risky parts can be
developed earlier which helps in better risk management.munotes.in
Page 27
27The disadvantages of the Spiral SDLC Model are as follows −
Management is more complex.
End of the proje ct may not be known early.
Not suitable for small or low risk projects and could be expensive for
small projects.
Process is complex
Spiral may go on indefinitely.
Large number of intermediate stages requires excessive documentation.
2.2.3 Incremental Pro cess Model
Incremental process model is also known as successive version model.
First, a simple working system implementing only a few basic features
is built and then that is delivered to the customer. Then thereafter many
successive iterations/ versions are implemented and delivered to the customer
until the desired system is released.
A, B, C are modules of Software Product that are incrementally
developed and delivered.
Life cycle activities –
Requirements of Software are first broken down into sev eral modules
that can be incrementally constructed and delivered. At any time, the plan is
made just for the next increment and not for any kind of long term plans.
Therefore, it is easier to modify the version as per the need of the customer.
Development Team first undertakes to develop core features (these do not
need services from other features) of the system.
Once the core features are fully developed, then these are refined to
increase levels of capabilities by adding new functions in Successive vers ions.
Each incremental version is usually developed using an iterative waterfall
model of development.
As each successive version of the software is constructed and
delivered, now the feedback of the Customer is to be taken and these were
then incorporate d in the next version. Each version of the software has more
additional features over the previous ones.munotes.in
Page 28
28
After Requirements gathering and specification, requirements are then
spitted into several different versions starting with version -1, in each
succe ssive increment, next version is constructed and then deployed at the
customer site. After the last version (version n), it is now deployed at the
client site.
Types of Incremental model –
1.Staged Delivery Model –Construction of only one part of the proje ct at a
time.
2.Parallel Development Model –Different subsystems are developed at the
same time. It can decrease the calendar time needed for the development,
i.e. TTM (Time to Market), if enough Resources are available.
When to use this –
1. Funding Sc hedule, Risk, Program Complexity, or need for early realization
of benefits.
2. When Requirements are known up -front.
3. When Projects having lengthy developments schedules.
4. Projects with new Technology.
Advantages –
Error Reduction (core modules are u sed by the customer from the
beginning of the phase and then these are tested thoroughly)
Uses divide and conquer for breakdown of tasks.
Lowers initial delivery cost.
Incremental Resource Deployment.munotes.in
Page 29
29Disadvantages –
Requires good planning and design.
Total cost is not lower.
Well defined module interfaces are required.
2.2.3.1 Iterative Approach
In an Iterative Incremental model, initially, a partial implementation of
a total system is constructed so that it will be in a deliverable state. Increased
functionality is added. Defects, if any, from the prior delivery are fixed and
the working product is delivered. The process is repeated until the entire
product development is completed. The repetitions of these processes are
called iterations. At the end of every iteration, a product increment is
delivered.
Iterative Incremental Model –Strengths
The advantages or strengths of Iterative Incremental model are −
You can develop prioritized requirements first.
Initial product delivery is faster.
Customers gets important functionality early.
Lowers initial delivery cost.
Each release is a product incre ment, so that the customer will have a
working product at hand all the time.
Customer can provide feedback to each product increment, thus avoiding
surprises at the end of development.
Requirements changes can be easily accommodated.
Iterative Incremental Model –Weaknesses
The disadvantages of the Iterative Incremental model are −
Requires effective planning of iterations.
Requires efficient design to ensure inclusion of the required functionality
and provision for changes later.
Requires early definition of a complete and f ully functional system to
allow the definition of increments.
Well-defined module interfaces are required, as some are developed long
before others are developed.
Total cost of the complete system is not lower.
When to Use Iterative Incremental Model?
Iterative Incremental model can be used when −
Most of the requirements are known up -front but are expected to evolve
over time.
The requirements are prioritized.
There is a need to get the basic functionality delivered fast.
A project has lengthy development schedules.
A project has new technology.
The domain is new to the team.munotes.in
Page 30
302.2.3.2 Rapid Application Development
RAD (Rapid Application Development) model:
The RAD (Rapid Application Development) model is based on
prototyping and iterative development wit h no specific planning involved. The
process of writing the software itself involves the planning required for
developing the product.
Rapid Application Development focuses on gathering customer
requirements through workshops or focus groups, early testin g of the
prototypes by the customer using iterative concept, reuse of the existing
prototypes (components), continuous integration and rapid delivery.
What is RAD?
Rapid application development is a software development
methodology that uses minimal plann ing in favour of rapid prototyping. A
prototype is a working model that is functionally equivalent to a component of
the product. In the RAD model, the functional modules are developed in
parallel as prototypes and are integrated to make the complete produ ct for
faster product delivery. Since there is no detailed preplanning, it makes it
easier to incorporate the changes within the development process. RAD
projects follow iterative and incremental model and have small teams
comprising of developers, domain experts, customer representatives and other
IT resources working progressively on their component or prototype. The
most important aspect for this model to be successful is to make sure that the
prototypes developed are reusable.
RAD Model Design
RAD mode l distributes the analysis, design, build and test phases into
a series of short, iterative development cycles.
Following are the various phases of the RAD Model −
Business Modelling:
The business model for the product under development is designed in
terms of flow of information and the distribution of information between
various business channels. A complete business analysis is performed to find
the vital information for business, how it can be obtained, how and when is
the information processed and wha t are the factors driving successful flow of
information.
Data Modelling:
The information gathered in the Business Modeling phase is reviewed
and analyzed to form sets of data objects vital for the business. The attributes
of all data sets is identified a nd defined. The relation between these data
objects are established and defined in detail in relevance to the business
model.
Process Modelling:
The data object sets defined in the Data Modeling phase are converted
to establish the business information fl ow needed to achieve specific businessmunotes.in
Page 31
31objectives as per the business model. The process model for any changes or
enhancements to the data object sets is defined in this phase. Process
descriptions for adding, deleting, retrieving or modifying a data objec ta r e
given.
Application Generation:
The actual system is built and coding is done by using automation
tools to convert process and data models into actual prototypes.
Testing and Turnover:
The overall testing time is reduced in the RAD model as the prot otypes
are independently tested during every iteration. However, the data flow and
the interfaces between all the components need to be thoroughly tested with
complete test coverage. Since most of the programming components have
already been tested, it red uces the risk of any major issues.
The following illustration describes the RAD Model in detail.
RAD Model Vs Traditional SDLC:
The traditional SDLC follows a rigid process models with high
emphasis on requirement analysis and gathering before the coding starts. It
puts pressure on the customer to sign off the requirements before the project
starts and the customer doesn’t get the feel of the product as there is no
working build available for a long time. The customer may need some
changes after he gets t o see the software. However, the change process is quite
rigid and it may not be feasible to incorporate major changes in the product in
the traditional SDLC. The RAD model focuses on iterative and incremental
delivery of working models to the customer. Th is results in rapid delivery to
the customer and customer involvement during the complete development
cycle of product reducing the risk of non -conformance with the actual user
requirements.
RAD Model –Application:
RAD model can be applied successfully t o the projects in which clear
modularization is possible. If the project cannot be broken into modules, RAD
may fail.
The following pointers describe the typical scenarios where RAD can
be used −
RAD should be used only when a system can be modularized to be
delivered in an incremental manner.
It should be used if there is a high availability of designers for modeling.
It should be used only if the budget permits use of automated code
generating tools.
RAD SDLC model should be chosen only if domain experts are available
with relevant business knowledge.
Should be used where the requirements change during the project and
working prototypes are to be presented to customer in small iterations of
2-3 months.munotes.in
Page 32
32RAD Model -Pros and Cons
RAD model enables rapid del ivery as it reduces the overall
development time due to the reusability of the components and parallel
development. RAD works well only if high skilled engineers are available and
the customer is also committed to achieve the targeted prototype in the give n
time frame. If there is commitment lacking on either side the model may fail.
The advantages of the RAD Model are as follows −
Changing requirements can be accommodated.
Progress can be measured.
Iteration time can be short with use of powerful RAD tools.
Productivity with fewer people in a short time.
Reduced development time.
Increases reusability of components.
Quick initial reviews occur.
Encourages customer feedback.
Integration from very beginning solves a lot of integration issues.
The disadvantages of the RAD Model are as follows −
Dependency on technically strong team membe rs for identifying business
requirements.
Only system that can be modularized can be built using RAD.
Requires highly skilled developers/designers.
High dependency on modelling skills.
Inapplicable to cheaper projects as cost of modelling and automated cod e
generation is very high.
Management complexity is more.
Suitable for systems that are component based and scalable.
Requires user involvement throughout the life cycle.
Suitable for project requiring shorter development times.
2.2.3.3 Joint Application Development Model
Collaboration and then building software is the key power which
drives technology and its innovation. JAD is a model for software
development that augments the stakeholders' association in cycles of software
development. Its life cycle ha s been adopted for areas of dynamic software
development method. It collects business and system requirements while
building a new information system for any organization or enterprise. In this
chapter, you will learn about the JAD model in detail.
JAD (J oint Application Development) Approach:
JAD (Joint Application Development) is a software development
approach which engages the client and/or the end users for designing and
developing the system. This model was designed and put forward by Dr.
Chuck Morri s and Dr. Tony Crawford of IBM, who propose this model in the
late 1970s. As compared to other primitive SDLC model, Joint Application
Development model leads to faster progression of the system development
which has better client approval.munotes.in
Page 33
33This model furt hermore, is vast when it comes to agile delivery
wherein the software products need to be developed as well as shipped in
short iterations depending on agreements among the industrial as well as
industry stakeholders which are termed as Minimum Viable Prod uct (MVP).
Phases of JAD Model: Since you have become familiar with the JAD
concept, it is time to know about its phases and how the model's design and
development approach works:
Define Specific Objectives: The facilitator, in partnership with stakehol ders,
set all the objectives as well as a list of items which is then distributed to other
developers and participants to understand and review. This objective contains
elements like the scope of this projected system, its potential outcome,
technical spec ification required, etc.
Session Preparation: The facilitator is solely responsible for this preparation
where all relevant data is collected and sent to other members before time. For
better insight, research carried out to know about the system requirem ent
better and gather all the necessary information for development.
Session Conduct: Here the facilitator is accountable to identify those issues
which have to be working out for making the system error -free. Here the
facilitator will serve as a particip ant but will not have a say regarding any
information.
Documentation: After the product is developed, the records and published
documents are put forward into the meeting so that the stakeholders and
consumers can approve it through the meeting.
Benefits of using JAD Model:
Improved Delivery Time: The time required for developing a product
using JAD model is lesser and efficient than that of other traditional
models.
Cost Reduction: Efficiently analyzing the requirements and facts with
business executive s and stakeholders will make less effort to develop the
system and hence less cost will be required for the entire development
process.
Better Understanding: Since the entire requirement is analyzed by
business executives, followed by a cautious choice of developers and team
member who can professionally interact with each other better usually
helps in understanding the product development better.
Improved Quality: Since all the key decision makers and stakeholders of
the project are involved in the devel opment of the project so there is the
least chance of error and hence the product quality becomes better and
more accurate.munotes.in
Page 34
342.2.3.4 Concurrent Development Model
` The concurrent development model
The concurrent development model is called as concurrent model.
The communication activity has completed in the first iteration and exits
in the awaiting changes state.
The modelling activity completed its initial communication and then goes
to the underdevelopment state.
If the customer specifies the change in the requirement, then the modelling
activity moves from the under development state into the awaiting change
state.
The concurrent process model activities moving from one state to another
state
.
Advantages of the concurrent development model
This model is applicable to all types of software development processes.
It is easy to understand and use.
It gives immediate feedback from testing.
It provides an accurate picture of the current state of a project.
Disadvantages of the concurrent development model
It needs better communication between the team members. This may not
be achieved all the time.
It requires remembering the status of the different activities.
2.2.4 Agile Development
Agile is a time -bound, iterative approach to software delivery that
builds software incrementally from the start of the project, instead of trying to
deliver all at once.
Why Agile?
Technology in this current era is progressing faster than ever,
enforcing the global software companies to work in a fast -paced changing
environm ent. Because these businesses are operating in an ever -changing
environment, it is impossible to gather a complete and exhaustive set of
software requirements. Without these requirements, it becomes practically
hard for any conventional software model to w ork.
The conventional software models such as Waterfall Model that
depends on completely specifying the requirements, designing, and testing the
system are not geared towards rapid software development. As a consequence,
a conventional software developmen t model fails to deliver the required
product.
This is where agile software development comes to the rescue. It was
specially designed to curate the needs of the rapidly changing environment by
embracing the idea of incremental development and developing the actual
final product.munotes.in
Page 35
35Let’s now read about the on which the Agile has laid its foundation:
Principles:
1. Highest priority is to satisfy the customer through early and continuous
delivery of valuable software.
2. It welcomes changing requirements, eve n late in development.
3. Deliver working software frequently, from a couple of weeks to a couple of
months, with a preference to the shortest timescale.
4. Build projects around motivated individuals. Give them the environment
and the support they need, and trust them to get the job done.
5. Working software is the primary measure of progress.
6. Simplicity the art of maximizing the amount of work not done is essential.
7. The most efficient and effective method of conveying information to and
within a de velopment team is face -to-face conversation.
Development in Agile: Let’s see a brief overview of how development occurs
in agile philosophy.
In Agile development, Design and Implementation are considered to be
the central activities in the software proces s.
Design and Implementation phase also incorporate other activities such as
requirements elicitation and testing into it.
In an agile approach, iteration occurs across activities. Therefore, the
requirements and the design are developed together, rather t han separately.
The allocation of requirements and the design planning and development
as executed in a series of increments. In contrast with the conventional
model, where requirements gathering needs to be completed in order to
proceed to the design and development phase, it gives Agile development
an extra level of flexibility.
An agile process focuses more on code development rather than
documentation.
Example: Let’s go through an example to understand clearly about how agile
actually works.
A Softwar e company named ABC wants to make a new web browser
for the latest release of its operating system. The deadline for the task is 10
months. The company’s head assigned two teams named Team A and Team B
for this task. In order to motivate the teams, the com pany head says that the
first team to develop the browser would be given a salary hike and a one week
full sponsored travel plan. With the dreams of their wild travel fantasies, the
two teams set out on the journey of the web browser. The team A decided to
play by the book and decided to choose the Waterfall model for the
development. Team B after a heavy discussion decided to take a leap of faith
and choose Agile as their development model.munotes.in
Page 36
36The Development plan of the Team A is as follows:
Requirement ana lysis and Gathering –1.5 Months
Design of System –2 Months
Coding phase –4 Months
System Integration and Testing –2 Months
User Acceptance Testing –5 Weeks
The Development plan for the Team B is as follows:
Since this was an Agile, the project was br oken up into several iterations.
The iterations are all of the same time duration.
At the end of each iteration, a working product with a new feature has to
be delivered.
Instead of Spending 1.5 months on requirements gathering, They will
decide the core f eatures that are required in the product and decide which
of these features can be developed in the first iteration.
Any remaining features that cannot be delivered in the first iteration will
be delivered in the next subsequent iteration, based in the pri ority
At the end of the first iterations, the team will deliver working
software with the core basic features.
Both the team have put their best efforts to get the product to a
complete stage. But then out of blue due to the rapidly changing environment,
the company’s head come up with an entirely new set of features and want to
be implemented as quickly as possible and wanted to push out a working
model in 2 days. Team A was now in a fix, they were still in their design
phase and did not yet started codi ng and they had no working model to
display. And moreover, it was practically impossible for them to implement
new features since waterfall model there is not reverting back to the old phase
once you proceed to the next stage that means they would have to start from
the square one again. That would incur them heavy cost and a lot of overtime.
Team B was ahead of Team A in a lot of aspects, all thanks to Agile
Development. They also had the working product with most of the core
requirement since the first in crement. And it was a piece of cake for them to
add the new requirements. All they had to do is schedule these requirements
for the next increment and then implement them.
Advantages:
Deployment of software is quicker and thus helps in increasing the trus t of
the customer.
Can better adapt to rapidly changing requirements and respond faster.
Helps in getting immediate feedback which can be used to improve the
software in the next increment.
People –Not Process. People and interactions are given a higher p riority
rather than process and tools.
Continuous attention to technical excellence and good design.munotes.in
Page 37
37Disadvantages:
In case of large software projects, it is difficult to assess the effort required
at the initial stages of the software development life cy cle.
The Agile Development is more code focused and produces less
documentation.
Agile development is heavily depended on the inputs of the customer. If
the customer has ambiguity in his vision of the final outcome, it is highly
likely for the project to g et off track.
Face to Face communication is harder in large -scale organizations.
Only senior programmers are capable of taking the kind of decisions
required during the development process. Hence it’s a difficult situation
for new programmers to adapt to t he environment.
Agile is a framework which defines how the software development
needs to be carried on. Agile is not a single method, it represents the various
collection of methods and practices that follow the value statements provided
in the manifesto. Agile methods and practices do not promise to solve every
problem present in the software industry (No Software model ever can). But
they sure help to establish a culture and environment where solutions emerge.
2.2.4.1 Extreme Programming
Extreme program ming (XP) is one of the most important software
development framework of Agile models. It is used to improve software
quality and responsive to customer requirements. The extreme programming
model recommends taking the best practices that have worked well in the past
in program development projects to extreme levels.
Good practices needs to practiced extreme programming: Some of the good
practices that have been recognized in the extreme programming model and
suggested to maximize their use are given below :
Code Review: Code review detects and corrects errors efficiently. It
suggests pair programming as coding and reviewing of written code
carried out by a pair of programmers who switch their works between
them every hour.
Testing : Testing code helps to r emove errors and improves its reliability.
XP suggests test -driven development (TDD) to continually write and
execute test cases. In the TDD approach test cases are written even before
any code is written.
Incremental development : Incremental development is very good
because customer feedback is gained and based on this development team
come up with new increments every few days after each iteration.
Simplicity : Simplicity makes it easier to develop good quality code as
well as to test and debug it.munotes.in
Page 38
38Desig n: Good quality design is important to develop a good quality
software. So, everybody should design daily.
Integration testing : It helps to identify bugs at the interfaces of different
functionalities. Extreme programming suggests that the developers shou ld
achieve continuous integration by building and performing integration
testing several times a day.
Basic principles of Extreme programming: XP is based on the frequent
iteration through which the developers implement User Stories. User stories
are simp le and informal statements of the customer about the functionalities
needed. A User story is a conventional description by the user about a feature
of the required system. It does not mention finer details such as the different
scenarios that can occur. On the basis of User stories, the project team
proposes Metaphors. Metaphors are a common vision of how the system
would work. The development team may decide to build a Spike for some
feature. A Spike is a very simple program that is constructed to explore the
suitability of a solution being proposed. It can be considered similar to a
prototype. Some of the basic activities that are followed during software
development by using XP model are given below:
Coding : The concept of coding which is used in XP mode l is slightly
different from traditional coding. Here, coding activity includes drawing
diagrams (modeling) that will be transformed into code, scripting a web -
based system and choosing among several alternative solutions.
Testing : XP model gives high imp ortance on testing and considers it be
the primary factor to develop a fault -free software.
Listening : The developers needs to carefully listen to the customers if
they have to develop a good quality software. Sometimes programmers
may not have the depth knowledge of the system to be developed. So, it is
desirable for the programmers to understand properly the functionality of
the system and they have to listen to the customers.
Designing : Without a proper design, a system implementation becomes
too compl ex and very difficult to understand the solution, thus it makes
maintenance expensive. A good design results elimination of complex
dependencies within a system. So, effective use of suitable design is
emphasized.
Feedback : One of the most important aspec ts of the XP model is to gain
feedback to understand the exact customer needs. Frequent contact with
the customer makes the development effective.
Simplicity : The main principle of the XP model is to develop a simple
system that will work efficiently in p resent time, rather than trying to build
something that would take time and it may never be used. It focuses on
some specific features that are immediately needed, rather than engaging
time and effort on speculations of future requirements.munotes.in
Page 39
39Applications of Extreme Programming (XP): Some of the projects that are
suitable to develop using XP model are given below:
Small projects : XP model is very useful in small projects consisting of
small teams as face to face meeting is easier to achieve.
Projects involvi ng new technology or Research projects: This type of
projects faces changing of requirements rapidly and technical problems.
So XP model is used to complete this type of projects.
1.2.4.2 Scrum
What is Scrum Project Management?
Scrum is an agile project management methodology or framework
used primarily for software development projects with the goal of delivering
new software capability every 2 -4 weeks. It is one of the approaches that
influenced the Agile Manifesto, which articulates a set of values and
principles to guide decisions on how to develop higher -quality software faster.
Who Uses Agile Scrum Methodology?
Scrum is widely used by software development teams. In fact it's the
most popular agile methodology. According to the 12th annual State of A gile
report, 70% of software teams use Scrum or a Scrum hybrid. However, Scrum
has spread to other business functions including IT and marketing where there
are projects that must move forward in the presence of complexity and
ambiguity. Leadership teams a re also basing their agile management practices
on Scrum, often combining it with lean and Kanban practices (subgroups of
agile project management).
What is Scrum in Relation to Agile Project Management?
Scrum is a sub -group of agile:
Agile is a set of va lues and principles that describe a group's day -to-day
interactions and activities. Agile itself is not prescriptive or specific.
The Scrum methodology follows the values and principles of agile, but
includes further definitions and specifications, especi ally regarding certain
software development practices.
Although developed for agile software development, agile Scrum
became the preferred framework for agile project management in general and
is sometimes simply referred to as Scrum project management or Scrum
development.
What is the Benefits Received from the Scrum Methodology?
Organizations that have adopted agile Scrum have experienced:
Higher productivity
Better -quality products
Reduced time to market
Improved stakeholder satisfaction
Better team d ynamics
Happier employeesmunotes.in
Page 40
402.3 SUMMARY
Software development using Waterfall Model approach.
Evolutionary Process Model allows for changing requirements as well as
all work in broken down into maintainable work chunks.
In Prototype Model, prototype is built , tests, and then reworked when
needed until an acceptable prototype is achieved.
Spiral Model allows incremental releases of the product or incremental
refinement through each iteration around the spiral.
Incremental process model is a successive version model.
Agile is a time -bound, iterative approach to software delivery that builds
software incrementally from the start of the project, instead of trying to
deliver all at once.
munotes.in
Page 41
41Module III
3
SOFTWARE REQUIREMENT ANALYSIS
AND SPECIFICATION
Unit Structure
3.0Objectives
3.1 Introduction
3.2 Types of Requirement
3.2.1 Functional Requirement
3.2.2 Non -Functional Requirement
3.3 Requirement Engineerin g Process
3.4. Requirement Analysis and Design
3.4.1 Data Flow Diagram
3.4.2 Data Dictionary
3.4.3 HIPO Chart
3.4.4 Warnier Orr Diagram
3.5 Requirement Elicitation
3.5.1 Interviews
3.5.2 Questionnaire
3.5.3 Brainstorming
3.5.4 Facilitated Applicati on Specification Technique(FAST)
3.5.5 Use Case Approach
3.6 Summary
3.0 OBJECTIVES
The objective of this chapter is to introduce software requirements and
to explain the processes involved in discovering and documenting these
requirements. When you have read the chapter, you will:
Understand the concepts of user and system requirements and why these
requirements should be written in different ways;
Understand the differences between functional and non -functional
software requirements;
Understand the main requirements engineering activities of elicitation,
analysis, and validation, and the relationships between these activities;
Understand why requirements management is necessary and how it
supports other requirements engineering activities.munotes.in
Page 42
423.1 INTRODUCTION
The requirements for a system are the descriptions of the services that
a system should provide and the constraints on its operation. These
requirements reflect the needs of customers for a system that serves a certain
purpose such as controll ing a device, placing an order, or finding information.
The process of finding out, analyzing, documenting and checking these
services and constraints is called requirements engineering (RE).
The term requirement is not used consistently in the software industry.
In some cases, a requirement is simply a high -level, abstract statement of a
service that a system should provide or a constraint on a system. At the other
extreme, it is a detailed, formal definition of a system function.
3.2 TYPES OF REQUIREM ENT
Software system requirements are often classified as functional or non -
functional requirements:
1. Functional requirements:
These are statements of services the system should provide, how the
system should react to particular inputs, and how the system should behave in
particular situations. In some cases, the functional requirements may also
explicitly state what the system should not do.
2. Non-functional requirements:
These are constraints on the services or functions offered by the
system. They inclu de timing constraints, constraints on the development
process, and constraints imposed by standards. Non -functional requirements
often apply to the system as a whole rather than individual system features or
services.
In reality, the distinction between different types of requirements is
not as clear -cut as these simple definitions suggest. A user requirement
concerned with security, such as a statement limiting access to authorized
users, may appear to be a non -functional requirement. However, when
devel oped in more detail, this requirement may generate other requirements
that are clearly functional, such as the need to include user authentication
facilities in the system. This shows that requirements are not independent and
that one requirement often gen erates or constrains other requirements. The
system requirements therefore do not just specify the services or the features
of the system that are required; they also specify the necessary functionality to
ensure that these services/features are delivered effectively.
3.2.1 Functional Requirement
The functional requirements for a system describe what the system
should do. These requirements depend on the type of software being
developed, the expected users of the software, and the general approach taken
bythe organization when writing requirements. When expressed as usermunotes.in
Page 43
43requirements, functional requirements should be written in natural language so
that system users and managers can understand them. Functional system
requirements expand the user requiremen ts and are written for system
developers. They should describe the system functions, their inputs and
outputs, and exceptions in detail.
Functional system requirements vary from general requirements
covering what the system should do to very specific requ irements reflecting
local ways of working or an organization’s existing systems. For example,
here are examples of functional requirements for the Mentcare system, used to
maintain information about patients receiving treatment for mental health
problems:
1.A user shall be able to search the appointments lists for all clinics.
2.The system shall generate each day, for each clinic, a list of patients who
are expected to attend appointments that day.
3.Each staff member using the system shall be uniquely identifie d by his or
her eight -digit employee number.
These user requirements define specific functionality that should be
included in the system. The requirements show that functional requirements
may be written at different levels of detail (contrast requirement s 1 and 3).
Functional requirements, as the name suggests, have traditionally
focused on what the system should do. However, if an organization decides
that an existing off -the-shelf system software product can meet its needs, then
there is very little po int in developing a detailed functional specification. In
such cases, the focus should be on the development of information
requirements that specify the information needed for people to do their work.
Information requirements specify the information neede d and how it is to be
delivered and organized. Therefore, an information requirement for the
Mentcare system might specify what information is to be included in the list
of patients expected for appointments that day.
Imprecision in the requirements spec ification can lead to disputes
between customers and software developers. It is natural for a system
developer to interpret an ambiguous requirement in a way that simplifies its
implementation. Often, however, this is not what the customer wants. New
requi rements have to be established and changes made to the system. Of
course, this delays system delivery and increases costs.
For example, the first Mentcare system requirement in the above list
states that a user shall be able to search the appointments lis ts for all clinics.
The rationale for this requirement is that patients with mental health problems
are sometimes confused. They may have an appointment at one clinic but
actually go to a different clinic. If they have an appointment, they will be
recorded as having attended, regardless of the clinic.
A medical staff member specifying a search requirement may expect
“search” to mean that, given a patient name, the system looks for that name inmunotes.in
Page 44
44all appointments at all clinics. However, this is not explicit in the requirement.
System developers may interpret the requirement so that it is easier to
implement. Their search function may require the user to choose a clinic and
then carry out the search of the patients who attended that clinic. This involves
more user input and so takes longer to complete the search.
Ideally, the functional requirements specification of a system should
be both complete and consistent. Completeness means that all services and
information required by the user should be defined. Cons istency means that
requirements should not be contradictory.
In practice, it is only possible to achieve requirements consistency and
completeness for very small software systems. One reason is that it is easy to
make mistakes and omissions when writing s pecifications for large, complex
systems. Another reason is that large systems have many stakeholders, with
different backgrounds and expectations. Stakeholders are likely to have
different —and often inconsistent —needs. These inconsistencies may not be
obvious when the requirements are originally specified, and the inconsistent
requirements may only be discovered after deeper analysis or during system
development.
3.2.2 Non -Functional Requirement
Non-functional requirements, as the name suggests, are requ irements
that are not directly concerned with the specific services delivered by the
system to its users. These non -functional requirements usually specify or
constrain characteristics of the system as a whole. They may relate to
emergent system properties such as reliability, response time, and memory
use. Alternatively, they may define constraints on the system implementation,
such as the capabilities of I/O devices or the data representations used in
interfaces with other systems.
Non-functional require ments are often more critical than individual
functional requirements. System users can usually find ways to work around a
system function that doesn’t really meet their needs. However, failing to meet
a non -functional requirement can mean that the whole s ystem is unusable. For
example, if an aircraft system does not meet its reliability requirements, it will
not be certified as safe for operation; if an embedded control system fails to
meet its performance requirements,
The control functions will not oper ate correctly.
While it is often possible to identify which system components
implement specific functional requirements (e.g., there may be formatting
components that implement reporting requirements), this is often more
difficult with non -functional requ irements. The implementation of these
requirements may be spread throughout the system, for two reasons:
1. Non-functional requirements may affect the overall architecture of a
system rather than the individual components. For example, to ensure that
perform ance requirements are met in an embedded system, you may have to
organize the system to minimize communications between components.munotes.in
Page 45
452. An individual non -functional requirement, such as a security
requirement, may generate several, related functional requireme nts that define
new system services that are required if the non -functional requirement is to
be implemented. In addition, it may also generate requirements that constrain
existing requirements; for example, it may limit access to information in the
system .
Figure: Types of Non -Functional Requirements
Non-functional requirements arise through user needs because of
budget constraints, organizational policies, the need for interoperability with
other software or hardware systems, or external factors such as safety
regulations or privacy legislation. Above figure is a classification of non -
functional requirements. You can see from this diagram that the non -
functional requirements may come from required characteristics of the
software (product requirements) , the organization developing the software
(organizational requirements), or external sources:
1. Product requirements: These requirements specify or constrain the
runtime behaviour of the software. Examples include performance
requirements for how fast the system must execute and how much memory it
requires; reliability requirements that set out the acceptable failure rate;
security requirements; and usability requirements.
2. Organizational requirements: These requirements are broad system
requirements derive d from policies and procedures in the customer’s and
developer’s organizations. Examples include operational process requirements
that define how the system will be used; development process requirements
that specify the programming language; the developme nt environment or
process standards to be used; and environmental requirements that specify the
operating environment of the system.
3. External requirements: This broad heading covers all requirements
that are derived from factors external to the system and its developmentmunotes.in
Page 46
46process. These may include regulatory requirements that set out what must be
done for the system to be approved for use by a regulator, such as a nuclear
safety authority; legislative requirements that must be followed to ensure that
the s ystem operates within the law; and ethical requirements that ensure that
the system will be acceptable to its users and the general public.
3.3.REQUIREMENT ENGINEERING PROCESS
Requirements engineering involves three key activities. These are
discovering requirements by interacting with stakeholders (elicitation and
analysis); converting these requirements into a standard form (specification);
and checking that the requirements actually define the system that the
customer wants (validation). Requirements engineering is an iterative process
in which the activities are interleaved.
The activities are organized as an iterative process around a spiral. The
output of the RE process is a system requirements document. The amount of
time and effort devoted to eac h activity in iteration depends on the stage of the
overall process, the type of system being developed, and the budget that is
available.
Early in the process, most effort will be spent on understanding high -
level business and non -functional requirements , and the user requirements for
the system. Later in the process, in the outer rings of the spiral, more effort
will be devoted to eliciting and understanding the non -functional requirements
and more detailed system requirements.
This spiral model accommo dates approaches to development where
the requirements are developed to different levels of detail. The number of
iterations around the spiral can vary so that the spiral can be exited after some
or all of the user requirements have been elicited. Agile de velopment can be
used instead of prototyping so that the requirements and the system
implementation are developed together.
In virtually all systems, requirements change. The people involved
develop a better understanding of what they want the software to do; the
organization buying the system changes; and modifications are made to the
system’s hardware, software, and organizational environment. Changes have
to be managed to understand the impact on other requirements and the cost
and system implications o f making the change.munotes.in
Page 47
47
Figure: Spiral View
3.4.REQUIREMENT ANALYSIS AND DESIGN
Some of the problems that arise during the requirements engineering
process are a result of failing to make a clear separation between these
different levels of description. I distinguish between them by using the term
user requirements to mean the high -level abstract requirements and system
requirements to mean the detailed description of what the system should do.
User requirements and system requirements may be defined as follows:
1. User requirements are statements, in a natural language plus diagrams,
of what services the system is expected to provide to system users and the
constraints under which it must operate. The user requirements may vary from
broad statements of the system features required to detailed, precise
descriptions of the system functionality.
2. System requirements are more detailed descriptions of the software
system’s functions, services, and operational constraints. The system
requirements document (someti mes called a functional specification) should
define exactly what is to be implemented. It may be part of the contract
between the system buyer and the software developers.
Different kinds of requirement are needed to communicate information
about a syste m to different types of reader. You need to write requirements at
different levels of detail because different types of readers use them in
different ways. The readers of the user requirements are not usually concernedmunotes.in
Page 48
48with how the system will be implement ed and may be managers who are not
interested in the detailed facilities of the system. The readers of the system
requirements need to know more precisely what the system will do because
they are concerned with how it will support the business processes or because
they are involved in the system implementation. System stakeholders include
anyone who is affected by the system in some way and so anyone who has a
legitimate interest in it. Stakeholders range from end -users of a system
through managers to exter nal stakeholders such as regulators who certify the
acceptability of the system.
3.4.1 Data Flow Diagram
Introduction to data -flow diagrams
What are data -flow diagrams?
Data-flow diagrams (DFDs) model a perspective of the system that is
most readily und erstood by users –The flow of information through the
system and the activities that process this information.
Data-flow diagrams provide a graphical representation of the system
that aims to be accessible to computer specialist and non -specialist users alike.
The models enable software engineers, customers and users to work together
effectively during the analysis and specification of requirements. Although
this means that our customers are required to understand the modelling
techniques and constructs, in data -flow modelling only a limited set of
constructs are used, and the rules applied are designed to be simple and easy
to follow. These same rules and constructs apply to all data -flow diagrams
(i.e., for each of the different software process activiti es in which DFDs can
be used).
The benefits of data -flow diagrams
Data-flow diagrams provide a very important tool for software
engineering, for a number of reasons:
• The system scope and boundaries are clearly indicated on the diagrams
(more will be de scribed about the boundaries of systems and each DFD later
in this chapter).
• The technique of decomposition of high level data -flow diagrams to a set of
more detailed diagrams provides an overall view of the complete system, as
well as a more detailed b reakdown and description of individual activities,
where this is appropriate, for clarification and understanding.
The different kinds (and levels) of data -flow diagrams:
Although all data -flow diagrams are composed of the same types of
symbols, and the v alidation rules are the same for all DFDs, there are three
main types of data -flow diagram:
Data-Flow Diagramsmunotes.in
Page 49
49•Context diagrams —context diagram DFDs are diagrams that present an
overview of the system and its interaction with the rest of the “world”.
•Level 1 data -flow diagrams —Level 1 DFDs present a more detailed view
of the system than context diagrams, by showing the main sub -processes and
stores of data that make up the system as a whole.
munotes.in
Page 50
50• Level 2 (and lower) data -flow diagrams —a major advantage of the data -
flow modelling technique is that, through a technique called “levelling”, the
detailed complexity of real world systems can be managed and modelled in a
hierarchy of abstractions. Certain elements of any dataflow diagram can be
decom posed (“exploded”) into a more detailed model a level lower in the
hierarchy.
During this unit we shall investigate each of the three types of diagram
in the sequence they are described above. This is both a sequence of
increasing complexity and sophis tication, and also the sequence of DFDs that
is usually followed when modelling systems.
For each type of diagram we shall first investigate what the features of
the diagram are, and then we shall investigate how to create that type of
diagram. However, b efore looking at particular kinds of dataflow diagrams,
we shall briefly examine each of the symbols from which DFDs are
composed.
3.4.2 Data Dictionary
There is a wide range of definitions for Data Dictionary /Directory
Systems (DD/DS). Due to the incre asing interest and the rapidly evolving
nature of this field in recent years, terminology is somewhat confusing. One
author speaks of a Data Dictionary System (DDS) or System Resources
Dictionary, while another refers to DD/DS or Data Element
Dictionary/Di rectory System, (DED/DS). Characteristic definitions include
those of:munotes.in
Page 51
51Leong -Hong and Marron (1977):
The DED/DS is a software tool that provides the means for defining
and describing the characteristics of a database, as opposed to the contents of
a database.
National Bureau of Standards (NBS) (1978):
The DED/DS is considered as a resource manager. It is an integrated
repository that provides data necessary for managing data. Data management
includes the planning, control, direction, and organization of data.
Allen, Loomis and Hannino (1982):
ADD/DS is an automated information system. It helps to achieve
control of the data resource, by providing an inventory of that resource. It
helps to control the cost of developing and maintaining applications. Fin ally it
can provide for independence of metadata across comput¬ing environments,
improving resiliency to the effects of hardware and software changes
Data has positive or negative value. The value of the data derives from
the fact that the entire enterpri se depends on its availability for the proper
management of all other resources. Thus, it must be treated as a resource. The
management and control of data resources begins with a proper definition and
description of data. A DD/DS is a tool for the control and management of data
as a resource.
To manage data as a resource it is basic that data about data must be
clearly specified, easily accessible and well controlled. These data are called
metadata. These are data objects, that in a data processing enviro nment are
represented in the form of elements, records, files or databases. Metadata is
not user data, but identifies, defines and describes the characteristics of the
latter. It describes the data resources of an organization. A DD/DS contains
two types o f metadata: Dictionary and Directory metadata. Dictionary
metadata describes the data, and defines their meaning and structure.
Directory metadata describes where the data is stored, and how internally
represented and accessed.
A collection of related met adata comprises the metadata database. It
consists of a database that contains descriptive and definitional information
about the user database. It has basically the same characteristics of a user
database. To achieve the goals of managing data as a resour ce it requires
proper management. That is, planning for the design, implementation,
maintenance, utilization and control. This implies that established lines of
responsibility and authority; formal rules and detailed procedures to guide
metadata -related a ctivities; common procedures for collection, update, and
maintenance; and common procedures for access control to the metadata must
be developed. The DD/DS is the basic tool for managing the metadata
database.
The DD/DS is divided into three categories, b ased on the scope of
control exercised through metadata management: Active, Potentially Active
and Passive. A DD/DS is said to be active with respect to a program ormunotes.in
Page 52
52process if that program or process is fully dependent on the DD/DS for its
metadata. A DD/ DS is said to be passive if it does not generate metadata and
does not have control over where and how a user or processing component
obtains the required metadata. A potentially active DD/DS provides the
capability of producing the metadata for a given p rogram or process. A
potentially active DD/DS can be extended to active through supportive
administrative procedures. Many of the currently commercially available
DD/DSs are of this type. In practice, the concept of active/passive DD/DS
refers to interface s that it provides to other software packages. A DD/DS with
active interfaces can better serve the goals of managing data as a resource.
3.4.3 HIPO Chart
Hierarchy -Input -Process -Output (HIPO)
Hierarchy -Input -Process -Output (HIPO) is a documentation techn ique
developed by IBM and used in a number of different situations. It is useful for
design documentation as well as stating requirements and specifications
before beginning design. It is based on two concepts: The input -process -
output model of informatio n processing and functional hierarchies. HIPO is
basically a graphical notation, consisting of hierarchy charts and process
charts. The hierarchy chart is similar to a structure chart. Each box in the chart
can represent a system, subsystem, program, or pr ogram module. Its purpose
is to show the overall functional components and to refer to overview and
detail HIPO diagrams. It does not show the data flow between functional
components or any control information. It does not show the arrows with open
or fill ed circles. Also, it does not give any information about the data
components of the system or program.
The second part of the HIPO notation is process charts. Process charts
have two levels: overview diagram and detail diagrams. They are used to
describe a function in terms of its inputs, the processing to be done, and the
outputs produced. Any of the information, especially the process part, may be
described in more detail by accompanying textual material. The process charts
show the flow of data through processes; however, they are more difficult to
draw than data flow diagrams. HIPO diagrams often require more verbiage
and symbols to give the same information as a comparable data flow diagram.
HIPO has been used in a number of DP (Data Processing) situat ions and some
more complex specification tasks. Its drawbacks, especially with respect to
interfaces and the description of data, were limited to its acceptance. HIPO
does not include any guidelines, strategies, or procedures to guide the analyst
in buildi ng a functional specification or the designer in building a system or
program design.
At the general level, a structure chart is usually preferred over a
hierarchy chart. At the detailed level, pseudocode is often preferred over
HIPO diagrams because it p rovides more information in a more compact
form. HIPO diagrams have no symbols for representing detailed program
structures such as conditions, case structures, and loops. HIPO diagrams
cannot represent data structures or the linkage to data models.munotes.in
Page 53
53
Figure: HIPO Chart
3.4.4 Warnier Orr Diagram
A graphical representation of a horizontal hierarchy
with brackets isolating the levels is utilized to plan or document a data
structure, a set of detailed logic, a program, or a system.
Strengths, weakness es, and limitations:
Warnier -Orr diagrams are excellent tools for describing, planning, or
documenting data structures. They can show a data structure or a logical
structure at a glance. Because only a limited number of symbols are required,
specialized so ftware is unnecessary and diagrams can be created quickly by
hand. The basic elements of the technique are easy to learn and easy to
explain. Warnier -Orr diagrams map well to structured code.
Concepts:
The Warnier -Orr design methodology, also known as the structured
requirements definition methodology was developed in the early 1970s by
Warnier and extended to system design by Orr. The first step in the
methodology is to create entity diagrams for each major user. The entity
diagrams are then merged to cre ate a system entity diagram, and the major
tasks that must be performed are derived from the system’s data requirements.
In-out diagrams:
A Warnier -Orr diagram shows a data structure or a logical structure as
a horizontal hierarchy with brackets separatin g the levels. Once the major
tasks are identified, the systems analyst or information system consultant
prepares an in -out Warnier -Orr diagram to document the application’s
primary inputs and outputs.munotes.in
Page 54
54For example, Figure shows an in -out diagram for a batch inventory
update application. Start at the left (the top of the hierarchy). The large
bracket shows that the program, Update Inventory, performs five primary
processes ranging from Get Transaction at the top to Write Reorder at the
bottom. The letter N in parentheses under Update Inventory means that the
program is repeated many (1 or more) times. The digit 1 in parentheses under
Get Transaction (and the next three processes) means the process is performed
once. The (0, 1) under Write Reorder means the pro cess is repeated 0 or 1
times, depending on a run -time condition. (Stock may or may not be reordered
as a result of any given transaction.)
Data flow into and out from every process. The process inputs and
outputs are identified to the right of the in -out diagram. For example, the Get
Transaction process reads an Invoice and passes it to a subsequent process.
The last column is a list of the program’s primary input and output data
structures. Note how the brackets indicate the hierarchical levels.
3.5 REQUIREMENT ELICITATION
The aims of the requirements elicitation process are to understand the
work that Stakeholders do and how they might use a new system to help
support that work.
During requirements elicitation, software engineers work with
stakehold ers to find out about the application domain, work activities, the
services and system features that stakeholders want, the required performancemunotes.in
Page 55
55of the system, hardware constraints, and so on. Eliciting and understanding
requirements from system stakeholde rs is a difficult process for several
reasons:
1.Stakeholders often don’t know what they want from a computer system
except in the most general terms; they may find it difficult to articulate
what they want the system to do; they may make unrealistic demand s
because they don’t know what is and isn’t feasible.
2.Stakeholders in a system naturally express requirements in their own terms
and with implicit knowledge of their own work. Requirements engineers,
without experience in the customer’s domain, may not un derstand these
requirements.
3.Different stakeholders, with diverse requirements, may express their
requirements in different ways. Requirements engineers have to discover
all potential sources of requirements and discover commonalities and
conflict.
4.Political factors may influence the requirements of a system. Managers
may demand specific system requirements because these will allow them
to increase their influence in the organization.
5.The economic and business environment in which the analysis takes plac e
is dynamic. It inevitably changes during the analysis process. The
importance of particular requirements may change. New requirements
may emerge from new stakeholders who were not originally consulted.
3.5.1 Interviewing
Formal or informal interviews w ith system stakeholders are part of
most requirements Engineering processes. In these interviews, the
requirements engineering team puts questions to stakeholders about the
system that they currently use and the system to be developed. Requirements
are der ived from the answers to these questions.
Interviews may be of two types:
1.Closed interviews, where the stakeholder answers a predefined set of
questions.
2.Open interviews, in which there is no predefined agenda. The
requirements engineering team explores a range of issues with system
stakeholders and hence develops a better understanding of their needs.
In practice, interviews with stakeholders are normally a mixture of
both of these. You may have to obtain the answer to certain questions, but
these usual ly lead to other issues that are discussed in a less structured way.
Completely open -ended discussions rarely work well. You usually have to ask
some questions to get started and to keep the interview focused on the system
to be developed.munotes.in
Page 56
56Interviews are g ood for getting an overall understanding of what
stakeholders do, how they might interact with the new system, and the
difficulties that they face with current systems. People like talking about their
work, and so they are usually happy to get involved in interviews. However,
unless you have a system prototype to demonstrate, you should not expect
stakeholders to suggest specific and detailed requirements. Everyone finds it
difficult to visualize what a system might be like. You need to analyze the
informat ion collected and to generate the requirements from this.
Eliciting domain knowledge through interviews can be difficult, for
two reasons:
1.All application specialists use jargon specific to their area of work. It is
impossible for them to discuss domain requirements without using this
terminology. They normally use words in a precise and subtle way that
requirements engineers may misunderstand.
2.Some domain knowledge is so familiar to stakeholders that they either
find it difficult to explain or they thin k it is so fundamental that it isn’t
worth mentioning. For example, for a librarian, it goes without saying that
all acquisitions are catalogued before they are added to the library.
However, this may not be obvious to the interviewer, and so it isn’t take n
into account in the requirements.
Interviews are not an effective technique for eliciting knowledge about
organizational requirements and constraints because there are subtle power
relationships between the different people in the organization. Publishe d
organizational structures rarely match the reality of decision making in an
organization, but interviewees may not wish to reveal the actual rather than
the theoretical structure to a stranger. In general, most people are generally
reluctant to discuss p olitical and organizational issues that may affect the
requirements.
To be an effective interviewer, you should bear two things in mind:
1.You should be open -minded, avoid preconceived ideas about the
requirements, and willing to listen to stakeholders. If the stakeholder
comes up with surprising requirements, then you should be willing to
change your mind about the system.
2.You should prompt the interviewee to get discussions going by using a
springboard question or a requirements proposal or by working tog ether
on a prototype system. Saying to people “tell me what you want” is
unlikely to result in useful information. They find it much easier to talk in
a defined context rather than in general terms.
Information from interviews is used along with other inf ormation
about the system from documentation describing business processes or
existing systems, user observations, and developer experience. Sometimes,
apart from the information in the system documents, the interview information
may be the only source of information about the system requirements.
However, interviewing on its own is liable to miss essential information, andmunotes.in
Page 57
57so it should be used in conjunction with other requirements elicitation
techniques.
3.5.2 Questionnaire
Interviews –Start Up Questio ns
• Context -free questions to narrow the scope a bit (Weinberg)
• Identify customers, goals, and benefits
• Who is (really) behind the request for the system?
• Who will use the system? Willingly?
• Are there several types of users?
• What is the potentia l economic benefit from a successful solution?
• Is a (pre -existing) solution available from another source?
• When do you need it by?
• Can you prioritize your needs?
• What are your constraints?
•T i m e
• Budget
• Resources (human or otherwise)
• Expected milestones (deliverables and dates)?
• Try to characterize the problem and its solution
• What would be a "good" solution to the problem?
• What problems is the system trying to address?
• In what environment will the system be used?
• Any special perform ance issues?
• Other special constraints?
• What is (un)likely to change?
• Future evolution?
• What needs to be flexible (vs. quick & dirty)?
• Questions that cannot be asked directly (ask indirectly)
• Are you opposed to the system?
• Are you trying to o bstruct/delay the system?
• Are you trying to create a more important role for yourself?
• Do you feel threatened by the proposed system?
• Are you trying to protect your job?
• Is your job threatened by the new system?
• Is anyone else's?
3.5.3 Brainsto rming
• To invent new way of doing things or when much is unknown
• When there are few or too many ideas
• Early on in a project particularly when:munotes.in
Page 58
58• Terrain is uncertain
• There is little expertise for the type of applications
• Innovation is important ( e.g., novel system)
• Two main activities:
• The Storm: Generating as many ideas as possible (quantity, not quality) –
wild is good!
• The Calm: Filtering out of ideas (combine, clarify, prioritize, improve…) to
keep the best one(s) –may require some vo ting strategy
• Roles: scribe, moderator (may also provoke), Participants
Brainstorming –Objectives
• Hear ideas from everyone, especially unconventional ideas
• Keep the tone informal and non -judgemental
• Keep the number of participants “reasonable“ –if too many, consider a
“playoff “ -type filtering and invite back the most creative to multiple sessions
• Encourage creativity
• Choose good, provocative project name.
• Choose good, provocative problem statement
• Get a room without distractions, but w ith good acoustics, whiteboards,
coloured pens, provide coffee/donuts/pizza/beer
• Provide appropriate props/mock -upsmunotes.in
Page 59
59Brainstorming –Roles
• Scribe
• Write down all ideas (may also contribute)
• May ask clarifying questions during first phase but witho ut criticizing
• Moderator/Leader
• Cannot be the scribe
• Two schools of thought: traffic cop or agent provocateur
• Traffic cop –enforces "rules of order", but does not throw his/her weight
around otherwise
• Agent provocateur –traffic cop plus more of a leadership role, comes
prepared with wild ideas and throws them out as discussion wanes
• May also explicitly look for variations and combinations of other
suggestions
Brainstorming –Participants
• Virtually any stakeholder, e.g.
• Developers
• Domai n experts
• End -users
• Clients
• ...
• “Ideas -people” –a company may have a special team of people
• Chair or participate in brainstorming sessions
• Not necessarily further involved with the project
Brainstorming –The Storm
• Goal is to generate as ma ny ideas as possible
• Quantity, not quality, is the goal at this stage
• Look to combine or vary ideas already suggested
• No criticism or debate is permitted –do not want to inhibit participants
• Participants understand nothing they say will be held ag ainst them later on
• Scribe writes down all ideas where everyone can see
• E.g., whiteboard, paper taped to wall
• Ideas do not leave the room
• Wild is good
• Feel free to be gloriously wrong
• Participants should NOT censor themselves or take too long t o consider
whether an idea is practical or not –let you go!
Brainstorming –The Calm
• Go over the list of ideas and explain them more clearly
• Categorize into "maybe" and "no" by pre -agreed consensus methodmunotes.in
Page 60
60• Informal consensus
• 50% + 1 vote vs. “clea r majority”
• Does anyone have veto power?
• Be careful about time and people
• Meetings (especially if creative or technical in nature) tend to lose focus
after 90 to 120 minutes –take breaks or reconvene later
• Be careful not to offend participants
•Review, consolidate, combine, clarify and improve.
• Rank the list by priority somehow
• Choose the winning idea(s)
Brainstorming –Tool Support
• With many good ideas, some outrageous and even farfetched, brainstorming
can be really fun!
• Creates a great environment that stimulates people and motivates them to
perform well!
• Can be done by email, but a good moderator/leader is needed to
• Prevent flamers to come into play
• Prevent race conditions due to the asynchronous communication medium
• Be careful not to go into too much detail
• Collaboration tools are also possible
• TWiki and many other more appropriate tools such as BrainStorm and
IdeaFisher
3.5.4 Facilitated Application Specification Technique
Its objective is to bridge the expectation gap –difference between
what the developers think they are supposed to build and what customers
think they are going to get.
A team oriented approach is developed for requirements gathering.
Each attendee is asked to make a list of objects that are -
1. Part of t he environment that surrounds the system
2. Produced by the system
3. Used by the system
Each participant prepares his/her list, different lists are then combined,
redundant entries are eliminated, team is divided into smaller sub -teams to
develop mini -specific ations and finally a draft of specifications is written
down using all the inputs from the meeting.
3.5.5 Use Case Approach
Use cases are a way of describing interactions between users and a
system using a graphical model and structured text. They were f irst introduced
in the Objectory method (Jacobsen et al. 1993) and have now become amunotes.in
Page 61
61fundamental feature of the Unified Modelling Language (UML). In their
simplest form, a use case identifies the actors involved in an interaction and
names the type of inte raction. You then add additional information describing
the interaction with the system. The additional information may be a textual
description or one or more graphical models such as the UML sequence or
state charts (see Chapter 5). Use cases are documen ted using a high -level use
case diagram. The set of use cases represents all of the possible interactions
that will be described in the system requirements. Actors in the process, who
may be human or other systems, are represented as stick figures. Each cl ass of
interaction is represented as a named ellipse. Lines link the actors with the
interaction. Optionally, arrowheads may be added to lines to show how the
interaction is initiated. This is illustrated in Figure 4.15, which shows some of
the use cases f or the Mentcare system. Use cases identify the individual
interactions between the system and its users or other systems. Each use case
should be documented with a textual description. These can then be linked to
other models in the UML that will develop t he scenario in more detail. For
example, a brief description of the Setup Consultation use case from Figure.
Setup consultation allows two or more doctors, working in different
offices, to view the same patient record at the same time. One doctor initiate s
the consultation by choosing the people involved from a dropdown menu of
doctors who are online. The patient record is then displayed on their screens,
but only the initiating doctor can edit the record. In addition, a text chat
window is created to help coordinate actions. It is assumed that a phone call
for voice communication can be separately arranged.
Figure: Use Case Diagram
The UML is a standard for object -oriented modeling, so use cases and
use case based elicitation are used in the requiremen ts engineering process.
However, my experience with use cases is that they are too fine -grained to be
useful in discussing requirements. Stakeholders don’t understand the term use
case; they don’t find the graphical model to be useful, and they are often n ot
interested in a detailed description of each and every system interaction.
Consequently, I find use cases to be more helpful in systems design than inmunotes.in
Page 62
62requirements engineering. I discuss use cases further in Chapter 5, which
shows how they are used alon gside other system models to document a system
design.
Some people think that each use case is a single, low -level interaction
scenario. Others, such as Stevens and Pooley (Stevens and Pooley 2006),
suggest that each use case includes a set of related, lo w-level scenarios. Each
of these scenarios is a single thread through the use case. Therefore, there
would be a scenario for the normal interaction plus scenarios for each possible
exception. In practice, you can use them in either way.
3.6 SUMMARY
Requi rements for a software system set out what the system should do and
define constraints on its operation and implementation
Functional requirements are statements of the services that the system
must provide or are descriptions of how some computations mus tb e
carried out.
Non-functional requirements often constrain the system being developed
and the development process being used. These might be product
requirements, organizational requirements, or external requirements. They
often relate to the emergent properties of the system and therefore apply to
the system as a whole.
The requirements engineering process includes requirements elicitation,
requirements specification, requirements validation, and requirements
management
Requirements elicitation is an iterative process that can be represented as a
spiral of activities requirements discovery, requirements classification and
organization, requirements negotiation, and requirements documentation.
Reference Books:
1.Software Engineering 6th edition Roger S. Pressman
2.Software Engineering Tenth Edition Ian Sommerville, Pearson.
munotes.in
Page 63
634
OBJECT ORIENTED ANALYSIS AND
DESIGN
Unit Structure
4.0 Objective
4.1 Introduction
4.1.1 Review of Object Orientation
4.2 UML Overview
4.2.1 Building block of UML
4.2.1.1 Things
4.2.1.1.1 Structural Things
4.2.1.1.2 Behavioral Things
4.2.1.1.3 Grouping Things
4.2.1.1.4 Annotation Things
4.2.1.2 Relationship
4.2.1.2.1 Dependency
4.2.1.2.2 Association
4.2.1.2.3 Generalization
4.2.1.2.4 Realization
4.2.1.3 Diagrams
4.2.1.3.1 Structure Diagram
4.2.1.3.2 Behavior diagram
4.2.1.3.3 Interaction diagram
4.3 Nature and Purpose of UML Model
4.4 Features of UML
4.5 UML Diagrams
4.5.1 Class Diagram
4.5.2 Object Diagram
4.5.3 Use Case Diagram
4.5.4 Activi ty Diagram
4.5.5 Sequence Diagram
4.5.6 State Transition Diagram
4.5.7 Deployment Diagram
4.0 OBJECTIVE
After studying this particular chapter, you will be able to understand
To know what is UML
To know the features of UML
To know what is UML not
To kn ow the Object Oriented Concepts
To understand need of diagrams and different model element used in it.munotes.in
Page 64
644.1 INTRODUCTION
UML stands for Unified Modeling Language. It is basically visual
modeling language that helps to create blueprints that capt ure vision in
standard, understandable form.
The UML is nothing but the graphical language which explains the
following artifacts of software system.
1.Specifying -Define model precisely, unambiguously and completely
2.Visualizing -Define Graphi cal Notations to communicate with system
ambiguously.
3.Constructing –Define design dimensions for building models.
4.Documenting –Define documentation for inception.
Models are representation of reality. Software under development can
be complex so models of software can be used. One such modeling technique
isUnified Modeling Language.
Models are created before actual development of the systems so that
we can understand possibility, problems, options etc. The different views give
different perspective of the system when models are created.
Example -car driver is interested in dashboard and its functions, but if we
consider electronics person he shows his interest in circuit connections.
4.1.1 Review of object orientation
The UML can be used in better way with the Object Oriented
Technology. So now we will see these concepts
1. Object The things that can be tangible.
Instance of a class
Things has some kind of identity, state, behavior
Example -A car(brand name ,color ,type etc.)
2. Class Group of structurally identical items
Encapsulation of data and operations.
Example -AC a r
Attribute -color, brand name etc
Operations –start(), stop(),accelerate() etc.
3. Encapsulation Wrapping of data and function in single unit.
The data is not directly accessible to outside
world
Example -for car class operations are around the
attributes.
4. Abstraction Representing essential features without
including background explanation.
Example -A car gives information about attributes
andoperations not its process.munotes.in
Page 65
655. Inheritance A process by which object of one class acquire
the properties of other class.
It is known as super class and sub class or
parent class and child class.
Example -vehicle is super class and car, auto, truck
are sub class
6 Polymorphism Ability to take more than one form
Example –All polygon occupies area. Triangle
,rectangle are polygon.
7.Message
PassingCommunication between set of objects
Example -AC operated by remote (on, off, tempincreased or decrease).
Here object remote invoke the function of object
AC.
4.2 UML OVERVIEW
UML is constructed from three building blocks: -Things, relationship,
diagram.
To use UML, it is necessary to understand these building block clearly.
4.2.1.1 Things
4.2.1.1.1 Str uctural Things –
It is also called as nouns of the UML model.
It is mostly representing the static part of the system.
The conceptual or physical elements are represented by structural things.
Some structural things which are available with UML -
Sr no Structural Things Symbols
1 Class -Abstact set of things contain
similar properties and functions
Example -Car class
2 Interface –Set of operation which
tells clearly what a class can do.
Example -car class, bus class
contain common action start
engin e()
3 Collab oration - Provide an
interaction between things
so that goal have achieved.
Example -Reservation System
4 Use case -Set of action that system
performed to achieve specific goal.
Example -Admission System
munotes.in
Page 66
665 Component –Describe physical
part of system.
Example -Set of classes.
6 Node –Run time physical element.
Example -
7 Active classe s–It is a class whose
objects having one or more
processes
4.2.1.1.2 Behavioral Things -
It is basically depending upon behavior (called dynamic also).
It is also called verbs of UML.
In behavioral things behaviors are represented based on time and space.
Sr
noBehavioral Things Symbols
1. Interaction –Exchange of message
between objects.
2. State Machine -Sequences of stat e
of objects used in its lifetime to
give response to event.
Example -ATM System
4.2.1.1.3 Grouping things
Grouping refers to organizational part of UML model.
Higher level abstraction is provided by grouping things.
In grouping model can be decomposed.
Sr
noGrouping Things Symbols
1. Package –It exist only during
development time.
It includes structural,
behavioral and other grouping things
4.2.1.1.4 Annotation things
If we wish to add comments to UML diagrams for more explanation
purpose, then annotation things are used.
Sr.no Annotation Things Symbols
1. Note-Graphical notation for attaching
comments, rules etc.
munotes.in
Page 67
67Relationship
Relationship is nothing but the links between the things which shows how
system is implemented.
There are four types of relationships
1.Dependency -
In this relationship change in one affects the other.
The notation used for this is
Example -If date of birth of a person changed then age will automatically
Change.
2.Association -
It is structural relationship.
It shows how objects are taking part in relationship.
The notation used for this
Example -Relationship between doctor and patient.
3.Generalization -
It is a relationship between Parent class and child class.
The notation used for this
Example -Account class contain two sub c lass Saving account and current
Account
4.Realization -
It is semantic relationship.
In this on specifies behavior to be carried and othe carries out behavior.
The notation used for this
Example -AC carries out the beh avior specified by remote.
4.2.1.2Diagrams
The diagrams are graphical representation of models which uses various
symbols and text.
There are Following types of UML Diagrams -
1.Structure diagrams -
Set of diagrams that mention the elements of specification.
It repr esents framework for system.
It includes class, structure, component, deployment diagrams.
2.Behavior diagram -
It represents features of system.
It describes the interaction in the system.
It includes activity, use -case, state machine and interaction diagr am.
3.Interaction Diagram -
This type comes under behavior diagram.
It emphasizes object interaction.
It includes communication, interaction and sequence diagram.munotes.in
Page 68
684.3NATURE AND PURPOSE OF UML MODEL
Nature of UML Model -
It is a representation in a certain med ium of something in the same or
another medium
It captures the important aspects of the thing being.
Model of a software system is made in a modelling language, such as
UML.
It generator of potential configurations of systems; the possible systems
are its extent, or values.
Model has both semantics and notation and can take various forms that
include both pictures and text.
The levels of models give guidance to thought process and also gives
abstract specification of the system.
The models can be
1.Conce ptual models
describe a situation of interest in the world, such as a business operation or
factory process.
Nothing about how much of the model is implemented or supported by
software.
2.Specification models
define what a software system must do, the in formation it must hold, and
the behaviour it must exhibit.
They assume an ideal computing platform.
3.Implementation models
describe how the software is implemented, considering all the computing
environment’s constraints and limitations.
Purpose of UML Model -
To capture and precisely state requirements and domain knowledge so that
all capture requirements about the appearance, traffic patterns, various
kinds of utility services, strength against wind and earthquakes, cost, and
many other things.
Different models of a software system may capture requirements about its
application domain, the ways users will use it, its breakdown into
modules, common patterns used in its construction, and other things.
To think about the design of a system.
softw are model system helps developers explore several architectures and
design solutions easily before writing code.
good modelling language allows the designer to get the overall
architecture right before detailed design begins.munotes.in
Page 69
69To capture design decisio ns in a mutable form separate from the
requirements.
One model of a software system can capture the external behaviour of a
system and the real -world domain information represented by the system.
Another model shows the internal classes and operations t hat implement
the external behaviour.
To generate usable work products.
model of a software system can be used to generate class declarations,
procedure bodies, user interfaces, databases, scenarios of legal use,
configuration scripts, and lists of race conditions.
To organize, find, filter, retrieve, examine, and edit information about
large systems.
model of a software system organizes information into several views:
static structure, state machines, interactions, requirements, and so on.
To explor e multiple solutions economically.
Models of a large software system permit several designs to be proposed
and compared.
The models are not constructed in full detail, of course, but even a rough
model can expose many issues the final design must deal with.
To master complex systems.
A model of a large software system permits dealing with complexity that
is too difficult to deal with directly.
A model can determine the potential impact of a change before it is made,
by exploring dependencies in t he system.
4.4FEATURES OF UML
UML provides following features -
1. Syntax only -
UML is a language not a notation so it used to describe that which
model elements are used with diagrams and how to used it.
2. Comprehensive -
It can be used to model anything even though the modeling syntax
aimed primarily at creating models of software based system.munotes.in
Page 70
703. 13 diagrams -
UML includes total 13 diagrams which helps in different perspectives
of the system. In practice we are not using all of them, we used them as per
requirements.
4. Language -independent -
It has no binding to any type of language. The binding can be decided
based on which tool we select for representation.
5. Process independent -
Any process can be used for creating models. It has no binding with
the process for creating models.
6. Tool-independent -
There are restrictions on the vendors who provide the tools for
drawing diagrams .Each vendor can do value addition to the visual modelling
of diagrams.
7. Well documented -
The UML diagrams having well documentation w hich describe the
notations and its examples.
4.5UML DIAGRAMS
2.5.1 Class Diagram
It depicts static view of the system.UML Diagram
Structure
DiagramsBehavior
Diagram
Class
DiagramCompone
nt
DiagramObject
Diagram
Composit
e
StructureDiagramDeploym
ent
DiagramPackage
DiagramActivity
Diagra
mUse
caseDiagraState
machineDiagramInteraction
Diagram
Sequence
DiagramCommunicati
on DiagramTiming
Diagrammunotes.in
Page 71
71It is also known as structural diagram as it shows the collection of classes,
interfac es, association, collaboration.
Class diagram shows the different classes involved and the relationship
between classes.
It describes the functionality shown by the system.
Purpose of class Diagram -
Analysis and designing of static view of application
Todescribe responsibility of system
Base for drawing component and deployment diagrams.
Creating an application with the help of given requirements.
How to draw class diagram?
The following points should be remembered while drawing a class
diagram –
1.Class name should be meaningful.
2.Each element of the class with its relationship should be identified earlier
3.Attributes and methods of a class should be clearly mentioned
4.For each class minimum number of properties should be mentioned
clearly.
5.To unders tand the diagram properly add notes in it.
6.Last but not the least prepare the diagram on paper to make it final.
Basic Class Diagram Symbols and Notations
1.Class –
It represents abstraction of entity having common characteristics
Class denote with rectang le symbol divided into compartments.
Name of the class in first compartment ( centred, bolded, and capitalized),
list of attributes in second compartment (left -aligned, not bolded, and
lowercase), write operations into the third compartment.
Symbol
Example
2.Active classes -
Active classes initiate and control the flow of activity
Active classes shown with a thicker border.munotes.in
Page 72
72Symbol
Example
3.Visibility
It is used to describe that who can access the information which is present
in class.
Symbols fo r the visibility are as follows -
Public -Allow all other classes to view information
Private -Hide information from anything outside the class.
Protected -Allows child class to access information from parent class.
4.Association
It is used to represent sta tic relationship between classes.
It is going to be shown by solid line
5.Multiplicity
This is used to show the relationship between two classes.
This notation is place d near the end of association line.
The symbols are shown belowmunotes.in
Page 73
73
6.Composition
Composition is special type of aggregation.
It shows strong relationship between classes.
In this one class is whole and other is part.
Composition shown by line with fille d diamond at the end.
Symbol
Example -ROOM class does not exist separate to HOUSE class.
7.Aggregation -
In this whole class plays more important role than part class.
Classes are not depending upon each other.
Aggregation shown by hollow diamond.
Symbol
Example -Class DEPARTMENT having association between class
COMPANY. Department is part of company.
8.Generalization -
It is nothing but an inheritance.
It is showing relationship between parent and child class.
It indicates “ is a” relationship
Symbolmunotes.in
Page 74
74
Example –MANGO class, ORANGE class are part of FRUIT Class.
9.Dependence -
It is special type of association.
If any changes happen in one class, it affects the changes in other class.
It is shown by dashed line with normal arrow head.
Symbol shown as
10.Realization -
It shows the realization between two objects.
It is shown between interfaces and the class or component.
It is represented by a dashed line with a hollow arrowhead.
Symbol shown as
munotes.in
Page 75
75Class diagram E xample –ATM system
4.5.2 Object Diagram
It is an instance of a class diagram.
It shows the snapshot of detailed state of the system.
It is used to depict the set of object and their relationship as an instance.
Purpose of Object Diagram -
It is used to r epresent the data structure examples.
Object diagram treated as test cases that will used to check accuracy and
completeness of class diagram.
It is used to identify fact about particular element and link.
How to draw Object Diagram -?
The followin g points should be remembered while drawing a class
diagram –
1.Diagram should have meaningful name
2.Elements along with data are to be identified.
3.Association should be clearly mentioned.
4.Different element values need to be captured.
5.For more clarity add not es.
Basic Object Diagram Symbols and Notations
1.Object Names -
Object shown by rectangle.
Object name and class name are underline and separated by colon.munotes.in
Page 76
76Symbol -
Object name: Class name
2.Object attributes -
Here similar to class objects are having attr ibutes.
Object attributes should have values assign to them.
Symbol
Object: class name
Attribute: value
3.Links -
Links tend to be instances associated with associations.
Symbols
Example of class to object diagram -
Class diagr am
Object Diagram for given class
diagram
4.5.3 Use Case Diagram
It is primary form for new software program which is under developed.
It specifies exact behavior of system.
It gives the representation in both ways textual and visual
Helps to design the system from user’s perspective.munotes.in
Page 77
77Purpose of Use -Case Diagram
To capture dynamic aspect of the system.
T0 capture, describe and document the requirements.
To get outside view of system.
Finds internal and external factors affecting system
Specify the co ntext of a system
Drive implementation and generate test cases
How to draw Use Case Diagram?
The following points should be remembered while drawing a Use Case
diagram –
1.Use case name should be simple and clearly define functionality.
2.Actor name must be s imple and clear.
3.Show relationship and dependency clearly.
4.Use notes to add more clarification.
Basic Use Case Diagram Symbols and Notations
1.An Actor
Represents a role that interact with system
An Actor can be device, person or other system
To find an act or we have to ask some questions like
Who uses main functionality of system?
Which hardware device system needs to handle?
With which the other system needs to interact?
What nouns are used to describe system.
The notation used for use case is a stick pers on or node or device symbol.
2. Use Case -
This is an abstraction of the set of sequences. Example -login
Name is given by verb and noun.
Each Actor must be linked to a use case, while some use cases may not
be linked to actors.
To find Us e Case We have to consider some questions like
What function system is expected to perform?
What do actor expect system to perform?
What are the input and output expected by system?
What are the verbs which used to describe the system?
The notation used for use case is an oval with use case name written
inside.
munotes.in
Page 78
783.Relationships -
It indicates which actor initiate which use case.
This link indicate interaction between a specific actor and specific use
case.
The pa rticipation of an actor in a use case is shown by connecting an
actor to a use case by a solid link.
The notation used for it is
The notation used for relationship fall in to three categories
1. Actor to Use Cas e
2. Between Use Case -
There are two types of relationships exist between Use Cases
a.Include -
When a use case is depicted as using the functionality of another use
case, the relationship between the use cases is named as i nclude or uses
relationship.
Au s ec a s ei n c l u d e st h ef u n c t i o n a l i t yd e s c r i b e di na n o t h e ru s ec a s ea sa
part of its business process flow.
A uses relationship from base use case to child use case indicates that an
instance of the base use case will include t he behaviour as specified in
the child use case.
An include relationship is depicted with a directed arrow having a dotted
line. The tip of arrowhead points to the child use case and the parent use
case connected at the base of the arrow.
The stereotype "< >" identifies the relationship as an include
relationship.
b.Extends -
It is used to relate the use cases which describe variations in the normal
flow of events for the particular function to the basic use case which
describe normal flow of even ts for the function.munotes.in
Page 79
79The stereotype "<>" identifies as an extend relationship
3.Between actors -
Two actors can be related only through the generalization -specialization
relationship.
This is used if specialised actor doing some kind of interacti on which is
not done by rest of the actors.
The notation used a line with arrow where the arrow head is empty
triangular head.
4.Boundry of System -
The system boundary is potentially the entire system as defined in the
requirements document.
For large and complex systems, each module may be the system
boundary.
For example, for an ERP system for an organization, each of the modules
such as personnel, payroll, accounting, etc.
Example -Use Case Diagram for ATM System
??
??munotes.in
Page 80
80??????
4.5.4 Activity Diagram
It describes the flow of activity
It describes dynamic aspect of the system.
It is used to describe complex activities in high level activities.
Purpose of Activity Diagram -
Examine business workflow and identify ca ndidate use case
Identify pre and post conditions
Describe various flow of system like parallel, branched, concurrent etc.
Modelling business requirements.
How to draw Activity Diagram?
The following points should be remembered while drawing a Activity
diagram
1.Set the scope of activity that is being describe.
2.Provide proper title to diagram.
3.Identify the activities, control flow between activities
4.Identify the decision which is present in model.
5.Identify any prospect for parallelism in the process.
6.If req uired then add swim lanes in a diagram.
Basic Activity Diagram Symbols and Notations -
1.Initial state or start point -
It represents start point for any activity diagram.
In case of swim lane the start point is place in the top left corner of first
column.
This notation is small filled circle followed by an arrow.
??
2.Activity / Action state -
Used to represent the activities of the process.
The notation is rectangle with rounded corners.
??
3.Action Flow -
It represents transition between activities.
The notation i s an arrowed line.
??
4.Object flow -
It represents creation and modification of objects by activity.
??
5.Decision and branching -
When activity requires to take a decision for moving into next activity
then decision and branching is used.
It divides the activity in true and false part.
The notation is diamond shape.
??munotes.in
Page 81
816.Guards -
These are the statements written next to decision diamond.
These are not essentials but useful.
??
7.Synchronisation -
In this fork and join nodes are used.
Join node joins multiple flows in si ngle flow.
Fork node splits single flow in multiple flow.
It represents by straight thicker line.
??
8.Time event -
It stops the flows of activity for a time.
??
9.Merge Event -
It brings multiple flows in single.
??
10.Sent and received signal
It shows how the activi ty is modified from outside the system.
It always comes in pair.
??
11.Swim lane –
It group the activity in to columns for clear presentation.
12.Final state -
It represents final action state.
The notation is an arrow pointing to filled circle.
??
Example of Acti vity Diagram -
1.Activity Diagram for overall ATM Machine.
??
2.Activity Diagram for ATM Machine using Swim lane
??
4.5.5 Sequence Diagram
This diagram shows interaction based on time ordering.
It helps to understand how the different objects interact with ea ch other.
It represents the life line of participants while exchanging message.
It helps to understands which classes are required for interaction.
Purpose of Sequence Diagram -
Represents use cases in visual format.
Used as requirement document to represe nts pre requisites for future
implementation.
Represents the working of object in current system.
How to draw Sequence Diagram?
1.Select only those use cases which contains complex interaction.
2.The actor should be same as use case diagram.
3.Find out the obje cts required for interaction.munotes.in
Page 82
824.Decide the flow of messages for exchanging data.
5.Write text along with message arrow.
6.Show the interaction between the objects by drawing lifelines.
7.Determine the type of interaction i.e. synchronous, asynchronous, return,
creation and destruction of objects.
Basic Sequence Diagram Symbols and Notations -
1.Object -
It represents the name of class.
??
2.Lifeline notation -
It shows interaction of objects with each other.
No two life line notations overlapped with each other.
The life line Shown by vertical dashed line starting from particular actor.
??
3.Actors -
It represents type of role where it interacts with system and objects.
??
4.Messages -
Shows communication between objects.
It represents using an arrow.
Following are the categories of messages -
i.Synchronous Message -
This message waits for reply before moving to next interaction i.e
acknowledgment from receiver.
It is represented by solid arrow head.
??
ii.Asynchronous Message -
It does not wait for reply from receiver.
It is showed by lin ed arrow head.
??
iii.Create Message -
Used to instantiate a new object.
It is represented with a dotted arrow and create word labelled on it
<>
??
iv.Delete Message -
Used to delete an object.
It is represented by an ar row terminating with a x.
??
v.Self Message -
Used to send message to itself.
represented with a U shaped arrow .
??
vi.Replay Message -
Messages are sent from sender to receiver.
Represented an open arrowhead with a dotted line.
??
vii.Found Message -
It is used when unk nown source send message.munotes.in
Page 83
83Represented using an arrow directed towards a lifeline from an end
point.
??
viii.Lost Message -
Used to represent when recipient not known.
It is represented using an arrow directed towards an end point from a
lifeline
??
5.Looping -
Some set of interaction required to perform again & again at that time
looping is used.
A box put around these steps to show looping.
6.Boundary -
It encloses set of objects, lifelines, interactions involved in diagram
It is represented by simple rectangle.
Example -Sequence Diagram of ATM System
??
4.5.6 State Transition Diagram
It shows behavior of class to external environment.
It shows dynamic behavior in between states.
It is also called as State Diagram or State Chart Diagram.
Purpose of State Transition Diagram -
Used to represent finite state machine.
Used to model the objects which contain finite states and interaction with
outside world.
Describe the behavior of single object in different event.
How to draw State Transition Diagram?
1.Identify initial a nd final state.
2.Identify actions/events to be carried out.
3.Show the transition of object from one state to another.
Basic State Transition Diagram Symbols and Notations
1.States -
It represents states of object during its lifetime.
It is shown by rectangle w ith rounded corners .
??
2.Transition -
It is a path between various object states.
Transition is labeled with event that will carried out.
Transition can come back to itself.
??
3.Initial State -
Represents starting point of an object.munotes.in
Page 84
84It represents by filled ci rcle followed by an arrow.
??
4.Final State -
Represents final state of an object.
It represents by an arrow pointing to a filled circle nested inside another
circle .
??
5.Synchronization and splitting of control -
It represents with small bar with two transition s.
One is fork in single transition splits into multiple transitions.
Second join in multiple transition combine in to single transition.
?? ??
Example -State Transition Diagram of ATM machine
1.State Transition Diagram for one Transaction ATM Machine
??
2.State Transition Diagram for one Session of ATM machine
??
4.5.7 Deployment Diagram
It describes static view of system.
It shows visualization of physical component of system.
Purpose of Deployment Diagram -
They show the structure of the run -time system
They capture the hardware that will be used to implement the system and
the links between different items of hardware.
They model physical hardware elements and the communication paths
between them
They can be used to plan the architecture of a system.
They are also useful for Document the deployment of software
components or nodes
How to draw Deployment Diagram?
1.First identify the artifact like nodes and relationship among nodes.
2.Add other elements to the diagram i.e. component, active object.
3.Add depend ency between components and object when required.
Basic Deployment Diagram Symbols and Notations
1.Artifact -
Represents specification of real world entity.
Describe the framework during software development process.
??
2.Node -
It is computational resource upo n which artifacts are deployed for
execution.
It is represented using a node with stereotype <>.munotes.in
Page 85
85??
<< execution environment >>
It is a node that represents an environment in which software is going
toexecute.
For example, Java applications are executed in java virtual machine
(JVM)).
??
Example -Deployment Diagram for ATM Machine
??
Summary
There are variety of modeling techniques available
The UML is one such technique which plays an important role in the
object oriented software developmen t.
The most important elements of the object oriented method are class,
object, encapsulation, polymorphism, inheritance etc.
There are three main building blocks viz. things, relationship, diagrams.
There are thirteen different diagram available with the UML.
The class diagram gives static view of system.
The main element of the class are classes and its relationships.
The set of object and its relationship shown by Object Diagram.
The complexity in the execution of interaction shown by Sequence
Diagram.
The flow of business functions is shown by Activity Diagram.
For gathering requirement of the system Use Case Diagram is used.
The transition from one state to another by triggering event shown by
State Transition diagram.
The visualization of physical com ponents shown by Deployment Diagram.
Self-Learning Topics : Comparison of Requirements Elicitation Techniques
References -
Unified Modeling Language User Guide by Ivar Jacobson
UML 2 Bible by Tom Pender
Object Oriented Modelling and Design with UML 2
Case study for Practice -
1. Draw a class diagram for the scenario given below. This scenario
shows an inheritance hierarchy of a series of classes and their subclasses. It’s
for an imaginary application that must model different kinds of vehicles such
as bicycles , motor bike and cars. All Vehicles have some common attributes
(speed and colour) and common behaviour (turn Left, turn Right). Bicycle and
Motor Vehicle are both kinds of Vehicle and are therefore shown to inherit
from Vehicle. To put another way, Vehicl e is the superclass of both Bicycle
and Motor Vehicle. In our model Motor Vehicle shave engines and license
plates. Attributes have been added accordingly, along with some behaviour
that allows us to examine those attributes. Motor Vehicles is the base cla ss of
both Motor Bike and Car; therefore, these classes not only inherit the speed
and colour properties from Vehicle, but also the additional attributes andmunotes.in
Page 86
86behaviour from Motor Vehicle. Both Motor Bike and Car have additional
attributes and behaviour whi ch are specific to those kinds of object.
2. Draw a class diagram for the scenario given below. This scenario is
from system that models companies for a payroll or reporting system.
Company object has properties such as name and employees list and get Name
and get Employees as its behaviour. Employee object includes employee no,
name, salary and manager as its properties getName (), get Emplyoee No ()
,getSalary() get Manager() as its methods. get Manager() accepts object of
manager. Company may have one or more employees. A manager object
keeps manages as list property and add Team Member (employee_list) and get
Team Member() as its behaviours. One or more employee can be managed by
manager objects. Some employees are contractual employees who are within a
lieu of a contractor object. A contractor object may have length_of _contract
as its property and get Length() as its behaviour
3. Construct a high level sequence diagram for online bookshop. Online
customer can search book catalogue, view description of a se lected book, add
book to shopping cart, do checkout.
4. Draw a Sequence diagram for the following scenario which shows
interactions involved in using LIBSYS for downloading and printing an
article. There are four objects of classes -Article, Form, Workspace and
Printer --involved in this interaction. Essentially, a user request for an article
triggers a request for a copyright form. Once the user has completed the form,
the article is downloaded and sent to the printer. Once printing is complete,
the article i s deleted from the LIBSYS workspace.
5. You need to develop a web -based application in such a way that user
can search other users and after getting search complete, the user can send the
friend request to other users. If the request is accepted, then both u sers are
added to friend list of each other. If one user does not accept the friend. The
second user can send friend request. The user can also block each other Draw
a state transition diagram for the above application
6. Draw an activity diagram from the na rrative text on “ONLINE PAPER
SUBMISSION SYSTEM”. The author completes an online form that requests
the user to input author name, Correspondence address, email and, title of
paper. The system validates this data and, if correct, asks the author to submit
the paper. The author then browses to find the correct paper on their system
and submits it. Once received and stored, the system returns to the author a
reference number for the paper. Authors may submit as many papers as they
like to be considered for ac ceptance to the conference up until the deadline
date for submissions. Papers are allocated to referees for assessment. They
review each paper and submit to the system their decision. Once the program
organizer has agreed the decisions authors are informed by email. Accepted
papers are then schedule to be delivered at a conference. This involves
allocating a date, time and place for the presentation of the paper.
munotes.in
Page 87
87Module -IV
5
SOFTWARE PROJECT PLANNING
Unit Structure
5.0 Objective
5.1 Introduction
5.2The Business Case
5.2.1 What Is A Business Case?
5.2.2 Developing The Business Case
5.2.3 Process For Developing A Business Case
5.3 Project Selection And Approval
5.3.1 The IT Project Selection Process
5.3.3 Balanced Scorecard Approach
5.3.2The Project Selection Decision
5.4 The Project Charter
5.4.1 What Should Be In A Project Charter
5.5Project Scope Definition
5.5.1 Project -Oriented Scope
5.5.2 Product –Oriented Scope
5.6 Project Scope Verification
5.7 Scope Change Control
5.8 Work Breakdown Structure
5.9 Software Estimation
5.10 COCOMO Model
5.11 Earned Value Management
5.12 Summary
5.0 OBJECTIVE
Describe and be able to prepare a business case.
Describe the project selection process as well as the Balanced Scored
approach.
Develop a project charter and describe its relationship to the project
plan.
Describe how project planning framework links the project’s measurable
organizational value (MOV) to the project’s scope, schedule and budget.munotes.in
Page 88
88Describe the difference between product sco pe and project scope.
Apply several tools and techniques for defining and managing the
project’s scope.
Develop a work breakdown structure.
5.1 INTRODUCTION
A business case is a deliverable that documents the project’s goal, as
well as several alternativ e or options. The feasibility, costs, benefits, and risks
for each alternative are analyzed and compared, and a recommendation to
approve and fund one of the alternatives is made to senior management. The
first phase of the IT project methodology, as in al l of phases, ends with a
review of the project by the client or sponsor.
The project charter and detailed project plan make up the project’s
tactical plan. The project charter defines the project infrastructure and
identifies the project manager, the proj ect team, the stakeholders, and the roles
each will play within the project. In addition, the project charter formalizes the
project’s MOV, scope, supporting processes and controls, required resources,
risks, and assumptions. This project infrastructure pr ovides the foundation for
developing a detailed project plan that answers four major questions. How
much will the project cost? When will the project be finished? Who will be
responsible for doing the work? And, what will we ultimately achieve at the
end o f the project?
The term scope is used to define the work boundaries and deliverables
of the project so what needs to get done, gets done -and only what needs to get
done, gets done. Therefore, it is important to define not only what is part of
the project is considered to be outside of the project’s scope.
A work breakdown structure (WBS) is discussed first. It provides a
hierarchical structure that outlines the activities or work that needs to be done
in order to complete the project scope. The WBS also p rovides a bridge or
link between the project’s scope and the detailed project plan that will be
entered into a project management software package.
Today, most project management software packages are relatively
inexpensive and rich in features. It is alm ost unthinkable that anyone would
plan and manage a project without such a tool. Project success, however, will
not be determined by one’s familiarity with a project management software
package or the ability to produce nice looking reports and graphs. It is the
thought process that must be followed before using the tool that counts.
Thinking carefully through the activities and their estimated durations first
will make the use of a project management software package much more
effective. You can still crea te nice looking reports and graphs, but you’ll have
more confidence in what those reports and graphs say.munotes.in
Page 89
895.2 THE BUSINESS CASE
5.2.1 What is a Business Case?
A business case provides the first deliverable in the IT project life
cycle. It provides an a nalysis of the organizational value, feasibility, costs,
benefits, and risks of several proposed alternatives or options. However, a
business case is not a budget or the project plan. The purpose of a business
case is to provide senior management with all the information needed to make
an informed decision as to whether a specific project should be funded.
For large projects, a business case may be a large, formal document.
Even for smaller projects, however, the process of thinking through why a
particula r project is being taken on and how it might bring value to an
organization is still useful.
Because assumptions and new information are sometimes used to
make subjective judgments, a business case must also document the methods
and rationale used for qua ntifying the costs and benefits. Different people who
work independently to develop a business case can use the information, tools,
and methods, but still come up with different recommendations.
One can also think of a business case as an investment propo sal or a
legal case. The business case developer has a large degree of latitude to
structure arguments, select or ignore evidence, and deliver the final
presentations. The outcome depends largely on the ability to use compelling
facts and logic in order to influence an individual or group with decision -
making authority .
A good IT business case should be
(1)Through in detailing all possible impacts, costs, and benefits;
(2)Clear and logical in comparing the costs/ benefits impact of each
alternative;
(3)Objective though including all pertinent information; and
(4)Systematic in terms of summarizing the findings.
5.2.2 Developing the Business Case
The purpose of a business case is to show how an IT solution can
create business value. For example, an I T project may be undertaken to:
Reduce costs
Create a new product or service
Improve customer service
Improve communication
Improve decision making
Create or strengthen relationships with suppliers, customers, or partners
Improve processes
Improve reportin g capabilities
Support new legal requirementsmunotes.in
Page 90
905.2.3 Process For Developing A Business Case
Step 1: Select the Core Team
The core team should include managers, business specialists, and users
who understand the requirements to be met, as well as IT special ists who
understand the opportunities, limitations, and risks associated with IT. There
are several advantages for having a core team develop the business case
Credibility -A team made up of individuals from various organizational areas
or departments can provide access to critical expertise and information that
may not be readily accessible to others outside that particular area.
Alignment with organizational goals –Higher level managers can help
connect the business case with organization’s long ter m strategic plan and
mission. This alignment may be beneficial in understanding and presenting
how the expected business value of the IT project will support the overall
goals and mission of the organization.
Access to the real costs –Core members with c ertain expertise or
access to important information can help build more realistic estimates in
areas such as salaries, overhead, accounting and reporting practices, training
requirements, union rules and regulations, and hiring practices.
Step 2: Define M easurable Organizational Value (MOV)
The core team’s objective should be to define the problem or
opportunity and then identify several alternatives that will provide direct and
measurable value to the organization. To provide real value to an
organizatio n, however, IT projects must align with and support the
organization‘s goals, mission, and objectives.
Be measurable –Measurement provides focus for the project team in
terms of its actions. Instead of implementing an information system, the
project team attempts to achieve a specific performance target.
Provide value to organization –Resources and time should not be devoted
to a project unless they provide some kind of value to the organization.
Be agreed on –A clear and agreed on MOV sets expectations for the
project stakeholders. It is important that all project stakeholders
understand and agree to the project’s MOV.
Be verifiable –At the end of project , the MOV must be verified to
determine if the project was a success.
The MOV guides all the decis ions and processes for managing the IT
project and serves as a basis for evaluating the project’s achievements. In
other words, a project cannot be properly planned or evaluated unless the goal
of the project is clearly defined and understood.
Step 3: Ide ntify Alternatives -Since no single solution generally exists for
most organizational problems, it is imperative to identify several alternativesmunotes.in
Page 91
91before dealing directly with a given business opportunity. The alternatives, or
options, identified in the business case should be strategies for achieving the
MOV.
The other options may provide the best solution. Consider a spectrum of
choices that include:
Changing the existing business processes without investing in IT
Adopting or adapting an application dev eloped by different area or department
within the organization
Reengineering the existing system
Purchasing an off -the shelf application package from a software vendor.
Custom building a new application using internal resources or outsourcing the
developm ent to another company.
Step 4 : Define feasibility and Assess Risk –
Feasibility should focus on whether a particular alternative is worth doing.
Risk –It focus on what can go wrong and what must go right.
Feasibility may be viewed in terms of:
Economic feasibility –An organization may evaluate an alternative in terms
of whether funds and resources exist to support the project.
Technical feasibility –It focuses on the existing technical infrastructure
needed to support the IT solution.
Organizational f easibility -It focuses on how people within the organization
will adapt to this planned organizational change. How will people and way
they do their jobs be impacted?
Other feasibilities –Depending on the situation and the organization, a
business case m ay include other issues, such as legal and ethical feasibility.
Risk should focus on:
Identification –What can go wrong? What must be right ?
Assessment –What is impact of each risk?
Response -How can the organization avoid or minimize the risk ?
Step 5 :Define Total cost of Ownership
It includes
Direct or up -front costs –Initial purchase price of all hardware, software,
and telecommunications equipment, all development or installation costs,
outside consultant fees etc.
Ongoing costs –Salaries, train ing, upgrades, supplies, maintenance etc.
Indirect costs –initial loss of productivity, time lost by users when the
system is down, the cost of auditing equipment, quality assurance, and
post implementation reviews.munotes.in
Page 92
92Step 6: Define Total Benefits of Owne rship
It must include all of direct, ongoing, and indirect benefits associated
with each proposed alternative.
Increasing high -value work: -For example, a salesperson may spend
less time on paper work and more time calling on customers.
Improving accu racy and efficiency: -For example, reducing errors,
duplication, or the number of steps in a process.
Improving decision making: -For example, providing timely and accurate
information.
Improving customer service: -For example, new products or services,
faster or more reliable service, convenience, and so on.
Step 7: Analyze Alternatives
Once costs and benefits have been identified, it is important that all
alternatives be compared with each other consistently. There are several
ways to analyze the p roposed alternatives. The most common are financial
models and scoring models.
Financial models –It focus on either profitability and/ or cash flows. Cash
flow models focus on the net cash , may be positive or negative, and are
calculated by subtracting the cash outflows from cash inflows. In general one
could view the benefit associated with a particular alternative as a source of
cash inflow and the costs as the source of outflows.
The most commonly used cash flow models include payback,
breakeven, r eturn on investment, net present value, and scoring.
Scoring models provide a method for comparing alternatives or
projects based on a weighted score. Scoring model also allow for quantifying
intangible benefits or for different alternatives using multipl e criteria. Using
percentage weights, one can assign values of importance to the different
criteria. The weights must sum to 100 percent, and when multiplied by a score
assigned to each criterion they allow a composite score that is weighted
average.
Step 8 : Propose and Support the Recommendation -Once the alternatives
have been identified and analyzed, the last step is to recommend one of the
options. It is important to remember that a proposed recommendation must be
supported. The business case should be formalized in a professional -looking
report. Remember that the quality and accuracy of your work will be a
reflection on you and your organization.
5.3 PROJECT SELECTION AND APPROVAL
The objective of the business case is to obtain approval and funding
for a proposed alternative. However, a proposed project may have to compete
against several others.munotes.in
Page 93
93The criteria for selecting a project portfolio, a set of projects that an
organization may fund, are very similar to the analysis and subsequent
selection of the proposed project alternatives. An IT project portfolio mainly
composed of projects with low risk or those that do not attempt to take
advantage of new technology may lead to stagnation. The organization may
not move ahead strategically and the IT e mployees may fail to grow
professionally due to lack of challenge. On other hand, an organization that
focuses too heavily on risky projects employing cutting -edge technology may
end up in a precarious position if the IT projects experience serious problem s
and failures. Learning from mistakes can be useful, unless the same mistakes
are repeated over and over. Thus , an organization should attempt to balance
its IT project portfolio with projects that have varying degrees of risk ,cutting
-edge technologies and structure.
5.3.1 The IT Project Selection Process
The selection process determines which projects will be funded in a
given period . This period can be a quarter, year, or a time frame used by
organization. In order to weed out projects that have lit tle chance of being
approved , many organizations use an initial screening process in which
business cases submitted for review are compared with a set of organizational
standards that outline minimum requirements.
Projects that meet the minimum requireme nts are then forwarded to a
decision -making committee of senior managers who have the authority to
approve and provide the resources needed to support the project.
Projects selected should then be assigned to a project manager who
selects the project tea m and then develops a project charter and detailed plan.
5.3.2 The Project Selection Decision
Even though each project proposal should be evaluated in terms of its
value to the organization, it is important to reiterate that projects should not be
underta ken for technology’s sake. The decision to approve a project requires a
number of conditions be met:
The project must map directly to the organization’s strategies and goals.
The project must provide measurable organizational value that can be
verified at the completion of the project.
The selection of a project should be based upon diversity of measures that
include :
i.Tangible costs and benefits.
ii.Intangible costs and benefits.
iii.Various levels throughout the organization ( e.g. individual , process
,depa rtment, and enterprise).munotes.in
Page 94
945.3.3 Balanced Scorecard approach
It helps balance traditional financial measures with operational metrics
across four different prospective: finance, customer satisfaction, internal
business processes, and the organization’s ability to innovate and learn.
Financial perspective : -
How do we look to our shareholders or to those who provide funding
to us ?
Customer perspective : -
How do we look to our customers and other stakeholders ?
Internal Processes Perspective :-
What internal processes must we excel at in order to attract and retain
our customers and other key stakeholders ?
Innovation and Learning Perspective :-
How do we keep getting better ?
5.4 THE PROJECT CHARTER
The project charter and baseline project plan p rovide governance
framework for carrying out or executing the IT project.
It serves as an agreement or contract between the sponsor and project
team-documenting the project’s MOV ,defining its infrastructure
,summarizing the project plan details ,definin g roles and responsibilities
,showing project commitments, and explaining project control mechanisms.
(I)Documenting the project’s MOV :-Although the project’s MOV was
included in the business case, it is important that MOV be clearly defined and
agreed upon before developing or executing the project plan.
(II)Defining the projects infrastructure : -The project charter defines all of
the people, resources, technology, methods, project management processes,
and knowledge areas that are required to support the project. In short ,the
project charter will detail everything needed to carry out the project.
(III) Summarizing the details of the project plan :-The project charter
should summarize the scope, schedule, budget, quality objectives, deliverables
,andmilestones of the project.
(IV) Defining roles and responsibilities : -The project charter should not
only identify the project sponsor, project manager, and project team, but also
when and how they will be involved throughout the project life cycle. In
addition ,the project charter should specify the line of reporting and who will
be responsible for specific decisions.
(V)Showing explicit commitment to the project :-In addition to defining
the roles and responsibilities of the various stakeholders , the project charter
should detail to resources to be provided by project sponsor and specifymunotes.in
Page 95
95clearly who will take ownership of the project’s product once project is
completed.
(VI) Setting out project control mechanisms : -Changes to project’s scope,
schedule ,and budget will undoubtedly be required over the course of the
project. But, the project manager can lose control and the project team can
lose its focus if these changes are not managed properly.
5.4.1 WHAT SHOULD BE IN A PROJECT CHARTER
Project Identi fication :-It is common for all projects to have a unique name
or way to identify them .It is especially necessary if an organization has
several projects underway at once. Naming a project can also give the project
team and stakeholders a sense of identi fy and ownership.
Project Stakeholders :-It is important that the project charter specifically
name the project sponsor and the project manager. This reduces the likelihood
of confusion when determining who will take ownership of the project’s
product and who will be leader of the project. In addition ,the project team
should be named along with their titles or roles in the project ,their phone
numbers , and e -mail addresses. This section should describe who will be
involved in the project, how will be inv olved , and when will be involved.
Project Description :-The project charter should be a single source of
information. Therefore, it may be useful to include a description of the project
to help someone unfamiliar with the project understand not only the details,
but the larger picture as well .This may include a brief overview or
background of the project as to the problem or opportunity that became a
catalyst for the project and the reason or purpose for taking on the project.
Measurable Organizational Value (MOV) :-The MOV should be clear,
concise, agreed on, and made explicit to the entire project stakeholders.
Therefore, the project’s MOV should be highlighted and easily identifiable in
the project charter.
Project Scope: -The project’s scope is the work to be completed . A specific
section of the project charter should clarify not only what will be produced or
delivered by the project team, but what will not be part of the project’s scope.
The scope defined in the project charter can take the form o f a narrative
description of the products or services produced by the project. This narrative
is often called the statement of work (SOW).
Project Schedule :-Although the details of project’s schedule will be in the
project plan , it is important to summa rize the detail of the plan with respect to
the expected start and completion dates. In addition, expected dates for major
deliverables, milestones, and phases should be highlighted and summarized at
a very high level.
Project Budget :-A section of the pr oject charter should highlight the total
cost of the project. The total cost of the project should be summarized directly
from the project plan.munotes.in
Page 96
96Quality Standard: -Although a quality management plan should be in place
to support the project, a section tha t identifies any known or required quality
standards should be made explicit in the project charter.
Resources: -Because the project charter acts as an agreement or contract, it
may be useful to specify the resources required and who is responsible for
providing those resources .Resources may include people, technology, or
facilities to support the project team.
Assumptions and Risks :-Any risks or assumptions should be documented in
the project charter. Assumptions may include things that may go right , such a
particular team member being available for the project , or specific criteria
used in developing the project plan estimates. Risks on other hand, may be
thought of as anything that can go wrong or things that may impact the
success of the project.
Project Charter should be summarize the following potential impacts
Key situations or events that could significantly impact the project’s
scope, schedule, or budget -These risks, their likelihood and the strategy
to overcome or minimize their impact shou ld be detailed in the project’s
risk plan.
Any known constraints that may be imposed by the organization or
project environment -Known constraints may include such things as
imposed deadlines, budgets, or required technology tools or platforms.
Dependenc ies on other projects internal or external to the
organization -In most cases, an IT project is one of several being
undertaken by an organization .Dependencies between projects may exists,
especially if different application systems or technology platform s must be
integrated.
Impacts on different areas of the organization –IT projects operate in a
broader environment than the project itself. As a result, the development
and implementation of an IT solution will have impact on the
organization. It is impo rtant to describe how the project will impact the
organization in terms of disruption, downtime, or loss of productivity.
Any outstanding issues –It is important to highlight any outstanding
issues that need further resolution. These may be issues identif ied by
project sponsor, the project manager, or the project team that must be
addressed and agreed upon at some point during the project. They may
include such things as resources to be provided or decisions regarding the
features or functionality of the s ystem.
Project Administration: -Project Administration focuses on knowledge
areas, processes, and controls that will support the project. These are actually
separate sub plans or strategies that make up the project management plan.munotes.in
Page 97
97A communication plan that outlines how the project’s status or progress
will be reported to various stakeholders. This plan also includes a process
for reporting and resolving significant issues or problems as they arise.
A scope management plan that describes how changes to the project’s
scope will be submitted logged and reviewed.
A quality management plans that details how quality planning, assurance,
and control will be supported throughout project life cycle.
A change management and implementation plan that will specify h ow the
project’s product will be integrated into the organizational environment.
A human resource plan for staff acquisition and team development.
Acceptance and Approval: -Since the project charter serves as an agreement
or contract between the project sponsor and project team, it may be necessary
to have key stakeholders sign off on the project charter. By signing the
document, the project stakeholder show formal acceptance of the project and
therefore, gives the project manager and team the authority t o carry out the
project plan.
References In developing the project charter and plan, the project manager
may use a number of references. It is important to document these references
in order to add credibility to the project charter and plan , as well a s to provide
a basis for supporting certain processes ,practices, or estimates.
5.5 PROJECT SCOPE DEFINITION
Developing a scope statement is a useful first step for defining the
scope of project and setting a boundary. A project’s scope, however, should
also be defined in terms of the deliverables that the team must provide. These
deliverables can be divided into project –oriented deliverables and product
oriented deliverables. This separation gives the team a clearer definition of the
work to be accompl ished and improves the likelihood of accurately assigning
resources and estimating the time and cost of completing the work.
5.5.1 Project -Oriented Scope
Project –oriented deliverables , orscope , support the project management
and IT development proces ses that are defined in the information technology
project methodology.
Project scope includes such things as the business case, project charter,
and project plan and defines the work products of various ITPM phases.
Project –oriented deliverables also include specific deliverables such as a
current systems study, requirements definition, and the documented design of
the information system.
Project –oriented deliverables requires time and resources and therefore, must
be part of the overall project sc hedule and budget. Their role is to ensure thatmunotes.in
Page 98
98project processes are being completed so that the project’s product achieves
the project’s MOV and objectives. Project -oriented deliverables also provide
tangible evidence of the project’s progress.
5.5.2Product –Oriented Scope
Product scope therefore focuses on identifying the features and
functionality of the information system to be implemented. A useful tool for
refining the scope boundary and defining what the system must do is a
modeling tool calle d a context level data flow diagram (DFD).
Acontext level DFD , presents a high level representation of the
system that has one process and depicts all the inflows and outflows of data
and information between the system and its external entities.
Another useful tool is Use Case Diagram , which has been used in object –
oriented world as part of Unified Modeling Language (UML).
5.6PROJECT SCOPE VERIFICATION
The project’s scope must be verified and formally accepted by the project
sponsor and other approp riate stakeholders. It is scope management process
that provides a mechanism for ensuring that the project deliverables are
completed.
MOV –Is project’s MOV clearly defined and agreed upon? Failure
to define and agree upon the MOV could result in scope changes later
in project, which can lead to added work impacting the project’s
schedule and budget.
Deliverables –Are the deliverables tangible and verifiable? Do they
support the project’s MOV?
Quality Standards -Are controls in place to ensure that th ew o r kw a s
not only completed, but completed to meet specific standards?
Milestones –Milestones tell us that a deliverable was not only
completed, but reviewed and accepted.
Review and acceptance -Are both sides clear in their expectations?
The project’ s scope must be reviewed and accepted by the project
stakeholders. The project sponsor must formally accept the boundary,
product to be produced, and the project –related deliverables. The
project team must be clear on what it must deliver. In both cases,
expectations must be realistic and agreed upon.
5.7 SCOPE CHANGE CONTROL
It is concerned with managing actual changes to the project’s scope as
when they occur, to ensure that any changes to the project‘s scope will be
beneficial.munotes.in
Page 99
99Scope grove -It descri bes a project team’s inability to define the project’s
scope. This situation is common early in a project when the project team and
sponsor have trouble understanding what the project is supposed to
accomplish. Scope grove can be minimized by having a clea rly defined MOV
and following or applying the processes, concepts, and tools.
Scope creep –It is adding features to the system once the scope of the project
has been approved.It does not always come from the project sponsor side. The
project team itself m ay come across interesting or novel ideas as the project
work progresses. It must be identified and controlled throughout the project
because it lengthen the project schedule and, in turn, lead to cost overruns.
Scope leap -It can occur as a result of cha nges in environment , the business
,and the competitive makeup of the industry .Scope leap entails changing the
MOV and therefore, requires that the organization rethink the value of the
current project. If this change is critical, the organization may be better off
pulling the plug on the current project and starting over by conceptualizing
and initiating a new project.
5.8WORK BREAKDOWN STRUCTURE
The WBS should Be Deliverable Oriented: -
The focus of a project should be to produce something, not merely on
completing a specified number of activates. Although the WBS does not
provide for any explicit looping, some activities may have to be repeated until
the milestone is achieved. For example, software testing may uncover a
number of problems or bugs that make the software system unacceptable to
the client.
The WBS Should Support the Project’s MOV: -
The WBS should include only tasks or activities that allow for the
delivery of the project’s deliverables. Before continuing with the development
of the proje ct plan, project team should ensure that the WBS allows for the
delivery of the entire project’s deliverables as defined in the scope. In turn,
this will ensure that the project is more likely to achieve its MOV.
-0.0 EC Bank Project
+1.0 Conceptualize a nd initialize project
+2.0 Develop charter and plan
+3.0 Analysis
+4.0 Design
+5.0 Construction
-6.0 Testing
+6.1 Test Planmunotes.in
Page 100
100+7.0 Implementation
+8.0 Close project
+9.0 Evaluate project success
Figure 1.1 -Work Breakdown Structure
The Level of De tail Should Support Planning and Control: -
The WBS provides a bridge between the project’s scope and project
plan-that is, the schedule and budget. Therefore, the level of detail should
support not only the development of the project plan but allow the pr oject
manager and project team to monitor and compare the project’s actual
progress to the original plan’s schedule and budget.
Developing the WBS Should Involve the People Who Will Be Doing the
Work: -One way to ensure that the WBS has the appropriate lev el of detail to
ensure that the people who do the work are involved in its development. A
person who has experience and expertise in a particular area probably has a
better feel for what activities need to be performed in order to produce a
particular pro ject deliverable.
Learning Cycles and Lessons Learned can Support the Development of a
WBS: -
By using the concept of learning cycles, the project team can focus on
what they know (the facts) ,what they think they know (assumption) , and
what they need to find out (research) in order to develop a more useful WBS.
Lessons learned from previous projects can be helpful in ensuring that the
WBS and subsequent project plan are realistic and complete.
5.9 SOFTWARE PROJECT ESTIMATION
Estimation of the size of so ftware is an essential part of Software
Project Management. It helps the project manager to further predict the
effort and time which will be needed to build the project. Various measures
are used in project size estimation. Some of these are:-6.2 Test results report
6.2.1 Review test plan with client
6.2.2 Carry out test plan
6.2.3 Analyze results
6.2.4 Prepare test results report and presentation
6.2.5 Present test results to client
6.2.6 Address any software issues or problems
6.2.7 Milestone: Client signs off on test results+6.3 Milestone: Testingmunotes.in
Page 101
101Lines of Co de
Number of entities in ER diagram
Total number of processes in detailed data flow diagram
Function points
1. Lines of Code (LOC): As the name suggest, LOC count the total number
of lines of source code in a project. The units of LOC are:
KLOC -Thousand lines of code
NLOC -Non comment lines of code
KDSI -Thousands of delivered source instruction
The size is estimated by comparing it with the existing systems of
same kind. The experts use it to predict the required size of various
components of software a nd then add them to get the total size.
Advantages:
Universally accepted and is used in many models like COCOMO.
Estimation is closer to developer’s perspective.
Simple to use.
Disadvantages:
Different programming languages contains different number of l ines.
No proper industry standard exist for this technique.
It is difficult to estimate the size using this technique in early stages of
project.
2. Number of entities in ER diagram: ER model provides a static view of
the project. It describes the entities and its relationships. The number of
entities in ER model can be used to measure the estimation of size of
project. Number of entities depends on the size of t he project. This is
because more entities needed more classes/structures thus leading to more
coding.
Advantages:
Size estimation can be done during initial stages of planning.
Number of entities is independent of programming technologies used.
Disadvant ages:
No fixed standards exist. Some entities contribute more project size than
others.
Just like FPA, it is less used in cost estimation model. Hence, it must be
converted to LOC.
3. Total number of processes in detailed data flow diagram: Data Flow
Diag ram (DFD) represents the functional view of a software. The model
depicts the main processes/functions involved in software and flow of data
between them. Utilization of number of functions in DFD to predict software
size. Already existing processes of sim ilar type are studied and used to
estimate the size of the process. Sum of the estimated size of each process
gives the final estimated size.munotes.in
Page 102
102Advantages:
It is independent of programming language.
Each major process can be decomposed into smaller processes .T h i sw i l l
increase the accuracy of estimation
Disadvantages:
Studying similar kind of processes to estimate size takes additional time
and effort.
All software projects are not required to construction of DFD.
4. Function Point Analysis: In this method , the number and type of
functions supported by the software are utilized to find FPC(function point
count). The steps in function point analysis are:
Count the number of functions of each proposed type.
Compute the Unadjusted Function Points(UFP).
Find To tal Degree of Influence(TDI).
Compute Value Adjustment Factor(VAF).
Find the Function Point Count(FPC).
The explanation of above points given below:
Count the number of functions of each proposed type: Find the
number of functions belonging to the followi ng types:
External Inputs: Functions related to data entering the system.
External outputs:Functions related to data exiting the system.
External Inquiries: They leads to data retrieval from system but don’t
change the system.
Internal Files: Logical files maintained within the system. Log files are
not included here.
External interface Files: These are logical files for other applications
which are used by our system.
Compute the Unadjusted Function Points(UFP): Categorise each of
the five function types a s simple, average or complex based on their
complexity. Multiply count of each function type with its weighting
factor and find the weighted sum. The weighting factors for each type
based on their complexity are as follows:
Function type Simple Average Complex
External Inputs 3 4 6
External Output 4 5 7
External Inquiries 3 4 6
Internal Logical Files 7 10 15
External Interface Files 5 7 10
Find Total Degree of Influence: Use the ’14 general characteristics’ of
as y s t e mt of i n dt h ed e g r e eo fi n f l u e n c e of each of them. The sum of all 14
degrees of influences will give the TDI. The range of TDI is 0 to 70. The 14
general characteristics are: Data Communications, Distributed Data
Processing, Performance, Heavily Used Configuration, Transaction Rate,
On-Line Data Entry, End -user Efficiency, Online Update, Complexmunotes.in
Page 103
103Processing Reusability, Installation Ease, Operational Ease, Multiple Sites
and Facilitate Change.
Each of above characteristics is evaluated on a scale of 0 -5.
Compute Value Adjustment Factor(VA F):Use the following formula
to calculate VAF
VAF = (TDI * 0.01) + 0.65
Find the Function Point Count: Use the following formula to calculate
FPC
FPC = UFP * VAF
Advantages:
It can be easily used in the early stages of project planning.
It is independin g on the programming language.
It can be used to compare different projects even if they use different
technologies (database, language etc).
Disadvantages:
It is not good for real time systems and embedded systems.
Many cost estimation models like COCOMO uses LOC and hence FPC
must be converted to LOC.
5.10 COCOMO MODEL
The Constructive Cost Model (COCOMO) is an algorithmic software
cost estimation model developed by Barry Boehmin 1981. The model uses a
basic regression formula, with parameters that are derived from historical
project data and current project characteristics. It predicts the efforts,
development time, average team size and effort required to develop a software
project .
COCOMO applies to three classes of software projects:
Organic proj ects-This suits small software team since it has a generally
stable development environment. The problem is well understood and has been
solved in the past. (In short, "small" teams with "good" experience working
with "less than rigid" requirements.)
Example: Small data processing or Inventory management system.
Semi -detached projects -The software project which requires more
experience and better guidance and creativity. For example, Compiler or
different Embedded System (In short, "medium" teams with mixed experience
working with a mix of rigid and less than rigid requirements.)
Example: Database design or OS development.munotes.in
Page 104
104Embedded projects -The project with operating tight constraints and
requirements is under this category. The developer requires high experiences
and has to be creative to develop complex models. (In Short, developed within
a set of "tight" constraints (hardware, software, operational,)
Example: Banking software or Traffic light control software.
Types of COCOMO model
COCOMO mode l allows software manager to decide how detailed they
would like to conduct the cost estimation for their own project. COCOMO can
unveil the efforts and schedule of a software product based on the size of the
software in different levels. There are basic C OCOMO, Intermediate
COCOMO , and Detailed/Completed COCOMO .
Basic COCOMO model
The basic COCOMO is used for rough calculation which limits
accuracy in calculating software estimation. This is because the model solely
considers based on lines of source code together with constant values obtained
from software project types rather than other factors which have major
influences to Software development process as a whole.
Intermediate COCOMO model
Intermediate COCOMO model is an extension of the Basic COCOMO
model which includes a set of cost drivers into account in order to enhance
more accuracy to the cost estimation model as a result.
Classification of Cost Drivers and their attributes:
(i) Product attributes –
Required software reliability extent
Size of t he application database
The complexity of the product
(ii) Hardware attributes –
Run-time performance constraints
Memory constraints
The volatility of the virtual machine environment
Required turnabout time
(iii) Personnel attributes –
Analyst capability
Software engineering capability
Applications experience
Virtual machine experience
Programming language experience
(iv) Project attributes –
Use of software tools
Application of software engineering methods
Required development schedulemunotes.in
Page 105
105Complete/detailed COCOMO model
The model incorporates all qualities of both Basic COCOMO and
Intermediate COCOMO strategies on each software engineering process. The
model accounts for the influence of the individual development phase
(analysis, design, etc.) of the projec t.
The effort is calculated as a function of program size and a set of cost
drivers are given according to each phase of the software lifecycle.
For instance, detailed COCOMO will perform cost estimation in each
development phase of Waterfall Model.
Numericals:
In COCOMO, the general calculation steps of COCOMO -based cost
estimation are the following:
1.Get an initial estimate of the development effort from evaluation
ofthousands of delivered lines of source code KDLOC .
2.Determine a set of 15 cost fac torsfrom various attributes of the project.
3.Calculate the effort estimate by multiplying the initial estimate with all the
multiplying factors i.e., multiply the values in previous steps.
Example:
1.Basic COCOMO model
Suppose the project was estimated to be 300 KDLOC, calculate the
effort, development time, and time of each of the 3 modes
Note: the basic COCOMO is used in Organic mode by default .
Here, T he estimated effort and scheduled time for the project are given
by the relation:
Effort (E) = a*(KLOC)bMM
Scheduled Time (D) = c*(E)dMonths(M)
Where,
E=Total effort required for the project in Man -Months (MM).
D=Total time required for project development in Months (M).
KLOC =the size of the code for the project in Kilo lines of code.
a, b, c, d =The constant parameters for a software project.munotes.in
Page 106
106PROJECT TYPEabcdOrganic2.41.052.50.38Semidetached31.122.50.35Embedded3.61.22.50.32
Solution:
Given estimated size of project is: 300 KLOC
For Organic
Effort (E) = a*(KLOC)b= 2.4*( 300)1.05=957.61 MM
Scheduled Time (D) = c*(E)d= 2.5*(957.61)0.38= 33.95 Months(M)
Avg. Resource Size = E/D = 957.61/33.95 = 28.21 Mans
Productivity of Software = KLOC/E = 300/957.61 = 0.3132 KLOC/MM =
313 LOC/MM
For Semidetached
Effort (E) = a*(KLOC)b= 3.0*(300)1.12=1784.42 MM
Scheduled Time (D) = c*(E)d= 2.5*(1784.42)0.35= 34.35 Months(M)
For Embedded
Effort (E) = a*(KLOC)b= 3.6*(300)1.2=3379.46 MM
Scheduled Time (D) = c*(E)d= 2.5*(3379.46)0.32= 33.66 Months(M)
2.Intermediate COCOMO model
The estimated effort and scheduled time are given by the relationship:
Effort (E) = a*(KLOC)b*EAF MM
Scheduled Time (D) = c*(E)dMonths(M)
Where,
E=Total effort required for the project in Man -Months (MM).
D=Total time required for project develo pment in Months (M).
KLOC =The size of the code for the project in Kilo lines of code.
a, b, c, d =The constant parameters for the software project.
EAF =It is an Effort Adjustment Factor, which is calculated by multiplying
the parameter values of diff erent cost driver parameters. For ideal, the value
is 1.
Suppose project was estimated with a size of 300 KLOC. Calculate the
Effort, Scheduled time for development by considering developer having high
application experience and very low experience in pr ogramming.munotes.in
Page 107
107COST DRIVERS
PARAMETERSVERY
LOWLOWNOMINALHIGHVERY
HIGHProduct ParameterRequired Software0.750.881.151.4Size of Project DatabaseNA0.941.081.16Complexity of The Project0.70.8511.151.3Hardware ParameterPerformanc e RestrictionNANA1.111.3Memory RestrictionNANA1.061.21virtual Machine
EnvironmentNA0.871.151.3Required Turnabout TimeNA0.9411.071.15Personnel ParameterAnalysis Capability1.461.190.860.71Application Experience1.291.130.910.82Software Engineer Capability1.421.170.860.7Virtual Machine Experience1.211.10.9NAProgramming Experience1.141.0710.95NAProject ParameterSoftware Engineering
Methods1.241.10.910.82Use of Software Tools1.241.10.910.83Development Time1.231.0811.041.1
Solution:
Given the estimated size of the project is: 300 KLOC
Developer having highly application experience: 0.82 (as per above table)
Developer having very low experience in programming: 1.14(as per abov e
table)
EAF = 0.82*1.14 = 0.9348
Effort (E) = a*(KLOC)b*EAF = 3.0*(300)1.12*0.9348 = 1668.07 MM
Scheduled Time (D) = c*(E)d= 2.5*(1668.07)0.35= 33.55 Months(M)
3.The Detailed COCOMO
In detailed cocomo, the whole software is divided into different
modu les and then we apply COCOMO in different modules to estimate
effort and then sum the effort.
The Six phases of detailed COCOMO are:
1.Planning and requirements
2.System design
3.Detailed design
4.Module code and test
5.Integration and test
6.Cost Constructive modelmunotes.in
Page 108
108Advantages and Disadvantages of COCOMO Model
Following are some advantages and disadvantages of the COCOMO model.
Advantages
Easy to estimate the total cost of the project.
Easy to implement with various factors.
Provide ideas about historical projects.
Disadvantages
It ignores requirements, customer skills, and hardware issues.
It limits the accuracy of the software costs.
It mostly depends on time factors.
COCOMO II Model
COCOMO -IIis the revised version of the original Cocomo (Constructive
Cost Model) and is developed at University of Southern California.
COCOMO II takes into account different approaches to software
development, reuse, etc. It is the model that allows one to estimate the cost,
effort and schedule when planning a new software development activity.
COCOMO II incorporates a variety of sub -models that generate increasingly
detailed software estimates .The sub -models in COCOMO II are:
a.Application composition model: Used w hen software is composed from
existing parts.
b.Early design model: Used when requirements are available but design
has not yet started.
c.Reuse model: Used to compute the effort of integrating reusable
components.
d.Post architecture model: Used once the syst em architecture has been
designed and more information about the system is available.
COCOMO II Estimation
1.End User Progra mming:
Application generators are used in this sub -model. End user writes
the code by using these application generators.Application generators &composition aids
Application CompositionEnd User
System IntegrationInfrastructuremunotes.in
Page 109
109Example –Spreadsheets, report generator, etc.
2.Intermediate Sector:
a. Application Generators andComposition Aids:
This category will create largely prepackaged capabilities for user
programming. Their product will have many reusable components. Typical
firms operating in this sector are Microsoft, Lotus, Oracle, IBM, Borland,
Novell.
b. Application Composition Sector:
This category is too diversified and to be handled by prepackaged
solutions. It includes GUI, Databases, domain specific components such as
financial, medical or industrial process control packages.
c. System Integration:
This category deals with large scale an d highly embedded systems.
3.Infrastructure Sector:
This category provides infrastructure for the software development
like Operating System, Database Management System, User Interface
Management System, Networking System, etc.
1.Stage -I:
It supports estimation of prototyping. For this it uses Application
Composition Estimation Model . This model is used for the prototyping stage
of application generator and system integration.IntermediateSectorApplicationGeneratorsandApplicationCompositionSystemIntegration
StagesofCOCOMOIIStageIStageIIStageIIImunotes.in
Page 110
110a.Stage -II:
It supports estimation in th e early design stage of the project, when
we less know about it. For this it uses Early Design Estimation Model .T h i s
model is used in early design stage of application generators, infrastructure,
and system integration.
b.Stage -III:
It suppo rts estimation in the post architecture stage of a project. For
this it uses Post Architecture Estimation Model .T h i sm o d e li su s e da f t e rt h e
completion of the detailed architecture of application generator,
infrastructure, and system integration.
COCOMO II can be used for the following major decision situations
Making investment or other financial decisions involving a software
development effort
Setting project budgets and schedules as a basis for planning and control
Deciding on or negotiating tradeoffs among software cost, schedule,
functionality, performance or quality factors
Making software cost and schedule risk management decisions
Deciding which parts of a software system to develop, reuse, lease, or
purchase
Making legacy software inventory decis ions: what parts to modify, phase
out, outsource, etc
Setting mixed investment strategies to improve organization's software
capability, via reuse, tools, process maturity, outsourcing, etc.
COMPARISION of COCOMO and COCZOMO -II
COCOMO I COCOMO II
COCOMO I is convenient in the
waterfall models of the software
development cycle.COCOMO II is helpful in non -
sequential, rapid development and reuse
models of software.
Effort equation’s exponent is
determined by 3 development
modes.Effort equation’s exponen ti s
determined by 5 scale factors.
This model is based upon the
linear reuse formula.This model is based upon the non -linear
reuse formula
Development begins with the
requirements assigned to the
software.It follows a spiral type of development.
5.11 EARNED VALUE MANAGEMENT
Earned value management (EVM) is a project management
methodology that integrates schedule, costs, and scope to measure projectmunotes.in
Page 111
111performance. Based on planned and actual values, EVM predicts the future
and enables project manager s to adjust accordingly. It is a technique that
project managers use to track the performance of their project against project
baselines. Often the progress of a project is thou ght of simply as being ahead
or behind schedule and over or under budget.
This is where knowing the earned value helps. It can provide deeper
information on your project. And when learning about earned value, it’s
important to remember that there are thr ee terms associated with it, which are
each slightly different.
1.Earned Value Analysis (EVA): This project management technique is
quantitative. It evaluates project performance by figuring out the likely results
of the project. It does this by comparing t he progress and budget of work
planned to the actual costs.
2.Earned Value Management (EVM): This methodology measures project
performance with an integrated schedule and budget, which is based on
theproject work breakdown structure (WBS).
3.Earned Valued Management System (EVMS): This is the collection of
tools, templates , processes and procedures that an organi zation uses to do
EVM.
Calculations for Earned Value Management
There are calculations that can be done quickly and easily to execute EVM.
To do so, you need to know the following:
c.Planned Value (PV)
Planned value is the budgeted cost for work scheduled (BCWS). PV
varies based on the scope of work in consideration and the point where you’re
at in the overall schedule.
PV = Total project cost * % of planned work
For example, let’s say, the PV for your 5 -month project is $25,000:
PV for the complete projec t = $25,000
PV at 2 months = $25,000 * 40% = $10,000
You can also calculate PV for a time period, say, month 2 to month 4 =
$25,000 * 60% = $15,000.
d.Actual Costs (AC)
Actual costs, also referred to as actual cost of work performed
(ACWP), is relatively straightforward. If you are using a robust project cost
management software, tracking actual costs should not be a challenge.
However, it’s important to remember to include several hidden costs —
material, resource, hardware, software licenses, overheads, et c.munotes.in
Page 112
112You can look at AC cumulatively, accounting for all the activities
done from the beginning of the project to date or over a specific time period.
In our example, let’s assume, AC at the end of 2 months = $15,000
e. Earned Value (EV)
Now, this is where E VM gets interesting. You’ve made a plan to finish some
amount of work and budgeted accordingly. But, from experience, you know
that there is bound to be some discrepancy from your estimate. At the end of 2
months, you may have planned to complete 40% of yo ur work, but let’s say
you managed to just finish 30%.
The question, then, is, what’s the budgeted cost for this work ? EV, also called
as budgeted cost for work performed (BCWP), gives you the answer.
In our example:
EV = Total project cost * % of actual work = $25,000 * 30% = $7,500
Variance Analysis
Planned value, actual cost, and earned value numbers are fundamental to
variance calculations. At this point, the project manager wants to know how
far off we are from the project baseline. This can be det ermined through
schedule and cost variance.
a. Schedule Variance (SV)
Schedule variance is a quantitative indicator of your divergence from the
initial planned schedule. A negative SV indicates that we are behind schedule,
a positive SV indicates that we are ahead of schedule and zero means that we
are exactly on schedule.
SV = EV –PV
In our example, SV at 2 months = $7,500 –$10,000 = -$2,500
SV% = (SV/PV) *100 = ( -$2,500/$10,000) *100 = -25%
This implies that we are 25% behind schedule. It’s interesting to note
that we aim to understand schedule, a time component, from the perspective
of costs. To arrive at these costs though, we needed to know the scope of work
planned and completed. This is how the three pillars —scope, time and cost
come together in EVM .
b. Cost Variance (CV)
Cost variance is a quantitative indicator of your divergence from the
initial planned budget. A negative CV indicates that we are over budget, a
positive CV indicates that we are under budget and zero means that we are
exactly on budg et.
CV = EV –AC
In our example, CV at 2 months = $7,500 –$15,000 = -$7500
CV% = (CV/EV) *100 = ( -$7,500/$7,500) *100 = -100%
This implies that we are 100% over budget.munotes.in
Page 113
113Again, this is an instance of how scope, time and cost come together to
give you a cl ear picture of where you stand at the moment in your project.
5.12 SUMMARY
The business case is defines the problem or opportunity, MOV,
feasibility, costs , and benefits of several alternatives that an organization may
choose in order to achieve its g oals and strategies. Based on the analysis of the
alternatives identified , a recommendation is made to approve and fund a
specific project.
The business case is formalized in a report to senior management who
may review several proposed projects. The dec ision to fund a particular
project depends on resources available and the value of the project to the
organization. The balanced scorecard approach focuses on four perspectives –
financial, customer, internal processes and innovation and learning . An
organization should make the project selection decision based on a diverse set
of measures and in terms of how well the project supports the goal and
strategies of the organization.
The project charter documents the project’s MOV and describes the
infrastruc ture needed to support the project. In addition, the project charter
should provide a consolidated source of information about the project and
reduce confusion and misunderstanding. The project charter and project plan
should be developed together –the de tails of project plan need to be
summarized in the project charter, and the infrastructure outlined in the
project charter will influence the estimates used to develop the project plan.
Product -oriented deliverables focus on the high level features and
functionality of the application system –the project’s product. On the other
hand, project -oriented deliverables focus on the project’s processes as defined
in the IT project methodology.
Scope grope is a common occurrence in the early stages of the project .
Often the project team struggle to define what the project is all about and what
work must be done.
Scope creep, on the other hand, is a common occurrence in many
projects. It entails adding additional features or functions to the scope once the
scope h as been set and approved. This phenomenon can increase the schedule
and budget, causing the project to miss its deadline and budget targets.
Sample Questions
1.What is a business case?
2.Why should an organization develop a business case?
3.Describe the balance d scorecard approach.
4.What is the purpose of a project charter
5.How does the project charter support the project plan?
6.What is a project’s scope?
7.Describe the scope definition process.munotes.in
Page 114
1148.Describe the scope verification process.
9.Describe the scope change contr ol process.
10.What is a WBS? What purpose does it serve?
Reference Books:
1.Software Engineering, 5thand 7thedition, by Roger S Pressman, McGraw
Hill publication.
2.Managing Information Technology Project 6thedition , by Kathy Schwalbe
, Cengage Learning publ ication.
3.Software Engineering 3rdedition by KK Agarwal , Yogesh Singh , New
Age International publication.
4.Information Technology Project Management by Jack T Marchewka
Wiley India publication.
5.Software Engineering for students: A Programming Approach by Douglas
Bell, Pearson publication.
6.Software Engineering Project Management by Richard H. Thayer Wiley
India Publication.
munotes.in
Page 115
115Module V
6
PROJECT SCHEDULING AND
PROCUREMENT MANAGEMENT
Unit Structure
6.0Objectives
6.1Introduction
6.2Overview
6.1.1 Scheduling Principals
6.1.2 Relationship between People and Effort
6.2.3 Project Effort Distribution
6.3Scheduling
6.3.1 Tracking Project Schedules
6.3.2 Tracking Increment Progress for OO Projects
6.3.3 Webapp Project Scheduling
6.3.4 Earned Value Analysis
6.4Project Procurement Management
6.4.1 Process of Project Procurement M anagement
6.4.2 Eight Steps for a Procurement Management Plan
6.5Degree of Rigor
6.5.1 Four various degrees of rigor
6.5.2 Defining a Task Set for the Software Project
6.6 Critical Path Method (CPM)
6.6.1 Critical Path Method helps in:
6.6.2 Technique for CPM
6.6.3 Steps for CPM
6.6.4 Examples
6.7Summary
6.8Questions
6.9Reference booksmunotes.in
Page 116
1166.0 OBJECTIVES OF PROJECT SCHEDULING
To arrange the manufacturing activities in such a way that the cost of
production is minimized and the goods produced are delivered on due dates is
the main objective of Project Scheduling. In order to meet the delivery dates
the sequence of operations is properly planned. To have minimum total time
of production by having better resources utilisation we use sch eduling. We
can also make use of this for having maximum capacity utilization and
reducing the labour cost by minimization of idleness of machines and
manpower. It also helps avoid unbalanced allocation of work among the
various departments and workstation s.
6.1 INTRODUCTION
Project Scheduling in a project is a roadmap of all activities to be done
with specified order and within time slot allotted to each activity. Project
managers tend to define various tasks, and project milestones and they arrange
them keeping various factors in mind. They look for tasks lie in critical path in
the schedule, which are necessary to complete in specific manner (because of
task interdependency) and strictly within the time allocated. Arrangement of
all tasks, which lies ou t of critical path are less likely to impact overall
schedule of the project.
6.2 OVERVIEW
Scheduling in project management is the listing of activities,
deliverables, and milestones within a project. A schedule also usually includes
the planned start an d finish date, duration, and resources assigned to each
activity. Effective project scheduling is a critical component of successful
time management.
For scheduling a project, following is necessary to -
Break down the project tasks into smaller, managea ble form
Find out various tasks and correlate them
Estimate time frame required for each task
Divide time into work -units
Assign adequate number of work -units for each task
Calculate total time required for the project from start to finishmunotes.in
Page 117
117In fact, when pe ople discuss the processes for building a schedule,
they are usually referring to the first six processes of time management:
Plan schedule management.
Define project activities.
Sequence activities.
Estimate resources.
Estimate durations.
Develop th e project schedule
6.2.1 Scheduling Principles
Compartmentalization -the product and process must be decomposed
into a manageable number of activities and tasks
Interdependency -tasks that can be completed in parallel must be
separated from those that must completed serially
Time allocation -every task has start and completion dates that take
the task interdependencies into account
Effort validation -project manager must ensure that on any given day
there are enough staff members assigned to comple ted the tasks within the
time estimated in the project plan
Defined Responsibilities -every scheduled task needs to be assigned to
a specific team member
Defined outcomes -every task in the schedule needs to have a defined
outcome
(usually a work prod uct or deliverable)
Defined milestones -a milestone is accomplished when one or more
work products from an engineering task have passed quality review
6.2.2 Relationship between People and Effort
Adding people to a project after it is behind schedule o ften causes the
schedule to slip further
The relationship between the number of people on a project and
overall productivity is not linear (e.g. 3 people do not produce 3 times the
work of 1 person, if the people have to work in cooperation with one
anoth er)munotes.in
Page 118
118The main reasons for using more than 1 person on a project are to
get the job done more rapidly and to improve software quality.
6.2.3 Project Effort Distribution
The 40 -20-40 rule:
40% front -end analysis and design
20% coding
40% back -end testi ng
Generally accepted guidelines are:
02-03 % planning
10-25 % requirements analysis
20-25 % design
15-20 % coding
30-40 % testing and debugging
6.3 SCHEDULING
Task networks (activity networks) are graphic representations can be
of the task interde pendencies and can help define a rough schedule for
particular project
Scheduling tools should be used to schedule any non -trivial project.
Program evaluation and review technique (PERT) and critical path
method
(CPM) are quantitative techniques that al low software planners to identify
the chain of dependent tasks in the project work breakdown structure
(WBS) that determine the project duration time.
Timeline (Gantt) charts enable software planners to determine what
tasks will be need to be conducted at a given point in time (based on
estimates for effort, start time, and duration for each task).
The best indicator of progress is the completion and successful review
of a defined software work product.
Time -boxing is the practice of deciding a priori th e fixed amount of
time that can be spent on each task. When the task’s time limit ismunotes.in
Page 119
119exceeded, development moves on to the next task (with the hope that a
majority of the critical work was completed before time ran out).
6.3.1 Tracking Project Schedules
Periodic project status meetings with each team member reporting
progress and problems
Evaluation of results of all work product reviews
Comparing actual milestone completion dates to scheduled dates
Comparing actual project task start -dates to scheduled start-dates
Informal meeting with practitioners to have them asses subjectively
progress to date and future problems
Use earned value analysis to assess progress quantitatively
6.3.2 Tracking Increment Progress for OO Projects
Technical milestone: OOanalysis complete
All hierarchy classes defined and reviewed
Class attributes and operations are defined and reviewed
Class relationships defined and reviewed
Behavioural model defined and reviewed
Reusable classed identified
Technical milestone: OOdesign complete
Subsystems defined and reviewed
Classes allocated to subsystems and reviewed
Task allocation has been established and reviewed
Responsibilities and collaborations have been identified
Attributes and operations have been designed and re viewed
Communication model has been created and reviewed
Technical milestone: OO programming complete
Each new design model class has been implementedmunotes.in
Page 120
120Classes extracted from the reuse library have been implemented o
Prototype or increment has been buil t
Technical milestone: OO testing complete
The correctness and completeness of the OOA and OOD models has
been reviewed
Class -responsibility -collaboration network has been developed and
reviewed
Test cases are designed and class -level tests have been co nducted for
each class
Test cases are designed, cluster testing is completed, and classes have
been integrated
System level tests are complete
6.3.3 Webapp Project Scheduling
During the first iteration a macroscopic is developed by allocating
effort to specific tasks (it is understood that this is changeable schedule)
The project is broken up into increments and the increments are
refined in to detailed schedules as each is begun (some increments may be
developed in parallel)
Each task on the task lis t for each increment is adapted in one of four
ways as its detailed schedule is created task is applied as is task is
eliminated because it is not necessary for the increment new (custom) task
is added task is refined (elaborated) into a number of named su btasks that
each becomes part of the schedule
This process continues until each planned increment is completed
6.3.4 Earned Value Analysis
Earned value is a quantitative measure given to each task as a percent
of project completed so far.
The total ho urs to complete each project task are estimated (BCWS -
budgeted cost of work scheduled)
The effort to complete the project is computed by summing the
effort to complete each task (BAC -budget at completion)
Each task is given an earned value based on i ts estimated
percentage contribution to the total (BCWP -budgeted cost of work
completed).munotes.in
Page 121
121It is compute the actual cost of work performed (ACWP) at any point
in the project and to compute progress indicators for both schedule and
costs based on these me asures
6.4 PROJECT PROCUREMENT MANAGEMENT
In project Management, Procurement is when you need to
purchase, rent or contract with some external resource to meet your project
goal. These relationships and any process in the project need management.
Managi ng these relationships means getting the best quality from
the outside vendors employed by the company to assist in its doing
business. There are constraints in a relationship with vendors that revolve
around cost and time. Procurement management is a way to more
efficiently and productively handle the process of sourcing, requisitioning,
ordering, expediting, inspecting and reconciliation of procurement.
6.4.1 Process of Project Procurement Management
Project management for procurement is usually divided into four major
processes:
Planning, Selection, Administering and Closing procurements.
Planning Process:
Planning, involves the creation of the official procurement management
plan.
The decisions involve which items will be internally procured and
which items will be externally outsourced. For every external contractor,
there needs to be a statement of work ( SOW ) to serve as a document
outlining the work being contracted. This information, will heavily impact
the project’s budget and financial scope.
Sample procurement documents will be prepared and criteria
frameworks will be developed to create a selection of potential vendors.
This selection matrix is based on the project’s scope, schedule, and
requirements. Risk factors and budgetary constraints a re also considered.
This process is collected in the procurement management plan,
which includes requirement documents, risk register , activity resource
requirements, project schedule, activity cost estimates and more.
Selection Process:
The selection p rocess involves comparing and contrasting vendors’
advantages, disadvantages, and contractual offerings. Standard tools and
techniques are used to select procurements, such as video conferencesmunotes.in
Page 122
122with bidders that allow them to understand the project require ments and
ask questions.
Procurement contracts are decided and awarded through
collaborations between various managers. Resource calendars are then
created that detail when, where and how resources will be used and
managed. The corresponding project manage ment plan is adjusted
according to resource calendar updates. Proposals are carefully evaluated
and if no satisfactory bids are available, the project management team may
utilize online ads to solicit new bidders.
Administration Process:
The third major s tep is administration, which refers to the tools and
processes used to manage relationships with vendors. The administration
phase results in the continual creation of procurement documents and
spreadsheets that may drive project changes. A centralized sys tem of
contract change monitoring and control will be used to evaluate and
determine whether potential changes to contracts are needed.
Once the contracts are signed, the management of those contractors
must be folded into the overall management responsib ilities. Contractors
can have negative impact on budgets and schedules, which can lead to a
project going off -track or worse.
It’s best to contract a change control system and have regular
procurement performance reviews, including inspections and audits to
make sure the work is going right. Performance reporting helps keep
managers informed, too. A payment system needs to be in place as well as
a claims administration and a records management system.
There are formal physical inspections, internal audits and reviews
of procurement operations in order to generate synthesized performance
reports that provide real -time feedback. The administration process is
extremely important, so it’s usually managed through supply chain or
project management software.
Closing Process:
Just as there is a process to start the procurement, there needs one
in place to finalize it. What constitutes completed work should be detailed
in the initial agreement with the contractor, so there is no confusion of
either’s part as to wh en the work is done.
The closing process isn’t just about ending procurement contracts;
it’s about noting weaknesses, documenting successful processes and
summarizing the project for future needs. Some companies prefer to
conduct simple audits using perfo rmance matrices in order to grade the
overall project.
Documentation is important for future projects, which may involve
entirely different teams in new locations. During the closing process,
negotiations may be necessary to resolve contract disputes. Ide ally,munotes.in
Page 123
123potential issues will be noted during the administration process in order to
begin the mediation process early.
When it comes to project procurement management, there are
standard features and functions. For example, most companies prefer to
use a s maller number of suppliers with long -term relationships instead of
using a group of suppliers to outbid each other for the lowest price.
Establishing and nurturing relationships with suppliers is important
because this enables various supply chain partners and shareholders to
work closely together on improvement and coordination activities.
6.4.2 Eight Steps for a Procurement Management Plan
The project manager is the project team member responsible for
overseeing the procurement management plan, but it’s not a one -person
job. Since the procurements will be project -wide, it’s important that
everyone is on board with the process. Everyone should have some
involvement in approving and even managing contracts.
The procurement management plan can be broken do wn into these eight
steps.
Define Terms: To begin, start by defining the procurement terms.
This means listing what you need to procure in detail: how many, what
size, for how long, etc. Then you want to know what service is provided to
the project and wh y this is important. Now add a date of use to each of
these procurements and who on the project team is authorized to make
these purchases.
Outline Type of Agreement: The contract is how everyone agrees on
theterms of service. There are different types o f contracts, for instance a
fixed price and cost reimbursement are two. Therefore, the type of
agreement must be decided on and how it will be managed.
Identify and Mitigate Risks: Risks are inherent in every part of a
project process, and so they lie dor mant in procurement until they show
themselves.
It is now time to figure out what those risks might be and list them. Once a
thorough list has been collected, each must have a way to resolve them.
It’s also good to assign a team member with the task of mit igating those
risks, so they have ownership to follow through on closing them.
Define Costs: What are the costs involved with the project
procurements?
Once those have been figured out, it is likely that a request for proposal
will be issued, with the ne eds outlined and requesting bids from suppliers.
Be thorough and note everything required. The suppliers will come back
with their cost for products or services.munotes.in
Page 124
124Identify Constraints: It helps to try and identify any project
constraints before starting th e project to avoid getting blindsided by
unforeseen limitations during execution. Once this list is complete it can
be looked at throughout the project phases. Constraints related to
procurements include cost, scope, limited resources and technical
specifi cations.
Get Contract Approved: Review the bids and do a service and cost
analysis. Then have a list of who the decision makers are in the project
group and pass the bids on to them for review. This process makes sure
that everyone who needs to oversee th e contract approval is involved and
can provide input.
Make Decision Criteria: You have a workflow, but now you need
criteria by which to decide on which bid to go into contract with. Every
person who reviews the bid should have these criteria at hand to measure
their response.
Create a Vendor Management Plan: Once a contract is signed, the
procurement management plan will segue into a vendor management plan .
The terms of the contract must be met. And, to make sure that happens, a
management plan surround ing the suppliers will help ensure that goods
and services are delivered as specified and on time. It is a good idea to add
a performance metric to rate how well each supplier does their job, so you
can improve relations on the next project and know who is worth
contracting with again.
5.5 DEGREE OF RIGOR
For a project of a particular kind the degree of rigor with which the
software procedure is applied may vary significantly. The degree of rigor
is function of several project characteristics. For an exam ple non -business,
small, critical projects can commonly be addressed with somewhat less
rigor which is large complex baseline critical applications. It should be
noted however, in which all projects must be conducted in a manner which
results in timely hig h quality deliverables.
6.5.1 Four various degrees of rigor
Four various degrees of rigor can be defined that are:
Casual: In general umbrella tasks will be documentation and
minimized needs will be reduced all basic principles of software
engineering a re yet applicable. All procedural frame work activities are
applied but only a minimum task group is needed.
Structured: Framework related tasks and activities appropriate to the
project type will be applied and umbrella activities necessary to ensure
high quality will be applied. The process framework will be applied formunotes.in
Page 125
125this project. SQA, SCM measurement and documentation tasks will be
conducted in a streamlined manner.
Strict: -The full process will apply for this project with a degree of
discipline which will ensure high quality. Robust documentation will be
produced and all umbrella activities will be applied.
Quick Reaction: Framework of process will be applied for this project
butbecause of an emergency condition only those tasks essential to
maintaining good quality will be applied Back -filling example for
developing a complete set of documentation conducting additional reviews
will be accomplished after the application or product is delivered to the
customer.
The project manager must have to de velop a systematic approach
for selecting the degree of rigor which is appropriate for a special project.
To accomplish this project adaptation criteria are describe and a task set
selector value is computed.
6.5.2 Defining a Task Set for the Software Pro ject
Task set -collection of software engineering work tasks, milestones, and
deliverables that must be accomplished to complete a particular project.
Task sets are designed to accommodate different types of projects and
different degrees of rigor.
determine type of project
assess the degree of rigor required
identify adaptation criteria
Select appropriate software engineering tasks
Five Most software organizations encounter the following projects:
Concept development projects -initiated to explore some new
business concept or application of some new technology.
New application development projects -undertaken as a
consequence of a specific customer request.
Application enhancement projects -occur when existing software
undergoes major modificat ions to function, performance, or interfaces that
are observable by the end -user.
Application maintenance projects -correct, adapt, or extend existing
software in ways that may not be immediately obvious to the end -user.munotes.in
Page 126
126Reengineering projects -underta ken with the intent of rebuilding an
existing (legacy) system in whole or in part.
5.6 CRITICAL PATH METHOD (CPM)
Critical Path Method (CPM) is a project schedule modeling
technique. Mr. Morgan R. Walker and James E. Kelly developed this
technique in the late 1950s.
Project planners use this method to develop schedules for many
kinds of projects including IT, research, and construction.
Critical Path Method is a lengthy and complex concept. Please
follow each step in this blog post and don’t move on unt il you understand
the previous steps. If you follow this advice and complete the blog post,
you won’t have any problems solving the questions on Critical Path
Method.
A network diagram has many paths originating from one point and
ending at another point. Every path has a duration and the one with the
longest duration is the critical path.
You can define a critical path as:
The longest path in the network diagram, or
The shortest duration to complete the project.
6.6.1 Critical Path Method helps in:
Determining the minimum time in which the project can be completed
Determining the sequence of activities which must be completed on
time in order to complete the project in time
Determining which all tasks can be delayed without delaying the
project comp letion time
Determining the Early and Late Start of tasks
Tracking project progress with regards to agreed timeline and taking
proactive corrective action if the project seems to be getting delayed
6.6.2 Technique for CPM
The technique for find out the critical path in your project can be derived
as follows.munotes.in
Page 127
127Break Down the Project: List all the tasks needed to complete the
project. You can use a work breakdown structure, which is a hierarchical
decomposition of the project, which includes every deliver able.
Estimate Task Duration: Now comes the tricky part, you want to know
how long each task will take. If possible, get advice from others who have,
so you can have the most accurate estimation of the duration of the various
tasks possible.
Determine Ta sk Dependencies: If there are any task dependencies, you
want to note them, too. A task dependency is when one task cannot start
until another one has been finished. It’s a key element of good task
management.
Add Milestones: What are the milestones in yo ur project? Having
milestones helps to keep you on track, so you can make sure you’re
meeting your baseline schedule.
When you have this data collected, you’re able to calculate the
longest path your planned tasks will take to reach the end of the project ,a s
well as the earliest and latest that each task can start and finish without
impacting the project schedule.
6.6.3 Steps for CPM
The typical steps involved to develop a project schedule using CPM
method are as below:
Identify the activities for all the work packages from the project’s
Work
Breakdown Structure (WBS)
Sequence all the activities by identifying all the dependencies between
the activities.
Develop a Schedule Network Diagram involving all the project
activities ensuring that each activi ty has at least one predecessor and one
successor except the first activity which will not have a predecessor and
last activity which will not have a successor.
Estimating the duration of each activity in the schedule network
diagram.
Carrying out the pr ocess of “Forward Pass” where in the “Early Start”
(ES) and “Early Finish” (EF) for each activity are calculated starting from
the beginning of the network diagram.munotes.in
Page 128
128
Carrying out the process of “Backward Pass” where in the “Late
Finish” (LF) and “Late Star t” (LS) for each activity are calculated starting
from the end (Finish) of the network diagram.
Identifying the “Path” which has the longest duration in the Network
Diagram. The longest path will also have the ES and LS and EF and LF of
all the activities as same.
The longest path is termed as the “Critical Path”. The duration of this
path will determine the shortest time taken to complete the project. Any
delay on this path delays the project completion time. Hence they are
critical from project’s schedu le constraint point of view.
The “Non -Critical -Path” path duration will be shorter than the
“Critical Path” and hence those paths will have flexibility to delay the start
of the tasks on them.
The amount of time a task can be delayed on a “non -critical p ath” is
known as “float” or “slack”, which is calculated by taking the difference
between
“LS-ES” or “LF -EF”.
The float on critical path will be Zero to start with and not -critical
paths will have a positive float time.
There may be more than one critic al path in a network. But having
more than one critical path increases the risk of falling behind the schedule
as there are more number of tasks which if they get delayed, the project
will get delayed.
6.6.4 Examples
An example of Critical Path analysis is as below (Figure 6.1).
Figure 6.1: Critical Path analysismunotes.in
Page 129
129
In the above diagram, the path with longest duration is Start -D-E-
F-G-End is the critical path with duration of 17. The other 2 non -critical
paths Start -A-B-C-G-End has duratio n of 10 and hence has a slack or float
of 7 and other non -critical path Start -D-H-I-End has a duration of 11 and
has a float of 6 days.
Critical Path once identified, the team can further explore if the
duration of critical path can be compressed if the n eed be. Techniques
such as crashing (applying more resources on critical path) or Fast
Tracking (doing tasks in parallel) are applied. Compressing the critical
path helps in compressing the overall project duration, thereby helping to
meet the required dea dline.
Based on the network diagram below (Figure 6.2), identify the total
paths, critical path, and float for each path.
Figure 6.2: Total Paths
The above network diagram has five paths. The paths and their durations
are as follows:
Start->A->B->C-> End {duration: 31 days.}
Start ->D->E->F-> End {duration: 18 days.}
Start ->D->B->C-> End {duration: 26 days.}
Start ->G->H->I-> End {duration: 13 days.}
Start ->G->E->F-> End {duration: 16 days.}
Since the dura tion of the first path is the longest, it is the critical
path. The float on the critical path is zero.munotes.in
Page 130
130
The float for the second path “Start ->D->E ->F-> End” =
duration of the critical path –duration of the path “Start ->D->E->F->
End” = 31 –18= 13
Hence, the float for the second path is 13 days.
Using the same process, we can calculate the float for other paths as well.
Float for the third path = 31 –26 = 5 days.
Float for the fourth path = 31 –13 = 18 days.
Float for the fifth path = 31 –16 = 15 days.
Calculate Early Start, Early Finish, Late Start, and Late Finish
We have identified the critical path and the duration of the other
paths. Now it’s time to move on to more advanced calculations: Early
Start, Early Finish, Late Start and L ate Finish.
Calculating Early Start (ES) and Early Finish (EF)
To calculate the Early Start and Early Finish dates, we use the
forward pass; we will start from the beginning and proceed to the end.
The Early Start (ES) for the first activity on any path will be 1
because you cannot start an activity before the first day of your project.
The starting point for any activity is the endpoint of the
predecessor activity on the same path (plus one).
The formula used for calculating Early Start and Early Fini sh dates:
Early Start of the activity = Early Finish of predecessor activity + 1
Early Finish of the activity = Activity duration + Early Start of activity
–1
Early Start and Early Finish Dates for the path Start ->A->B->C->
End (Figure 6.3)
Figure 6.3:munotes.in
Page 131
131
Early Start of activity A = 1 (Since this is the first activity of the path)
Early Finish of activity A = ES of activity A + activity duration –1= 1 +
10–1 = 10 Early Start of activity B = EF of predecessor activity + 1= 10
+1 = 11
Early Finish of activity B = ES of activity B + activity duration –1= 11 +
12–1 = 22 Early Start of activity C = EF of predecessor activity + 1= 22
+1 = 23
Early Finish of activity C = ES of activity C + activity duration –1= 23 +
9–1 = 31
Early Start and Early Finish Dates for the path Start ->D->E->F->
End (Figure 64)
Figure 6.4:
Early Start of activity D = 1 (Since this is the first activity of the path)
Early Finish of activity D = 1 + 5 –1=5
Early St art of activity E = EF of predecessor activity + 1
Since activity E has two predecessor activities, which one will you
select? The answer is the activity with the greater Early Finish date. The
Early Finish of activity D is 5, and the Early Finish of acti vity G is 3 (we
will calculate it later).munotes.in
Page 132
132Therefore, we will select the Early Finish of activity D to find the Early
Start of activity E.
Early Start of activity E = EF of predecessor activity + 1= 5 + 1 = 6
Early Finish of activity E = 6 + 7 –1 = 12
Early Start of activity F = 12 + 1 = 13
Early Finish of activity F = 13 + 6 -1 = 18
Early Start and Early Finish Dates for the path Start ->G->H ->I->
End (Figure 6.5)
Figure 6.5
Early Start of activity G = 1 (Sinc e this is the first activity of the path)
Early Finish of activity G = 1 + 3 –1=3
Early Start of activity H = 3 + 1 = 4
Early Finish of activity H = 4 + 4 –1=7
Early Start of activity I = 7 +1 = 8
Early Finish of activity I = 8 + 6 –1 = 13
Calculating Late Start (LS) and Late Finish (LF) We have calculated the
Early Start and Early Finish dates of all activities. Now it is time to
calculate the Late Start and Late Finish dates.
The Late Finish date of the last activity on all paths will be the
same because no activities can continue once the project is completed.
munotes.in
Page 133
133
The formula used for Late Start and Late Finish dates:
Late Start of Activity = Late Finish of activity –activity duration + 1
Late Finish of Activity = Late Start of successor act ivity –1
To calculate the Late Start and Late Finish, we use the backward pass; i.e.
we will start from the last activity and move back towards the first
activity.
Late Start and Late Finish Dates for the path Start ->A->B->C->
End (Figure 6.6)
Figure 6.6:
On a critical path, the Late Start, and Late Finish dates will be the same as
the Early Start and Early Finish dates
Late Start and Late Finish Dates for the path Start ->D ->E->F->
End (Figure 6.7)
Figure 6.7:
Late Finish of activity F = 31 (because you cannot allow any activity to
pass the project completion date)munotes.in
Page 134
134
Late Start of activity F = LF of activity F –activity duration + 1= 31 –6
+1 = 26
Late Finish of Activity E = LS of successor activit y–1= LS of Activity F
–1= 26 –1 = 25
Late Start of Activity E = LF of activity E –activity duration + 1= 25 –7
+ 1 = 19
Late Finish of activity D = LS of successor activity –1
If you look at the network diagram, you will notice that activity D has two
successor activities, B and E. So, which activity would you select?
You will select the activity with the earlier (least) Late Start date. Here,
the Late Start of activity B is 11, and the Late Start of activity E is 19.
Therefore, you will select a ctivity B, which has the earlier Late Start date.
Hence,
Late Finish of activity D = LS of activity B –1= 11 –1 = 10
Late Start of Activity D = LF of activity D –activity duration + 1= 10 –5
+1=6
Late Start and Late Finish Dates for the path Star t->G ->H ->I->
End (Figure 6.8)
Figure 6.8:
Late Finish of activity I = 31 (because you cannot allow any activity to
pass the project completion date)
Late Start of activity I = 31 –6 + 1 = 26
Late Finish of activity H = 26 –1=2 5munotes.in
Page 135
135Late Start of activity H = 25 –4 + 1 = 22
Late Finish of Activity G = 19 –1= 18 (we will choose the late start of
activity E, not activity H because the Late Start of activity E is earlier than
the Late Start of activity H).
Late Start of activity G = 18 –3 + 1= 16
6.7 SUMMARY
This Chapter includes scheduling principals and relationship
between people and efforts. It describes tracking of project schedule with
earned value analysis. This chapter covered the process of procurement
management with s ome plans. After this various Degree of rigor are listed.
The main part of critical path method is explained step by step with
numerical.
6.8 QUESTIONS
Explain Project scheduling with the relationship between people and
efforts?
State the Project Effort Distribution
Describe the Tracking Project Schedules
Explain the process of project procurement Management
What is degree of rigor?
State the Technique for CPM with example.
6.9 REFERENCE BOOKS
Information Technology Project Management by Jack T Ma rchewka
Wiley
India publication
Software Engineering, by Roger S Pressman, McGraw Hill
publication.
Software Engineering by KK Agarwal , Yogesh Singh , New Age
International publication.
munotes.in
Page 136
136Module VI
7
SOFTWARE AND SYSTEM QUALITY
MANAGEMENT
Unit Structure
7.1 Introduction
7.2 Overview of ISO 9001
7.3 SEI Capability Maturity Model
7.4 McCalls Quality Model
7.5 Six Sigma
7.6 Formal Technical Reviews
7.7 Tools and Techniques for Quality Control
7.8 Pareto Analysis
7.9 Statistical Sampling
7.10 Quality Control Charts
7.11 The Seven Run Rule
7.1 INTRODUCTION
Definition by ISTQB,
Quality : The degree to which a component, system or process meets
specified requirements and/or user/custome r needs and expectations.
software quality: The totality of functionality and features of a software
product that bear on its ability to satisfy stated or implied needs.
Software quality management (SQM) is a management process that
aims to develop and manage the quality of software in such a way so as
the best ensure the product meets the quality standards expected by the
customer while also meeting any necessary regulatory and developer
requirements, if any.
7.2 OVERVIEW OF ISO 9001
●ISO 9000 -3, the G uidelines offered by the International Organization
for Standardization (ISO), represent implementation of the general
methodology of quality management ISO 9000 Standards to the
special case of software development and maintenance.munotes.in
Page 137
137●Both ISO 9001 and ISO 9000 -3 are reviewed and updated once every
5–8 years, with each treated separately.
●As ISO 9000 -3 adaptations are based on those introduced to ISO 9001,
publication of the revised Guidelines follows publication of the revised
Standard by a few years.
●Atthe time of writing, the 2000 edition of ISO 9001 (ISO, 2000a) has
been issued, but only the final just -completed draft of ISO 9000 -3
(ISO/IEC, 2001) is awaiting approval.
●From the 1997 edition on, the ISO 9000 -3 will represent the stand -
alone ISO standar d for the software industry.
●The 2000 edition of ISO 9001 as well as the new edition of ISO 9000 -
3 are supported by two additional conceptual standards:
1.ISO 9000 (ISO, 2000b), which deals with fundamental concepts and
terminology, and
2.ISO 9004 (ISO, 200 0c), which provides guidelines for performance
improvement.
ISO 9001 —application to software: the TickIT initiative :
TickIT was launched in the late 1980s by the UK software industry
in cooperation with the UK Department for Trade and Industry to pro mote
development of a methodology for adapting ISO 9001 to the
characteristics of the software industry known as the TickIT initiative.
TickIT is currently authorized to accredit other organizations as
certification bodies for the software industry in the UK.
TickIT activities include:
■Publication of the TickIT Guide, that supports the software industry’s
efforts to spread ISO 9001 certification. The current guide (edition 5.0,
TickIT, 2001), which includes references to ISO/IEC 12207 and
ISO/IEC 15504, is distributed to all TickIT cus tomers.
■Performance of audit -based assessments of software quality systems and
consultation to organizations on improvement of software
development and maintenance processes in addition to their
management.
■Conduct of ISO 9000 certification audits.munotes.in
Page 138
138
7.3 SEI CAPABILITY MATURITY MODEL
Carnegie Mellon University’s Software Engineering Institute (SEI)
took the initial steps toward development of what is termed a capability
maturity model (CMM) in 1986.
The initial version of the CMM was released in 1 992, mainly for
receipt of feedback from the software community.
The first version for public use was released in 1993 (Paulk et al.,
1993, 1995; Felschow, 1999).munotes.in
Page 139
139The principles of CMM
Following are the concepts and principles of CMM assessment:
●Application of more elaborate management methods based on
quantitative approaches increases the organization’s capability to
control the quality and improve the productivity of the software
development process.
●The vehicle for enhancement of software develop ment is composed of
the five -level capability maturity model. The model enables an
organization to evaluate its achievements and determine the efforts
needed to reach the next capability level by locating the process areas
requiring improvement.
●Process a reas are generic; they define the “what”, not the “how”. This
approach enables the model to be applied to a wide range of
implementation organizations because:
➔It allows use of any life cycle model
➔It allows use of any design methodology, software develo pment tool
and programming language
➔It does not specify any particular documentation standard.
The CMM and its key process areas (KPAs) are presented in
following Figure
munotes.in
Page 140
140Variety of specialized capability maturity models are as following:
●System Eng ineering CMM (SE -CMM)
➔It focuses on system engineering practices related to product -oriented
customer requirements.
➔It deals with product development: analysis of requirements, design of
product systems, management and coordination of the product systems
and their integration.
➔In addition, it deals with the production of the developed product:
planning production lines and their operation.
●Trusted CMM (T -CMM)
It was developed to serve sensitive and classified software systems
that require enhanced so ftware quality assurance.
●System Security Engineering CMM (SSE -CMM)
It focuses on security aspects of software engineering and deals with
secured product development processes, including security of
development team members.
●People CMM (P -CMM)
It d eals with human resource development in software
organizations: improvement of professional capacities, motivation,
organizational structure, etc.
●Software Acquisition CMM (SA -CMM)
It focuses on special aspects of software acquisition by treating
issue s–contract tracking, acquisition risk management, quantitative
acquisition management, contract performance management, etc. –that
touch on software purchased from external organizations.
●Integrated Product Development CMM (IPD -CMM)
It serves as a f ramework for integration of development efforts
related to every aspect of the product throughout the product life cycle as
invested by each department.
7.4 MCCALLS QUALITY MODEL
The classic model of software quality factors, suggested by
McCall, consis ts of 11 factors (McCall et al., 1977). The McCall factor
model provides a practical, up -to-date method for classifying software
requirements (Pressman, 2000).munotes.in
Page 141
141McCall’s Factor Model
The 11 factors are grouped into three categories –product
operation, pr oduct revision, and product transition factors.
●Product operation factors −
Product operation category includes five software quality factors,
which deal with the requirements that directly affect the daily operation of
the software. They are as follows −Correctness, Reliability, Efficiency,
Integrity , Usability.
●Product revision factors −
According to McCall’s model, three software quality factors are
included in the product revision category. These factors are as follows −
Maintainability, Flexibility, Testability.
●Product transition factors −
According to McCall’s model, three software quality factors are
included in the product transition category that deals with the adaptation
of software to other environments and its interaction with other software
systems. These factors are as follows −Porta bility, Reusability,
Interoperability.
1 Correctness:
These requirements deal with the correctness of the output of the
software system. They include −
●Output mission
●The required accuracy of output that can be negatively
affected by inaccurate data or ina ccurate calculations.
●The completeness of the output information, which can be
affected by incomplete data.
●The up -to-dateness of the information defined as the time
between the event and the response by the software system.
●The availability of the informa tion.
●The standards for coding and documenting the software
system.
2 Reliability:
Reliability requirements deal with service failure. They determine
the maximum allowed failure rate of the software system, and can
refer to the entire system or to one or more of its separate
functions.
3 Efficiency:
It deals with the hardware resources needed to perform the
different functions of the software system. It includes processing
capabilities (given in MHz), its storage capacity (given in MB or
GB) and the data communication capability (given in MBPS or
GBPS).munotes.in
Page 142
142It also deals with the time between recharging of the system’s
portable units, such as, information system units located in
portable computers, or meteorological units placed outdoors.
4 Integrity:
This f actor deals with the software system security, that is, to
prevent access to unauthorized persons, also to distinguish
between the group of people to be given read as well as write
permit.
5 Usability:
Usability requirements deal with the staff resources needed to train
a new employee and to operate the software system.
6 Maintainability:
This factor considers the efforts that will be needed by users and
maintenance personnel to identify the reasons for software failures,
to correct the failures, and to v erify the success of the corrections.
7Flexibility:
This factor deals with the capabilities and efforts required to
support adaptive maintenance activities of the software.
These include adapting the current software to additional
circumstances and cust omers without changing the software.
This factor’s requirements also support perfective maintenance
activities, such as changes and additions to the software in order to
improve its service and to adapt it to changes in the firm’s
technical or commercial environment.
8 Testability:
Testability requirements deal with the testing of the software
system as well as with its operation.
It includes predefined intermediate results, log files, and also the
automatic diagnostics performed by the software system p rior to
starting the system, to find out whether all components of the
system are in working order and to obtain a report about the
detected faults.
Another type of these requirements deals with automatic
diagnostic checks applied by the maintenance techn icians to detect
the causes of software failures.
9 Portability:
Portability requirements tend to the adaptation of a software
system to other environments consisting of different hardware,
different operating systems, and so forth.
The software should b e possible to continue using the same basic
software in diverse situations.munotes.in
Page 143
14310 Reusability:
This factor deals with the use of software modules originally
designed for one project in a new software project currently being
developed.
They may also enable f uture projects to make use of a given
module or a group of modules of the currently developed software.
The reuse of software is expected to save development resources,
shorten the development period, and provide higher quality
modules.
11 Interoperabili ty:
Interoperability requirements focus on creating interfaces with
other software systems or with other equipment firmware.
For example, the firmware of the production machinery and testing
equipment interfaces with the production control software.
7.5SIX SIGMA
●The process of producing high and improved quality output is known
as Six Sigma.
●This can be done in two phases –identification and elimination.
●The cause of defects is identified and appropriate elimination is done
which reduces variation in whole processes.
●Six Sigma's aim is to eliminate waste and inefficiency and increase
customer satisfaction by delivering what the customer is expecting.
●It follows a structured methodology, and has defined roles for the
participants.
●It is a data driven methodology, and requires accurate data collection
for the processes being analyzed.
●It is about putting results on Financial Statements.
Following are few characteristics of Six Sigma:
The Characteristics of Six Sigma are as follows:
➔Statistical Quality Control:
Six Sigma denotes Standard Deviation in statistics. Standard
Deviation is used for measuring the quality of output.
➔Methodical Approach:
The Six Sigma is a systematic approach of application in
DMAIC(Design -Measure -Analyze -Improve -Control) and DMADV
(Design -Measure -Analyze -Design -Verify) which can be used to improve
the quality of production.munotes.in
Page 144
144➔Fact and Data -Based Approach:
The statistical and methodical method shows the scientific basis of
the technique.
➔Project and Objective -Based Focus:
The Six Sigma process is implemented to focus on the
requirements and conditions.
➔Customer Focus:
The customer focus is fundamental to the Six Sigma approach. The
quality improvement and control standards are based on specific customer
requirements.
➔Team work Approach to Quality Management:
The Six Sigma process requires organizations to get organized for
improving quality.
7.6 FORMAL TECHNICAL REVIEWS
“A formal review produces a report that identifies the material, the
reviewers, and the revi ew team’s judgment as to whether the product is
acceptable. The principal deliverable is a summary of the defects found
and the issues raised. The members of a formal review team share
responsibility for the quality of the review , although authors are
ultimately responsible for the quality of the products they create
(Freedman and Weinberg 1990).”
●The purpose of an Formal Technical Review (FTR) is to identify
errors in function,logic and implementation of software.
●It is used to verify that the software under review meets its
requirements.
●It ensures that the software has been represented according to
predefined standards.
●It also helps to achieve software that is developed in a uniform manner
and to make projects more manageable.
The FTR is actually a class of reviews that includes walkthroughs
and inspections.
●Areview is ‘a process or meeting during which a software
product is presented to project personnel, managers, users, customers,
user representatives, or other interested parties for comment or a pproval’
●Aninspection is ‘a visual examination of a software product to
detect and identify software anomalies, including errors and deviations
from standards and specifications ’
●Awalkthrough is ‘a static analysis technique in which a designer
or progr ammer leads members of the development team and othermunotes.in
Page 145
145interested parties through a software product, and the participants ask
questions and make comments about possible errors, violation of
development standards, and other problems’
Characteristics of FTR are:
●Well-defined process: Phases (orientation, etc.) Procedures
(checklists, etc.)
●Well-defined roles: Moderator, Reviewer, Scribe, Author, etc.
●Well-defined objectives: Defect removal, requirements elicitation,
etc.
●Well-defined measurements: Forms, co nsistent data collection, etc.
7.7 TOOLS AND TECHNIQUES FOR QUALITY
CONTROL
●The control quality process is defined as the “process of monitoring
and recording the results of executing the quality activities to assess
performance and recommend necessary c hanges.”
●In other words, quality control focuses on project results ensuring that
they comply with the quality standards defined for the project and
eliminating any causes of unsatisfactory performance.
●This process measures the details of the product re sults, such as
deliverables or defects, and also of the project management results,
such as schedule.
●Many of the techniques under the control quality process assume a
working knowledge of statistical quality control, in particular the
concepts of samplin g and probability.
●The distinctions between attribute and variable sampling, precision
and accuracy, and tolerance and control limits are fundamental
components of a working knowledge of statistical quality control:
Prevention aids in identifying and a voiding potential problems so that
they never enter or impact the process.
Inspection helps to identify and eliminate or correct errors so that they are
not delivered to the customer.
Tolerance is a range of acceptable performance or results.
There are seven basic quality tools identified as appropriate for use
in both the quality management plan and control quality processes. They
are known as Ishikawa’s seven basic tools of quality:
1. cause -and-effect diagrams,
2. flowcharting,
3. check sheets,
4. Pareto dia grams,
5. control charts,munotes.in
Page 146
1466. histograms and
7. scatter diagrams.
Ishikawa’s seven basic tools are also referred to as the 7QC tools.
Cause and Effect Diagrams
➔Cause -and-effect diagrams, or Ishikawa diagrams, were developed by
Kaoru Ishikawa to illustrate and help determine how various factors
relate to potential problems.
➔Also called fishbone diagrams because they resemble the skeleton of a
fish.
➔The head of the fish is the effect and each bone of the fish is a cause
that leads to that effect.
➔The bones ca n branch off into smaller bones as you determine the
lowerlevel cause -effect relationships.
➔When all the bones are filled in, the diagram lets you look at all the
possible causes (individual or combinations) of the effect (or problem)
so that you can deve lop a solution to mitigate that effect.
➔The diagram allows organized thought and encourages orderly
consideration of the factors that result in a certain outcome.
Flowcharts
➔Flowcharts show the logical steps in a process and how various
elements within a system are related.
➔They can be used to determine and analyze potential problems in
quality planning and quality control.
➔Flowchart outlines the logical steps to complete a process.
➔By documenting these logical steps, the team can identify where
quality problems might occur and then develop approaches to
proactively manage them.
➔Flowcharting also helps create a process that is repeatable.munotes.in
Page 147
147
Check Sheets
➔Check sheets are used to organize information in order to facilitate
data gathering.
➔Check shee ts are particularly effective for doing inspections, enabling
focus on the particular attributes that may be contributing to potential
or identified quality problems.munotes.in
Page 148
148
Pareto Diagrams
➔A Pareto chart or diagram, is a specific type of histogram that is b ased
on Pareto’s principle, which states that a large number of defects or
problems are caused by a small number of causes.
➔Pareto’s principle, frequently referred to as the 80/20 rule or 80/20
principle.
➔Which means that eighty percent of the cost of def ects are caused by
twenty percent of the problems.
➔A Pareto diagram is an ordered bar graph showing the number of
defects and their causes ranked by frequency.
➔The bars on the diagram graphically show the number and percentage
of causes individually and the line shows the cumulative value.
➔Pareto charts help focus attention on the most critical issues to get the
most benefit.
munotes.in
Page 149
149Histograms
➔A histogram is a vertical bar graph that represents the frequency of
each measured category (known as bins) of vari able.
➔The histogram is particularly useful for identifying common causes.
➔The histogram can be ordered, similar to a Pareto chart, or unordered.
Control Charts
➔Control charts are used to determine if processes are in or out of
statistical control. Most processes experience a degree of normal
variation i.e. most processes do not achieve target performance all the
time.
➔Control charts provide a mechanism for establishing a statistically
objective range of acceptable variation around the target perfo rmance,
thereby enabling attention to be focused on special cause variations
(those that fall outside of the established performance limits).
➔Control chart limits are established on the basis of standard deviations
from the mean (target) performance. The upper control limit (UCL)
and lower control limit (LCL) are established so that 99.73 percent
(three standard deviations above and below the mean) of the measured
data points fall within the range.
➔The following ones are more common:
❏Rule of Seven, or S even Run Rule: Seven data points in a row are
above or below the mean.
❏Trend of Seven Rule: Seven data points in a row follow a trend up or
down.
❏Rule of One: Any single data point is outside of the control limits
(upper or lower).munotes.in
Page 150
150
Scatter Diagrams
➔Scatter diagrams plot two variables, the independent variable and the
dependent variable, to graphically show the relationship between them.
➔The X -axis in the diagram represents one characteristic (usually the
independent variable), and the Y -axis measu res the other.
➔To interpret the diagram, look at two characteristics of the clustering:
❏Tightness: The closer the cluster is to a diagonal line drawn through
the graph, the more the two variables are likely to be linearly
correlated. High correlation b etween the characteristics means that a
change in one characteristic will be accompanied by a change in the
other.
❏Direction: If the correlation is positive, then as one variable increases
so does the other, and the line will have a positive slope (from lower
left to upper right). On the other hand, if the correlation is negative, it
implies that as one characteristic increases, the other decreases, and the
line will have a negative slope (from lower right to upper left).munotes.in
Page 151
151
7.8 ANSWER THE FOLLOWING :
1. Explain the benefits of the use of SQA standards.
❏The ability to make use of the most sophisticated and comprehensive
professional methodologies and procedures
❏Better understanding and cooperation between users of the same
standards:
–Between team me mbers and between project teams
–Between software developers and external participants in the
project
–Between suppliers and customers.
2. Describe the contributions made by the use of standards.
❏Provision of superior professional methodologies for use in the
development process and for its management
❏Provision of SQA certification services based on independent
professional quality audits
❏Provision of tools for “self -assessment” of achievements in planning
and operating an organization’s SQA system.
3. Describe the general principles underlying quality management
according to ISO 9000 -3.
❏Customer focus –understanding a customer’s current and future needs
❏Leadership exercised in the creation and maintenance of a positive
internal environment in or der to achieve the organization’s objectivesmunotes.in
Page 152
152❏Involvement of people at all levels to further organizational goals
❏Process approach –activities and related resources perceived and
managed as a process
❏Systems approach to management –managing processes a s a system
❏Continual improvement of the organization’s overall performance
❏Factual approach to decision -making –decisions based on the analysis
of data and information
❏Mutually beneficial supplier relationships –emphasis on coordination
and cooperatio n
4. Describe the principles embodied in the Capability Maturity Model
(CMM).
❏Application of more highly elaborated software quality management
methods increases the organization’s capability to control quality and
improve software process productivity
❏Application of the five levels of the CMM enables the organization to
evaluate its achievements and determine what additional efforts are
needed to reach the next capability level
❏Process areas are generic, with the model defining “what” and leaving
the“how” to the implementing organizations, i.e., the choice of life
cycle model, design methodology, software development tool,
programming language and documentation standard.
munotes.in
Page 153
1538
SOFTWARE RISK MANAGEMENT
Unit Structure
8.0 Objective
8.1 Introduction
8.2 Risk Analysis And Management
8.2.1 Steps of Risk Analysis and Management
8.3 Types OfIT Project Risk
8.4 Reactive Vs Proactive Risk Strategies
8.4.1 Rea ctive risk strategies
8.4.2 Proactive risk strategies
8.5 Risk Identification
8.5.1 Assessing Overall Project Risk
8.5.2 Risk Components and Drivers
8.6 Risk Projection
8.6.1 Developing a Risk Table
8.7 Risk Assessment
8.8 Risk Mitigation, Monitoring, An d Management
8.9 The RMMM Plan
8.10 Summary
8.0 OBJECTIVES
Define risk identification and causes , effects , and nature off project
risks.
Apply several analysis techniques that can be used to prioritize and
analyze various project risks.
Describe the various risk strategies
Describe the risk monitoring and control
Describe risk evaluation in terms of how the entire risk management
process should be evaluated in order to identify best practices.
8.1INTRODUCTION
Project risk management provides an ear ly warning system for
problems that need to be addressed or resolved .Although risk has a
certain negative connotation , project stakeholders should be vigilant in
identifying opportunities. Although many associate uncertainty withmunotes.in
Page 154
154threats, it is important to keep in mind that there is uncertainty when
pursuing opportunities, as well.
Plan risk management determines how to approach and plan the
project risk management activities. an output of this process is the
development of arisk management plan.
Deciding which risks impact the project. Risk identification
generally includes many of the project stakeholders and requires an
understanding of the project’s goal , as well as the project’s scope
,schedule, budget , and quality objectives.
Developing proced ures and techniques to reduce the threats of
risks, while enhancing the likelihood of opportunities.
8.2 RISK ANALYSIS AND MANAGEMENT
Risk analysis and management are series of steps that help a
software team to understand and mange uncertainty.
Many pr oblems can plague a software project .A risk is a potential
problem –it might happen it might not.
8.2.1 Steps of Risk Analysis and Management
1.Recognizing what can go wrong is the first step , called “risk
identification.”
2.Each risk is analyzed to determ ine the likelihood that it will occur and
the damage that it will do if it does occur.
3.Risks are ranked, by probability and impact.
4.Finally, a plan is developed to manage those risks with high
probability and high impact.
In short, the four steps are
Risk Identification
Risk Projection
Risk Assessment
Risk Management
Risk always involves two characteristics a set of risk information
sheets is produced.
Uncertainty -the risk may or may not happen; that is, there are no
100 % probable risks.
Loss –if the risk becomes a reality, unwanted consequences or losses
will occur.munotes.in
Page 155
1558.3 TYPES OF IT PROJECT RISK
What types of risks are we likely to encounter as the software
is built??
Project risks threaten the project plan. That is, if project risks become
real, it is likely that project schedule will slip and that costs will
increase. Project risks identify potential budgetary, schedule, personnel
(staffing and organization), resource, customer, and requirements
problems and their impact on a software project .
Technical risks threaten the quality and timeliness of the software to
be produced. If a technical risk becomes a reality, implementation may
become difficult or impossible.
Business risks –threaten the viability of the software to be built.
Business ris ks often jeopardize the project or the product. Candidate
for top five business risks are
Market risk
Strategic risk
Management risk and
Budget risk
Known risks are those that can be uncovered after careful evaluation
of the project plan.
Predictable ri sksare extrapolated from past project experience (e.g.,
staffturnover, poor communication with customer, dilution of staff
effort as ongoing maintenance requests are serviced).
Unpredictable risks –are the joker in the deck. They can do occur,
but they are extremely difficult to identify in advance.
8.4 REACTIVE VS PROACTIVE RISK STRATEGIES
8.4.1 Reactive risk strategies
1.Reactive risk strategies follows that the risks have to be tackled at the
time of their occurrence.
2.No precautions are to be taken a s per this strategy.
3.They are meant for risks with relatively smaller impact.
8.4.2 Proactive risk strategies
1.Proactive risk strategies follows that the risks have to be identified
before start of the project.
2.They have to be analyzed by assessing their p robability of occurrence
,their impact after occurrence , steps to be followed for its precaution.
3.They are meant for risks with relatively higher impact .munotes.in
Page 156
1568.5 RISK IDENTIFICATION
Risk identification is asystematicattemptto the project plan (estimates,
schedule, resource loading, etc.) .By identifying known and predictable
risks, the project manager takes a first step toward avoiding them when
possible and controlling them when necessary.
One method for identifying risks is to create a risk item checkl ist.
The checklistcan be used for risk identification and focuses on some
subset of known and predictable risks a in the following generic
categories:
Product size –risks associated with overall size of the software to be
built or modified.
Business impa ct–risks associated with constraints imposed by
management or the marketplace.
Customer characteristics –risks associated with sophistication of the
customer and developer’s ability to communicate with the customer in
a timely manner.
Process definition -risks associated with the degree to which the
software process has been defined and is followed by the development
organization.
Development environment –risks associated with the availability and
quality of the tools to be used to build the product.
Technology to be built –risks associated with the complexity of the
system to be built and the “newness” of the technology that is
packaged by the system.
Staff size and experience -risks associated with the overall technical
and project experience of the s oftware engineers who will do the work.
8.5.1 Assessing Overall Project Risk
Is the software project we are working on at serious risk?
The questions are ordered by their relative importance to success
of a project.
1.Have top software and customer manager s formally committed to
support the project?
2.Are end –users enthusiastically committed to the project and the
system/product to be built?
3.Are requirements fully understood by the software engineering team
and their customers?
4.Have customers been involved f ully in the definition of requirements?
5.Do end –users have realistic expectations?
6.Is the project scope stable?
7.Does the software engineering team have the right mix of skills?
8.Are project requirements stable?munotes.in
Page 157
1579.Does the project team have experience with t he technology to be
implemented?
10.Is the number of people on the project team adequate to do the job?
11.Do all customer/ user constituencies agree on the importance of the
project and on the requirements for the system/ product to be built?
If any one of the se questions is answered negatively, mitigation,
monitoring, and management steps should be instituted without fail.
2.5.2 Risk Components and Drivers
The risk components are defined in the following manner:
Performance risk -the degree of uncertainty th at the product will
meet its requirements and fit for its intended use.
Cost risk -the degree of uncertainty that the project budget will be
maintained.
Support risk –the degree of uncertainty that the resultant software
will be easy to correct, adapt, a nd enhance.
Schedule risk -the degree of uncertainty that the project schedule will
be maintained and that the product will be delivered on time.
The impact of each risk driver on the risk component is divided into
one of four impact categories –negligib le, marginal, critical, or
catastrophic.
Components
CategoryPerformance Support Cost Schedule
1Failure to meet the
requirement would result in
mission failureFailure results in increased
costs and schedule delays
with expected valu es in
excess of $ 500KCatastrophic
2Significant
degradation
to non -
achievement
of technical
performanceNonresponsive
or
unsupportable
softwareSignificant
financial
shortage
budget
overrun
likelyUnachievable
IOC
1Failure to meet the
requirement would degrade
system performance to a point
where mission success is
questionable.Failure results in
operational delays and /or
increased costs with
expected value of $ 100K
to $500KCritical
2Some
reduction in
technical
performanceMinor delays in
software
modific ationsSome
shortage
of
financial
resources
,possible
overrunsPossible
slippage in
IOCmunotes.in
Page 158
1581Failure to meet the
requirement would result in
degradation of secondary
mission.Costs, impacts, and /or
recoverable schedule slips
with expected value of
$1K to $100KMarginal
2Minimal to
small
reduction in
technical
performanceResponsive
software
supportSufficient
financial
resourcesRealistic
achievable
schedule
1Failure to meet the
requirement would create
inconvenience or non -
operational impactError results in minor cost
and/ or schedule impact
with expected value of
less than $ 1KNegligible
2No
reduction in
technical
performanceEasily
supportable
softwarePossible
budget
under runEarly
achievable
IOC
1)The potential consequence of undetected softwa re errors or faults.
2)The potential consequence if the desired outcome is not achieved.
8.6 RISK PROJECTION
Risk projection , also called risk estimation, attempts to rate each
risk in two ways –the likelihood or probability that the risk is real and th e
consequences of the problems associated with the risk , should it occur.
The project planner, along with other managers and technical staff ,
performs four risk projection activities.
1.Establishing a scale that reflects the perceived likelihood of a risk.
2.Delineating the consequences of the risk.
3.Estimating the impact of the risk of the project and the product.
4.Noting the overall accuracy of the risk projection so that there will be
no misunderstandings.
8.6.1 Developing a Risk Table
Risks Category Probability Impact RMMM
Size estimate may be
significantly lowPS 60% 2
Larger number of users
than plannedPS 30% 3
Less reuse the planned PS 70% 2
End–users resist system BU 40% 3
Delivery deadline will
be tightenedBU 50% 2munotes.in
Page 159
159Funding will be lost CU 40% 1
Customer will change
requirementsPS 80% 2
Technology will not meet
expectationsTE 30% 1
Lack of training on tools DE 80% 3
Staff inexperienced ST 30% 2
Staff turnover will be
highST 60% 2
I.Arisk table provides a project manager with a simple technique for
risk projection.
II.A sample risk table is illustrated in Figure. The risk table is sorted
by probability and impact to rank risks.
III.A project team begins by listing all risks in the first colu mn of the
table. This can be accomplished with the help of risk item
checklists referenced. Each risk is categorized in the second
column (e.g. PS implies a project size risk, BU implies business
risk).
IV.The probability of occurrence of each risk is entered in the next
column of the table. The probability value for each risk can be
estimated by team members individually. Individual team
members are polled in round –robin fashion until their assessment
of risk probability begins to converge.
V.Next, the impact of each risk is assessed.
VI.The categories for each of four risk components –performance,
support, cost, and schedule -are averaged to determine an overall
impact value.
VII.Once the first four columns of the risk table have been completed ,
the table is sorted by probability and by impact. High –probability,
high –impact risks percolate to the top of the table, and low –
probability risks drops drop to bottom.
VIII.This accomplishes first -order risk prioritization. The project
manager studies the resultant sorted ta ble and defines a cutoff line.
The cutoff line implies that only risks that lie above the line will be
given further attention.
IX.Risks that fall below the line are re -evaluated to accomplish
second -order prioritization.
X.A risk factor that has a high impac t but a very low probability of
occurrence should not absorb a significant amount of management
time.
XI.All risks that lie above the cut off line must be managed.munotes.in
Page 160
160XII.The column labeled RMMM contains a pointer into a Risk
Mitigation, Monitoring and Management Pl an or alternatively, a
collection of risk information sheets developed for all risks that lie
above the cutoff.
How do we assess the consequences of a risk?
The following steps are recommended to determine the overall
consequences of a risk.
I.Determine the average probability of occurrence value for each
risk component.
II.Using figure determine the impact for each component based on
criteria shown.
III.Complete the risk table and analyze the results as described in the
preceding sections.
The overall risk exposu re RE, is determined using the following
relationship
RE = P * C
Where P is probability of occurrence for a risk, and C is cost to the
project should the risk occur.
8.7 RISK ASSESSMENT
At this point in the risk analysis process we have established a se t
of triples of the form:
[ri,li,xi]
Where r iis risk, l iis the likelihood (probability) of the risk, and x i
is the impact of the risk.
During risk assessment, we further examine the accuracy of the
estimates that were made during risk projection , attempt to rank the risks
that have been uncovered, and begin thinking about ways to control and /
or avert risks that are likely to occur.
Therefore, during risk assessment we perform the following steps:
I.Define the risk referent levels for the project .
II.Attempt to develop a relationship between each (ri, li,xi) and each
of the referent levels.
III.Predict the set of referent points that define a region of termination,
bounded by a curve or areas of uncertainty.
IV.Try to predict how compound combinations of ri sks will affect a
referent level.munotes.in
Page 161
1618.8 RISK MITIGATION, MONITORING, AND
MANAGEMENT
An effective strategy must consider three issues:
Risk avoidance
Risk monitoring
Risk management and contingency planning
High staff turnover in any organization will have a critical impact on
project cost and schedule.
To mitigate the risk, project management must develop a strategy for
reducing turnover.
Among the possible steps to be taken are
Meet with current staff to determine causes for turnover * Mitigate
those caus es that are under our control before the project starts.
Once the project commences, assume turnover will occur and develop
techniques to ensure continuity when people leave.
Organize project teams so that information about each development
activity is wid ely dispersed.
Define documentation standards and establish mechanisms to be sure
that documents are developed in a timely manner.
Conduct peer reviews of all work.
Assign a backup staff member for every critical technologist.
8.9 THE RMMM PLAN
1.A risk m anagement strategy can be included in the software project
plan or the risk management steps can be organized into a separate
Risk Mitigation, Monitoring and Management Plan.
2.The RMMM plan documents all work performed as part of risk
analysis and is used b y the project manager as part of the overall
project plan
3.Some software teams do not develop a formal RMMM document.
Rather, each risk is documented individually using a risk information
sheet(RIS).
4.Once RMMM has been documented and the project has begun, risk
mitigation and monitoring steps commence.
Risk monitoring is a project tracking activity with three primary
objectives:
1)To assess whether predicted risks do, in fact, occur
2)To ensure that risk aversion steps defined for the risk are being
properly ap plied
3)To collect information that can be used for future risk analysis. In
many cases, the problems that occur during a project.munotes.in
Page 162
162Risk information sheet
Risk ID : PO 2 -
4-32Date: 5/9/02 Prob: 80% Impact : high
Description :
Only 70 percent of the soft ware components scheduled for reuse will, in
fact, be Integrated into the application. The remaining functionality will
have to be custom developed.
Refinement / context :
Sub condition 1: certain reusable components were developed by a third
party with n o knowledge of internal design standards.
Sub condition 2: The design standard for component interface has not
been solidified and may not conform to certain existing reusable
components.
Sub condition 3: Certain reusable components have been implemented i na
language that is not supported on the target environment.
Mitigation / monitoring:
1. Contact third party to determine conformance with design
standards.
2. Press for interface standards completion; consider component
structure when deciding on interface pr otocol.
3. Check to determine number of components in sub condition 3
category; check to determine if language support can be acquired.
Management / contingency plan / trigger :
RE computed to be $ 20,200. Allocate this amount within project
contingency cost .
Develop revised schedule assuming that 18 additional components will
have to be custom built; allocate staff accordingly.
Trigger : Mitigation steps unproductive as of 7/ 1 /02
Current status :
5/12/02: Mitigation steps initiated.
Originator: D. Gagn e Assigned : B.Laster
8.10 SUMMARY
Risk identification should include identifying both threats and
opportunities. Since most risks are interrelated and can affect the project in
different ways, the project stakeholders should take a broad view of
projec t risks.
Risk assessment allows the project stakeholders to determine what
risks require a response. The goal of project risk management is not to
avoid each and every risk at all costs, but to make well -informed
decisions as to which risks are worth ta king and which risks require a
response. A well informed decision requires an analysis of the probability
of a particular risk occurring and its likely impact.munotes.in
Page 163
163Risk strategies define how the project stakeholders will respond to
risk. It include (1) accep ting or ignoring the risk (2) avoiding the risk (3)
mitigating or reducing the likelihood and / or impact of the risks , and (4)
transferring the risk to someone else.
Once the risk response plan has been completed and the project is
underway, the various risks identified must be monitored and controlled.
This process should include vigilance on the identified and unidentified
threats and or opportunities. As these risks present themselves, project risk
owners should make resources available and respond to risk in an
appropriate manner, as outlined in the risk response plan.
Risk evaluation provides a key to learning and identifying best
practices. A formal and documented evaluation of a risk response or
episode can help an organization evaluate its entire risk management
approach and provide insight for future project teams that may have to
deal with a similar risk in the future.
Sample Questions:
1)What is project risk?
2)What is project risk management?
3)What is the purpose of risk analysis and assessment?
4)What is risk monitoring and control?
5)Why can identifying IT project risks be difficult?
6)Discuss the risk strategies?
Reference Books:
1.Software Engineering, 5thand 7thedition, by Roger S Pressman,
McGraw Hill publication.
2.Managing Information Technology Project 6thedition , by Kathy
Schwalbe , Cengage Learning publication.
3.Software Engineering 3rdedition by KK Agarwal , Yogesh Singh ,
New Age International publication.
4.Information Technology Project Management by Jack T Marchewka
Wiley India publication.
5.Software Engineering for students: A Programming Approach by
Douglas Bell, Pearson publication.
6.Software Engineering Project Management by Richard H. Thayer
Wiley India Publication.
munotes.in
Page 164
164Module VII
9
PROJECT IMPLEMENTATION PLAN AND
CLOSURE
Unit Structure
9.0 Objective
9.1 Introduction
9.2 Project Implementation
9.2.1 What is project Implementation?
9.2.2 Key factors of successful project implementation
9.2.3 Methods of project implementation
9.2.4 Process of project implementation
9.2.5Approaches of project implementation
9.3 Closure
9.3.1 Reasons for Project Closure
9.3.2 Why are projects not properly closed?
9.3.3 Problems of improper project closure
9.3.4 Project Closure Process
9.3.5 Administrative Closure
9.1 OBJECTIVE
After studying this particular chapter, you will be able to understand
How to prepare project from start to end?
Understand the activities taken up for implementation.
Understand the need to carry out project closure.
Discuss the problems that may arises if prop er project closer is not
carried out.
Assess the activities needed to be performed to close a project.
9.1 INTRODUCTION
When we handled a particular project we consider that the project
must be perfect and run without any interruption or any error. For r unning
the project without error/mistake detailed step -by-step process required.
There are four phases i.e planning, building, implementation and closure
determine the aspect of project.munotes.in
Page 165
165Project implementation is a stage where all actions are takes place
which mentioned in planning. In implementation project details and
coordination of team is most important. For obtaining the outcome
accurate, exact resources also required. The project implementation phase
has two basic functions: execution of work and pro per delivery In closure
all activities are finalized before delivering the project to customer.
Closure activity can be done after successful completion of project or due
to any interruption in project.
9.2 PROJECT IMPLEMENTATION
9.2.1 What is project Im plementation?
Project Implementation means putting the project into action.
It will carry out the phases like execution, monitoring, control and
production.
In project implementation decided structures are executed and their
analysis done later on.
The suc cess of the project is determined by proper monitoring and
feedback process.
9.2.2 Key factors of successful project implementation
The plan prepared in planning phase execute with proper action plan to
achieve goal.
To know about each and every step in d etail prepare documentation.
Communication must be carried out to determine the success and
failure factors of the project.
If prepared plan is failed due to some unknown factors, then take quick
decision to change it.
Form a consensus about the changes an d implement immediately.
9.2.3Methods of project implementation
Following are the various methods of project implementation -
1.Critical Chain Method
In this method actual result is compared with expected result.
If the expected result is not shown, then so metimes plan or goals needs
to be changed.
To implement this, we can use the following tools: -
Kick-off phase
Staff meeting
Problem solving
Review meeting
Risk analysis
2.Extreme Project Management
This method is used to handle complex project or the proj ect which not
provide certain output.
It uses the approach of Extreme Programming where phases are not
fixed as well as activities are also not to fixed.
This implementation focus on human factor rather than phases.munotes.in
Page 166
1663.Critical Path Technique
It is used to te ll that how the project activities are schedule or planned.
In this path from start to end is setup and if that path is long then
analysing will done to understand what are the critical task involve in
it.
If some task might not complete with in given time period, they will
come under scrutiny.
This technique is used for those projects where deadline matters.
4.Program Evaluation and review technique(PERT)
This technique was developed for optimizing efficiency.
Program evaluation is systematic approach for c ollecting, analysing
and using information for project.
PERT helps in scheduling and coordinating all task required in project.
PERT helps in increasing use of resources.
Long term project used this technique.
5.Agile Method
In this method we identify the r equirements and find solution to
complete them.
In this set of principles that are depends upon value centred approach.
In this method project divided into short sprint with planning and
improvement.
This technique used for multiple iterations.
The techni ques used for agile methods are Scrum, DSDM, Kanban,
FDD
6.Classic Technique
This is one of the simplest way of managing and implementing
projects.
This method mentioned the plan for activities held in future and
suggest task to complete them.
It also sugge sts some resources those can full fill the activity.
To obtained quality feedback was taken and activities were monitor to
achieve deadlines.
9.2.4 Process of project implementation
For successful project, all the necessary steps are taken as preca utions.
The delivery of the project means giving out a final product of your
work.
The project management includes mapping out the idea, processing
the project, analysing the outcomes, discussing the project, and finally
executing the outcome.
Along with this risk mitigation and success probabilities are also
checked.
Before presenting the idea to customer we should know background
and views about them because every customer is different.
Project Implementation Steps are as follows:munotes.in
Page 167
1671. Have a firm eye on the process and the budget
In the implementation phase, it is crucial to look at the bigger picture.
There is various project monitoring software to ensure that the
management focuses on the end -goal and is not engulfed in petty,
unimportant details.
It is also essential to respond quickly to changes at every step of
execution and have the entire team on -board to implement these.
Have an explanation in place for overriding costs that spurt in the last
stages. These might be to adhere strictly to the schedu le or
unaccounted inflationary pressures.
The processes involved in the whole project may exceed costs, or there
might be some problems during the management phase. The team may
get distracted with unwanted suggestions and may not focus on the
project’s ma intarget .
So supervising the overall activities and keeping track of the
happenings is necessary.
2. Prepare Reports along the way
In the implementation phase, the stakeholders business demand
updates and status report always. Being up -to-date with the progress
and documenting it neatly comes in handy to present the statistics to
the stakeholders at any point in time.
While yo u execute the project idea to the clients or stakeholders, you
have to be mentally prepared for all the queries raised. They may ask
about a minor aspect and small proceedings of any of the preparation
phases.
The project presenter should be ready with all the recorded data during
the initial stages, like planning and building up.
To avoid any trouble during the implementation, start making reports,
and collect data from day one. Hence you will be prepared with the
data that will act as your backup strategy .
3. Hold periodic meetings regularly
Looking at the bigger picture, the person might get lost along the way
and falls off the track.
To ensure that everyone is on the same page with the progress, it is
essential to hold general and specific meetings within smaller groups.
Keep an eye on production numbers and revenue goals in agenda
meetings.
This step is crucial to maintain team spirit. The project is not a one -
person job. Instead, several hands are needed to make it successful.
Without a team effort, the project would lack strength.
So regular meetings will also encourage sharing ideas, feedback on
ongoing proceedings, and brainstorming sessions .munotes.in
Page 168
1684. Rekindle enthusias m in the working personnel
It is necessary to review progress along the way; it is equally important
to successfully reward the staff to complete small and big targets.
Performance Review is an essential aspect of the Project
Implementation phase.
It accounts for a significant part of enhancing individual productivity
that aids the overall performance in the long run.
5. Resolve Issues at the initial stage
At this crucial stage of p roject implementation, resolving issues as
soon as or before they emerge becomes hugely significant.
Paying attention to details, loss of team enthusiasm, scope creep, or
dip in the quality should be tackled as soon as it begins to appear.
This early respo nse to stress leads to a smoother implementation .
9.2.5 Approaches of Project Management
1.Waterfall model
It is traditional approach to project management.
It uses sequential o r linear approach to develop project.
The project is broken into sequence of task.
2. Agile Approach
It uses iterative development approach.
Agile basically means respond to change and it providing changes in
all type of organisation.
This approach is us ed to provide qualitative product in given time
period.
3.Scrum Approach
It shows the progress in project by making the use of cycles.
The activities start by sprint master and he remove all obstacles.
Scrum is a framework that helps teams to work togeth er.
4. Kanban
It is a popular framework to implement agile and DevOps Software.
This approach manage work by balancing demands with available
capacity.
It requires full transparency of work.
5. Scrum ban
It is an agile development methodology which is hy brid of Scrum and
Kanban.
It provides the structure of Scrum with the flexibility and visualization
of Kanban.
It will provide flexibility to adapt to stakeholder and production needs
without feeling overburdened by their project methodology.munotes.in
Page 169
1696.Extreme Pr ogramming
It is also agile development framework.
It produces higher quality software to fulfil customer needs.
XP is the most specific of the agile frameworks regarding appropriate
engineering practices for software development .
7.Adaptive Project Frame work
It is also known as adaptive Project Management.
It is going to accommodate unknown factors that can crop up during
the project.
It will manage the complexity in case of uncertainty.
8.Lean methodology
It is based on elimination all forms of waste a nd increase customers
perceived.
It is a way to optimize people, resources, efforts and energy.
It is based on continuous improvement and respect for people.
Along with the above approaches project implementation also
having the following three approache s-
1.Direct cutover -
In this old system is shut down and new system start.
This approach is used when existing system is not performing the
functions and require to replace by new system.
In this if system fails it does not show major impact on business.
2.Parallel cutover -
As the name suggest this approach allow old and new system to run
concurrently on time.
This approach is used when failure of system shows major impact on
business.
It provides confidence that before relying on new system it works
efficien tly.munotes.in
Page 170
170
3.Phased
This approached is used to introduce software system to different areas
of the organisation.
Example -accounting information system package by first
implementing the general ledger component, then accounts payable
and accounts receivable, and finally payroll.
9.3CLOSURE
Every project must come to an end sometime or other. The project
manager decides which is the suitable time to close the project. Once it is
decided then project manager check that project is close by using proper
projec t closure activities. This is the last phase of project life cycle.
Project closure also involves handover project to customer, passing
documentation to business, release staff working on that project, inform
stockholders about closure.munotes.in
Page 171
171Projec t closure activities can broadly have divided into
Administrative Closure and Contract Closure.
Administrative closure insure that all project deliverables are
achieved. In contract closure all terms of the contacts with customer are
verified to check all requirements are met and satisfactory closed.
In case of multiphase project various closeout activities may have
carried out at the end of every phase.
9.3.1Reasons for Project Closure
There are two main reasons to close the project
1.All the stated g oals are successfully completed.
2.Project is unlikely to achieve its stated objectives and has to be
prematurely terminated.
Most of the time the manager tries to close the project by satisfying
all goals successfully. There can be many reasons for prematu rely
terminating a project. A few important reasons for project termination are
as follows:
1.Lack of resources -
A project may have terminated due to shortfall of resources.
Resource shortfall includes change of priority, financial strain on
company, bankru ptcy of company, change in management of
company.
2.Changed business need of customer -
Customers stated requirements quite change after initiation of the
project.
This make the outcome not useful in that situation
Example -Customer initially told to prepare inventory management
software and later on decides to outsource its entire inventory
management activity to third party.
3.The perceived benefits accruing from project no longer remain
valid -
The expected time period of obtaining benefit from project may al ter.
During implementation of the particular software some competitor
may launch similar type of software in market.
4.Changes to the regulatory policies -
External factors such as government policies can have the adverse
effect on the project and due to that project needs to be terminated.
5.Key terminology used in the project becoming obsolete during
project execution -
Software is being developed based on co re technology.munotes.in
Page 172
172Those technologies get outdated before the project completes. Then,
there may be reason for terminating project.
6.Risk become high -
Even after project have been carried out throughout the risk,
sometimes the risk become so high that project could have adverse
effect on the company.
Impact will be shown such as unsettling its financial soundness,
inviting negative publicity, safety hazards.
9.3.2Why are projects not properly closed?
Here we are considering some of the reasons as why project closu re may
be delayed or not be properly closed.
1.Lack of interest by project team -
Project closing activity require some creativity, the project team may
loss interest to participate in these activities.
Sometimes project team members already start working on other
project so they have no interest in earlier project.
Team members also be reluctance on part of project which require
redeployment after project gets closed.
2.Emotional factor -
After working on the particular project team members and project
manager may become emotionally attached to project and they want
the project to continue as long as possible.
3.Indecision regarding project closure -
Often some tough decisions are required to be taken by project
manager or senior manager to solve the problems aris es in the project.
If they are not able to take the decision on time, then premature
termination of the project carried out.
4.Underestimation of how fast know -how can get lost and how much
implicit knowledge exist with team member -
Team members working on that project build up significant knowledge
on that project.
It is often underestimated by stakeholders as how much knowledge
pertaining to project exist with team members and how fast can the
knowledge decay and get lost.
9.3.3Problems of improper project clo sure
When the project is not closed in appropriate time period several
problems can arise. Some of the important problems that may be faced
include the following:
1.Time and cost overrun -
If the time period for the project is delay, then cost runs up expend iture
in the meanwhile leading to cost overrun.
If the time exceed then project shows no value.munotes.in
Page 173
1732.Locking up valuable human and other resources -
When project closing is delay then redeployment and other resources
gets delayed.
As a result, valuable resources and manpower that can used in other
project gets wasted.
3.Stress on project personnel -
The person who is appointed on particular project having experience
about projects that they deploy.
The team members will be stressed if they are not doing anythin g
challenging, missing out learning opportunity etc.
9.3.4 Project closure process
To perform the project closure activity, it requires to carry out
certain steps. If project facing termination problem, then manager will ask
top management and customer t hat whether they want to continue it or
stop it.
The following are the steps that are consider for project closure process -
1.Getting client acceptance -
Client acceptance mechanism varies project to project.
If the client is internal, then acceptance tends to informal.
If the client s external, then acceptance obtained from formal contract
process.
In formal contract acceptance done by the client and sometime written
acceptance is also required.
2.Achieving project deliverable -
Now a day’s emails are used to send the documentation so we can
easily retrieve the documents.
Project achieved should be properly documented so that if we required
it in future then problems will not arise.
Document used as deliverable should contain information regarding
description o f documents, application, stored location, contact
information of person.
3.Performing Financial Closure -
Every project will start only after financial grant is approved.
Grant may consider the components such as capital and contingency
budget.
Before closu re we have to check all payments are completed and have
been reconciled.
4.Post implementation project review -
It is called as post -mortem because it is used to perform critical
analysis so that we can improve and avoid mistakes in future.
Following are som e of the steps for conducting post implementation
project review -munotes.in
Page 174
1741.Conduct project survey -
The main goal of project survey is to collect various types of
information regarding project.
Questionnaire is design to collect the information. Following points
are including in questionnaire -
Project performance
Administrative performance
Organizational structure
Team performance
Techniques of project management
Risk management
2.Collection of objective information -
It is most critical aspect of project where we stu dy about various
metrics.
Real data helps to focus discussion on critical issues during post
implementation process.
The metric which used to collect information are cost metric, schedule
metric, quality metric.
3.Debriefing meeting -
It is preparatory meeti ng that helps to make final project review
meeting focused on most relevant aspects.
The main purpose of meeting is to check what was successful and
what was not.
4.Final project review -
This review basically include issues of project planning and tracking,
results of various development phase, specification in design and
testing.
5.Project closeout report -
This report shows the result obtained from various project closeout
task.
It also contains recommendation for improvement to be used by other
project o f similar size and scope.
It includes the following things -
Project description
What worked well
The factors that impeded the performance of the project.
A prescription for other projects to follow.
6.Releasing Staff -
This is final step of project closeo ut process.
This step tells about meeting before the team members disperse to
different project and recognizing exceptional performance by the team
members and recognizing the experience.munotes.in
Page 175
1759.3.5Administrative Closure
As we know that project closure activity broadly divided into
administrative closure and contact closure.
The definition provided by Gray and Larson following are five
circumstances for ending the project -
1.Normal -
When all the requirements of the project complete then normal closure
perform.
Innormal closure cost, quality and scope are handled properly.
2.Premature -
Premature closure occurs when project is pushed forcefully in early
completion even though not completed its functionality.
3.Perpetual -
This closure is basically known as runaway proj ects.
This project is result from delay or scope which is not clearly
mentioned.
4.Failed -
Projects are not able to complete its defined requirements, then it
failed.
Due to failure of project it shows effects on cost factor.
5.Changed priorities -
Sometime p roject may have terminated due to some policy changed
made in requirements.
In this even though the project is never closed officially resources are
released and assign to some other project.
As we consider that the project closure must done normally but
unfortunately if project not closed normally then project manager and
team should prepare for the following reality
Team members are concerned about future jobs
Bugs still exist
Resources are running out
Documentation attains paramount importance
Promise d delivery dates may not be met
The players may possess a sense of panic
Summary -
Project implementation is the phase where we bring visions and plan
in reality.
After completing requirement analysis project implementation starts.
Project manager conduct project implementation activity.munotes.in
Page 176
176The deliverable for your project provide all product and services that
you provide to customer.
Once the information system has been built or purchased, it must be
tested adequately in order to make installation of the syst em go more
smoothly.
Three approaches to implementation were discussed in this chapter.
Thefirst approach, called direct cutover, provides the quickest means
for implementing the system.
The parallel and phased approaches are less risky alternatives,
although implementation may take longer.
The phased approach may be appropriate when implemen ting an
upgrade or modular system in different departments or at different
geographical locations.
Once the information system has been implemented, the project
manager and team must plan for an orderly end to the project.
Projects can be terminated for a variety of reasons. If project scope is
complete then project complete under normal condition.
A useful way to gain acceptance is the development of a final project
report.
This report provides a history of the project and outlines how each
deliverable was completed and meets the standards of the client or
sponsor.
The report should also address any open items or issues so that they
can be completed within a reasonable time.
This report can serve as a foundation for the project team’s final
meeting with and presentation to the key stakeholders of the project.
In this chapter we discussed with various reasons of closing project
and problems of improper closure.
In this chapter we also discussed with process of closure.
Self-Learning Topics : Ethics in Projects, Multicultural Projects
References -
Information Technology Project Management by Jack T Marc hewka
Wiley India publication.
Software Project Management by Bob Hughes Mc GrawHill
publication